Complete archaeology study phase II and III promulgated by the division of louisina office of cultural development

Ended Awarded Last action

Contract number
VACFM050876
Awardee
Awarding agency
Obligated
$3,029,277

Award facts

Contract value 100% obligated
$3,029,434.29 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
NAICS code
541620 Environmental Consulting Services
PSC
B503 Special Studies/Analysis- Archeological/Paleontological
Set-aside
No set-aside
Competition
Full and Open Competition · 1 offer Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Greenville, SC 29615, USA
National interest action
Hurricane Katrina 2005

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Close Out SA036 · Deobligation for closeout -$137,195
Supplemental Agreement for work within scope SA035 · Slvhcs- extend POP, definitize change orders and deobligate funds -$21,085
Supplemental Agreement for work within scope SA034 · Slvhcs- extend POP and name change $0
Supplemental Agreement for work within scope SA033 · Slvhcs- definitize CO-017 and CO-020 $158,420
Supplemental Agreement for work within scope SA031 · Slvhcs- definitize CO-016, 019 and 021 $109,140
Supplemental Agreement for work within scope SA032 · Slvhcs- to provide recap report for the building 8 (definitizes CO-10) $36,197
Change Order CO022 · Removal of usts at dixie $25,000
Change Order CO021 · Removal and disposal of petroleum-based product at dixie $99,000
Supplemental Agreement for work within scope SA030 · Slvhcs- to provide services for reviewing required submittals, report reviews and preparation (on behalf of the VA), reviewing draft reports (prepared by… $20,854
Change Order SA029 · Plug and decommission abandoned well at dixie building. Defnitizes CO-018. $24,452
Change Order CO020 · Delineate soil contamination at dixie building. $25,000
Change Order CO019 · Removal/disposal of contaminated waste located under the foundation of the dixie building. $95,000
Change Order CO018 · Plug and decommission abandoned well at dixie building. $32,497
Supplemental Agreement for work within scope CO016 · Evaluate soil discrepancies at dixie building. $10,000
Supplemental Agreement for work within scope CO017 · Removal/disposal of contaminated water/sludge at dixie. $10,000
Change Order CO015 · Incorporate safety reporting requirements $0
Supplemental Agreement for work within scope SA028 · Hazardous waste drum sampling and removal at dixie building. $33,967
Change Order CO014 · Remove drums in the dixie building as per modification. $20,000
Supplemental Agreement for work within scope SA026 · Provide all labor, materials, equipment and necessary to perform the following changes in work. Aecom to provide oversight of the demolition, asbestos… $55,264
Other Administrative Action SA027 · Administrative modification being issued pursuant GSA modification p-0014 to change aecom GSA environmental schedule GS-10F-0115K. This contract action… $0
Supplemental Agreement for work within scope SA025 · The purpose of this modification is to collect additional native soils from the dixie brewery site. Three samples from various depths at each sample location… $21,944
Change Order CO013 · The removal and disposal and post disposal testing for safety and environmental. $10,000
Supplemental Agreement for work within scope SA24 · Furnish all materials, equipment and personnel to monitor vibrations at dixie brewery during horizontal drilling operations. $9,698
Supplemental Agreement for work within scope SA023 · No cost MOD - add time to contract. $0
Supplemental Agreement for work within scope SA022 · Sub-slab investigations at dixie brewery via horizontal drilling $33,057
Supplemental Agreement for work within scope CO012 · Finalize ldeq sicar letter and MO3 work plan for pan am $52,206
Supplemental Agreement for work within scope SA021 · PCB investigations at pan am. Finalization of investigation and remediation. $84,472
Supplemental Agreement for work within scope CO011 · Sampling and analysis according to approved soil reuse permit and provide report to VA showing sampling results. $32,933
Supplemental Agreement for work within scope SA020 · Archaeological field site investigations block 554 $85,911
Supplemental Agreement for work within scope SA018 · Field archaeology site investigations block 550 and 524 $75,372
Supplemental Agreement for work within scope SA019 · Archaeological field site work block 551 $90,881
Supplemental Agreement for work within scope SA008 · Contractor definitizes CO-001; finalizes recap and storm water support $135,428
Change Order CO008 · Contractor to test and analyze PCB samples at pan american building $95,000
Change Order CO009 · Contractor to provide recap report at site $95,000
Supplemental Agreement for work within scope SA017 · Contractor finslizes cost for GPR $6,730
Supplemental Agreement for work within scope SA016 · Contractor finslizes cost associated with CO-003 for tclp ampling for blocks 549 and 529 $37,723
Change Order CO010 · Contractor to provide recap report at site $95,000
Change Order CO007 · Contractor to test and analyze PCB samples at pan american building $10,000
Supplemental Agreement for work within scope SA011 $20,013
Supplemental Agreement for work within scope SA012 · Contractor definitizes CO-005; final for removal of UST $64,206
Supplemental Agreement for work within scope SA014 · Contractor to complete asbestos additional testing ten samples $2,020
Supplemental Agreement for work within scope SA010 · Contractor to investigate black GOO at dixie brewery propoertry and definitizes CO-002 $89,092
Change Order CO006 · Contractor to test and analyze PCB samples at pan american building $23,939
Supplemental Agreement for work within scope SA009 · Time extention for performance $0
Change Order CO005 · Contractor to remove UST tanks $41,000
Supplemental Agreement for work within scope SA006 · Contractor to conduct structural assessment and asbestos condition at dixie brewery $84,953
Supplemental Agreement for work within scope SA007 · Contractor to provide additional GPR support $23,772
Change Order CO003 · Contractor to provide tcip samping $71,115
Supplemental Agreement for work within scope SA003 · Contractor to complete ldeq letter for soil at the site $43,782
Change Order CO004 · Direct funding for task order to complete archaeology field investigation $95,000
Show 40 more

Latest 50 listed here. See the rest on GovTribe.

Quick answers

Who was awarded contract VACFM050876?

VACFM050876 was awarded to AECOM C&E, Inc. by VA Office of Construction and Facilities Management (Headquarters) on September 30, 2011.

How much is contract VACFM050876 worth?

The government has obligated $3,029,277 on VACFM050876. Its current value, with exercised options, is $3,029,434.

Is contract VACFM050876 an order under another contract?

Yes. VACFM050876 is a delivery order under GS10F0115K, a federal supply schedule.

Was contract VACFM050876 competed?

The extent of competition for VACFM050876 was full and open competition. The government received 1 offer.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award