Delivery Order INR12PC20255-INR14PD00483

Award Date 6/10/14
Potential Completion Date 9/30/14
Potential Value $114K
Ultimate Awardee
Not listed
Federal Contract Vehicle
Set-Aside Type
No Set-Aside Used
Extent Competed
Full and Open Competition
Major Defense Program
Not listed
Pricing Type
Firm Fixed Price
Place of Performance
Sacramento, CA 95826, USA
Solicitation Procedures
Multiple Award, Fair Opportunity
Number Of Offers Received
3
Legislative Mandate
Not listed
National Interest Action
Not listed
Research Type
Not listed
Primary Consortia Member
Not listed
Similar Awards
The Department of the Interior Bureau of Reclamation awarded a $744,000 firm fixed price contract to Precision Water Resources Engineering, LLC for the Lahontan Basin Area Office Truckee Canal Losses Study. Under the contract, Precision Water Resources Engineering will develop an updated statistical method for estimating losses in the Truckee Canal by reviewing previous studies, developing a draft method incorporating new streamgage data, and documenting the final Bureau-approved method. The...
This is a $6,693,301.52 firm-fixed-price delivery order contract awarded by the Bureau of Reclamation's Lahontan Basin Area Office (LBAO) to Stantec Consulting Services Inc. for a Tahoe Dam Replacement Feasibility Study. The contract has been extended by 20 months, with a new ultimate completion date of May 31, 2027. As the prime contractor, Stantec will lead the feasibility study, which includes services such as economic analysis, alternatives evaluation, hydrologic analysis, and formulation of...
The Department of the Interior Bureau of Reclamation awarded a $374,000 purchase order to River Focus, Inc., doing business as River Focus Inc., to provide hydrologic and hydraulic analysis services in support of the Truckee Basin Water Management Options Pilot study. The contractor will update rain and snowmelt flood frequency curves, calibrate and validate hydraulic models, develop a synthetic incremental flow hydrograph, and identify channel capacity and breakout points. This requirement...
The Department of the Interior Bureau of Reclamation (DOI) awarded a $2,398,645.23 firm fixed price definitive contract to Syblon-Reid CO., doing business as Syblon-Reid Co., to reconstruct portions of the Folsom South Canal (FSC) bank that have experienced slope failures due to bank saturation. The goal of the project is to restore the canal to its original operational condition at the location on the FSC in Rancho Cordova, California. The period of performance for reconstruction services is...
This is a firm fixed-price delivery order awarded by the Federal Highway Administration, a civilian agency, to CH2M Hill, Inc. for $2,406,467.95 to prepare 100% plans, specifications, and estimates for the CA FLAP SR89(1) Truckee River Bridge project. The order was placed under an existing contract vehicle and does not have a set-aside designation. Key subcontractors include Arrowtrenchless for other transportation support activities, Andregg Geomatics for surveying and mapping, and Shannon...
This firm-fixed price construction contract was awarded by the U.S. Army Corps of Engineers' Sacramento District to Michels Construction, Inc., a large for-profit Subchapter S Corporation, to complete Phase 2 of the Tule River/Success Lake Spillway Enlargement Project. The $43,082,582.47 contract involves constructing a 10-foot high, 350-foot long reinforced concrete ogee weir across the Success Lake spillway, as well as related civil engineering work such as excavation, rock anchoring, and...
The Army Corps of Engineers Engineering District Sacramento awarded Shimmick Construction Company, Inc. a $970,900 firm-fixed-price contract to complete Phase 2 of the Tule River/Success Lake Spillway Enlargement Project in Porterville, California. The scope of work involves constructing a 10-foot high, 350-foot long curved reinforced concrete ogee weir across Success Lake spillway, as well as associated side walls, a downstream apron, spillway widening, excavations using blasting and equipment,...
This is a $1,337,348.65 firm-fixed-price delivery order contract awarded by the U.S. Army Corps of Engineers to the HDR GEI Joint Venture, a partnership between HDR, Inc. and CH2M. The contract is for the preparation of water control manual update management plans for multiple dams in the Truckee River Basin in Nevada and California, as well as the Pine Flat Dam and Lake on the Kings River and the Buchanan Dam-H.V. Eastman Lake on the Chowchilla River in California. The contract is a task...
This is a definitive contract awarded by the U.S. Department of the Interior's Bureau of Reclamation to BWI Tpc, A Joint Venture, for the FKC Middle Reach Capacity Correction Project Phase 1 in Lindsay, California. The $186,812,234.67 firm-fixed-price contract involves constructing approximately 19 miles of new concrete-lined canal, 12 miles of concrete lining and embankment raise along the existing Friant-Kern Canal, and associated infrastructure such as siphons, check structures, and pump...
This federal contract award, valued at $78,674.41, was issued by the Federal Highway Administration (FHWA) to Atlas Technical Consultants (Ca), Inc., a for-profit organization that specializes in construction inspection and support services for federal transportation infrastructure projects. The contract, awarded on January 8, 2019, is a firm-fixed-price delivery order under a larger Indefinite Delivery/Indefinite Quantity (IDIQ) contract that Atlas holds with the FHWA, valued at up to $69.975...
  • INR12PC20255
    Indefinite Delivery Contract
  • INR12PC20255-INR14PD00483
    Delivery Order

TRUCKEE CANAL BREACH ANALYSIS

Posted 6/10/14, 12:00 AM