Delivery Order INP09PC60858-INPT3400100147
Award Date 9/16/10
Potential Completion Date 1/22/11
Potential Value $42K
Federal Agency
Awardee
Ultimate Awardee
Not listed PSC Category
Not listed Federal Contract Vehicle
- Not listed
Set-Aside Type
No Set-Aside Used
Extent Competed
Full and Open Competition
Major Defense Program
Not listed Pricing Type
Firm Fixed Price
Place of Performance
Washington, DC 20242, USA
Solicitation Procedures
Multiple Award, Fair Opportunity
Number Of Offers Received
1
Legislative Mandate
Davis Bacon Act
National Interest Action
Not listed Research Type
Not listed Primary Consortia Member
Not listed Similar Awards
- The Department of the Interior National Park Service National Office awarded a $112.76 million firm fixed price contract to Cianbro Corporation. The contract is for design-build services to rehabilitate approximately 6,400 linear feet of historic seawalls located within the National Mall and Memorial Parks in Washington, D.C. Key requirements under the contract include rebuilding the seawalls to their historical functional height, reusing existing historic stone where possible, and providing for...
- The Department of the Interior National Park Service National Office awarded a $411,201 firm fixed price contract to CMR Construction & Roofing, LLC for roof repairs to the Annex 1 building at Fort Lesley J. McNair in Washington, D.C. The contract is set aside for total small businesses. Under the terms of the award, CMR Construction & Roofing will perform roof repairs, replacing terracotta roof tiles and wood sheathing, restoring gutters and insulation, and installing a catwalk. The...
- This firm fixed price purchase order was awarded by the Department of the Interior National Park Service National Office to The Tradesmen Group, LLC for $663,208.60. The contract calls for exterior repairs to the National Park Service property located in Southeast Washington, D.C. Specifically, the contractor will fully replace the slate shingled roof on the main building and garage with new aluminum gutters and downspouts. Additional repairs include work on porticos and atrium roofs, repainting...
- <p>This is a $95,147.97 fixed-price level of effort delivery order contract awarded by the National Park Service to Hord Coplan Macht Inc. for Title III services to restore the DC War Memorial on the National Mall in Washington, DC. The contract does not have a set-aside designation and the work must be completed by December 15, 2011. This contract is associated with NAMA-150359, a larger project to restore various National Mall and Memorial Parks sites.</p>
- The Department of the Interior National Park Service National Office awarded a $421,301 definitive contract to Matos Builders LLC. The firm fixed price contract calls for the installation of fire protection and security systems at the historic Peirce Mill Barn located in Rock Creek Park, Washington D.C. Specifically, Matos Builders will install a new sprinkler system, fire alarm system, intrusion detection system, and associated infrastructure improvements. The solicitation sought proposals from...
- The Department of the Interior National Park Service awarded a $272,195 firm fixed price contract to Mission Contracting Inc. to replace the roof on the Buckeye Building within the National Mall and Memorial Parks in Washington D.C. The contract is being carried out under a total small business set-aside. Per the original solicitation, the work involves removal of the existing metal roof system and installation of a new roof deck, polyiso insulation board and single-ply TPO or EPDM membrane. The...
- This is a $129,414,686 design-build construction contract awarded by the U.S. Army Corps of Engineers (USACE) Baltimore District to Grunley Construction Co., Inc. to upgrade existing windows, doors, and the cityscape for a secured federal building located on the National Mall in Washington, D.C. The contract has a completion date of October 3, 2027. This procurement was not set aside for any special type of business. Key subcontractors include Mac-Plants Inc. for landscaping, D2 LLC for...
- The Department of the Interior National Park Service National Office awarded a $1.7 million firm fixed price contract to Terra Site Constructors LLC for interim stabilization of the Southside Prism wall in Washington, D.C. The contract has an 8(a) sole source set aside designation. Under the award, Terra Site Constructors will perform installation of wall stabilization including concrete footings, steel H-piles, lagging, and backfill with stone to restore the site upon completion of work....
- F.l. Pinto Companies, LLC doing business as PWC Builders was awarded a $533,000 firm fixed price delivery order to replace existing standing seam sloped roofs, split system HVAC system and rooftop units, and complete electrical upgrades including an automatic transfer switch for the National Park Service National Office in Washington, D.C. The funding agency, the Department of the Interior National Park Service National Office, issued the delivery order under the Multiple Award Maintenance and...
- The Department of the Interior National Park Service National Office awarded a $183,272 firm fixed price delivery order to The Tradesmen Group, LLC for maintenance of Virginia Avenue statuary in the National Mall and Memorial Parks. The order was issued on July 12, 2022 under an indefinite-delivery/indefinite-quantity contract vehicle and has a completion date of May 31, 2023. No set-aside provisions were applied to this award for conservation and maintenance services at Fort Lesley J. McNair in...
- INP09PC60858Indefinite Delivery Contract
- INP09PC60858-INPT3400100147Delivery Order
NATIONAL MALL AND MEMORIAL PARK, STABILIZE EXTERIOR PORTICO CEILING OF EAST POTOMAC PARK CLUBHOUSE, DISTRICT OF COLUMBIA COUNTY, WASHINGTON, DC
Posted 9/16/10
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| Not listed | Not listed | $42.1k | 9/16/10 |