Crater lake national park, oregon, rehabilitate historic cafeteria (1928 building), predesign and schematic design services, crla 077366

Ended Awarded Last action

Contract number
INP08PD76480
Awardee
Awarding agency
Obligated
$603,103

Award facts

Contract value 100% obligated
$603,103.41 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
NAICS code
541310 Architectural Services
PSC
C219 Architect And Engineering- General: Other
Set-aside
No set-aside
Competition
Full and Open Competition · 1 offer Architect-Engineer FAR 6.102
Pricing
Firm Fixed Price
Place of performance
Seattle, WA 98102, USA

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope 12 · Crla 162722 this modification will extend the completion date to october 31, 2014 for the rehabilitate historic cafeteria (1928 building) and rehabilitate… $0
Supplemental Agreement for work within scope 11 · Crla 162722 this modification will add architectural renderings to the scope of services for the rehabilitate historic cafeteria (1928 building) and… $16,839
Supplemental Agreement for work within scope 10 · Crla 162722 this modification will extend the period of performance from february 21, 2014 through may 30, 2014 for the rehabilitate historic cafeteria (1928… $0
Supplemental Agreement for work within scope 9 · Crla 162722 this modification will provide for additional and revised schematic design for the `rehabilitate historic cafeteria (1928 building)rehabilitate… $63,152
Other Administrative Action 8 · Crla 162722 & 129663 change of contracting officer $0
Change PIID 7A $0
Supplemental Agreement for work within scope 7 · Extend period of performance for predesign and schematic design services for the 'rehabilitate historic cafeteria (1928) building' project at crater lake… $0
Supplemental Agreement for work within scope 6 · Additional schematic design services for the 'rehabilitate historic cafeteria (1928 building)' project , crater lake national park, oregon, crla 162722… $112,001
Change Order 5 · Additional design options and miscellaneous meetings, crater lake national park, oregon, rehabilitate historic cafeteria (1928)building, predesign and schematic… $34,849
Supplemental Agreement for work within scope 4 · Extension of completion date from march 31, 2010 to june 30, 2010 for task order T2011080542 for predesign and schematic design services for the 'rehabilitate… $0
Other Administrative Action 3 · Modification 3 for this task order is to change the acccount number for an amount of $3,484.90 from 9324-0902-M8B to 9320-1001-471. $0
Change Order 2 $34,849
Change Order 1 $0
Original award $341,413
Show all 14

Quick answers

Who was awarded contract INP08PD76480?

INP08PD76480 was awarded to Leavengood, David Architect by National Office (National Park Service) on September 25, 2008.

How much is contract INP08PD76480 worth?

The government has obligated $603,103 on INP08PD76480.

Is contract INP08PD76480 an order under another contract?

Yes. INP08PD76480 is a delivery order under INP08PC60729, an indefinite delivery contract.

Was contract INP08PD76480 competed?

The extent of competition for INP08PD76480 was full and open competition. The government received 1 offer.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award