Recovery, fire island national seashore, design services for predesign, schematic design and design-build request for proposal development, replace patchogue bulkheads and complete ferry terminal…
Ended Awarded Last action
- Contract number
- INPT2011091537
- Awardee
-
Bargmann Hendrie + Archetype, Inc. UEI GLDTL4UAREF8
- Awarding agency
-
National Office
National Park Service, Department of the Interior
- Obligated
- $49,723
Award facts
- Contract value 100% obligated
- $49,723.22 Current and potential, with all options
- Completion date 100% complete
- Current and potential, with all options
- NAICS code
- 541310 Architectural Services
- Set-aside
- No set-aside
- Competition
- Competitive Delivery Order · 4 offers Negotiated Proposal / Quote
- Pricing
- Firm Fixed Price
- Place of performance
- Patchogue, NY 11772, USA
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Original award | $49,723 |
About this award
This federal contract award, with ID INP09PC60860|INPT2011091537, was issued by the National Park Service (NPS) to the prime contractor Bargmann Hendrie + Archetype, Inc. for design services related to the replacement of approximately 2,000 linear feet of failed or deteriorating timber bulkhead at the Fire Island National Seashore headquarters in Patchogue, New York. The contract, valued at $49,723.22 on a firm fixed-price basis, requires the prime contractor to provide predesign, schematic design, and design-build request for proposal development services to assist the government in preparing for a future design-build construction contract. This award is not associated with a set-aside program.
Description
Recovery, fire island national seashore, design services for predesign, schematic design and design-build request for proposal development, replace patchogue bulkheads and complete ferry terminal building. The architect-engineer design firm will assist the government in developing a schematic design for replacement of approximately 2,000 linear feet of failed or deteriorating timber bulkhead at fire island national seashore headquarters in patchogue, NY. The schematic design will be used in the solicitation of a design-build construction contract for completion of design and actual construction associated with the project.
Quick answers
Who was awarded contract INPT2011091537?
INPT2011091537 was awarded to Bargmann Hendrie + Archetype, Inc. by National Office (National Park Service) on July 16, 2009.
How much is contract INPT2011091537 worth?
The government has obligated $49,723 on INPT2011091537.
Is contract INPT2011091537 an order under another contract?
Yes. INPT2011091537 is a delivery order under INP09PC60860, an indefinite delivery contract.
Was contract INPT2011091537 competed?
The extent of competition for INPT2011091537 was competitive delivery order. The government received 4 offers.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award