Construction of energy conservation measures (ecms) at the david skaggs research center, boulder, colorado. Arra funded.

Ended Awarded Last action

Contract number
GSP0810JB5024
Awardee
Awarding agency
Obligated
$2,346,489

Award facts

Contract value 100% obligated
$2,346,488.80 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 5 offers Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Boulder, CO 80305, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope PS16 · Delivery date of contract extended to 9/17/2012. $0
Supplemental Agreement for work within scope PS15 · Delivery date extended to 8/1/2012 to provide sufficient time for completion of the energy monitoring and dashboard reporting element, and the green screen… $0
Supplemental Agreement for work within scope PS14 · Time extension to allow for advanced software configuration work for the green screen, david skaggs research center, boulder, colorado. $0
Supplemental Agreement for work within scope PS13 · This modification extends the contract delivery date from 1/31/12 to 3/30/12 to allow for multiple consecutive weekends for the replacement of electrical… $0
Supplemental Agreement for work within scope PS12 · This modification extends the delivery date of the contract form december 31, 2011 to january 31, 2011 to provide time for completion of programming wokr and… $0
Supplemental Agreement for work within scope PS11 · Time extension to allow time required to complete programming efforts in support of energy conservation measures (ECS) installation at the david skaggs research… $0
Supplemental Agreement for work within scope PS09 · Building automation system programming to correct building pressurization. $77,722
Supplemental Agreement for work within scope PS08 · Modification in lighting control sequencing, david skaggs research center, ECM construction project, boulder, CO. $824
Supplemental Agreement for work within scope PS07 · Fan programming and chiller wiring modifications, ECM construction arra project, david skaggs research center, boulder, colorado $9,444
Supplemental Agreement for work within scope PS06 · Arra funded: installation of crac units $71,556
Supplemental Agreement for work within scope PS05 · Addition of modbus panels to david skaggs research center ECM construction project, boulder, CO. Arra funded. $72,088
Supplemental Agreement for work within scope PS04 · Funding for supervision labor to cover extended time on site. David skaggs research center ECM construction project - boulder, CO. $11,200
Supplemental Agreement for work within scope PS03 · Replace worn couplers for HVAC pump motors and cooling tower motors as part of david skaggs ECM construction arra project. $40,477
Supplemental Agreement for work within scope PS02 · Lighting, plumbing, HVAC changes required for implementation of energy conservation measures at david skaggs research center. Arra funded. $99,376
Supplemental Agreement for work within scope PS01 · Modification for increase in services for energy conservation measure #10 building envelope remediation. David skaggs research center. Arra funded. $146,809
Original award $1,816,992
Show all 16

About this award

This federal contract award was made by the U.S. General Services Administration (GSA) Region 8 to PCL Construction Services, Inc., a foreign-owned, for-profit construction company. The $2,346,488.80 firm-fixed-price delivery order is for the construction of energy conservation measures (ECMs) at the David Skaggs Research Center in Boulder, Colorado. The project is funded through the American Recovery and Reinvestment Act (ARRA). No set-aside was used for this award. Based on the prime contractor's background and the nature of the work, this contract appears to be for construction and facilities management services related to improving the energy efficiency of the research center's infrastructure.

Quick answers

Who was awarded contract GSP0810JB5024?

GSP0810JB5024 was awarded to PCL Construction Services, Inc. by Region 8 (Public Buildings Service) on March 17, 2010.

How much is contract GSP0810JB5024 worth?

The government has obligated $2,346,489 on GSP0810JB5024.

Is contract GSP0810JB5024 an order under another contract?

Yes. GSP0810JB5024 is a delivery order under GS08P08JBD0056, an indefinite delivery contract.

Was contract GSP0810JB5024 competed?

The extent of competition for GSP0810JB5024 was full and open competition. The government received 5 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award