Delivery Order GS07P99HHD0134-GSP0714UT5015

Award Date 1/30/14
Potential Completion Date 4/30/14
Potential Value $24K
Federal Agency
Region 7
Ultimate Awardee
Not listed
Federal Contract Vehicle
Set-Aside Type
No Set-Aside Used
Extent Competed
Full and Open Competition
Major Defense Program
Not listed
Pricing Type
Firm Fixed Price
Place of Performance
Monroe, LA 71201, USA
Solicitation Procedures
Multiple Award, Fair Opportunity
Number Of Offers Received
1
Legislative Mandate
Davis Bacon Act
National Interest Action
Not listed
Research Type
Not listed
Primary Consortia Member
Not listed
Similar Awards
This is a firm-fixed-price delivery order awarded by the Administrative Office of the U.S. Courts (AOUSC) to Wright Bros LLC, a minority-owned small disadvantaged business, for the renovation of the 2nd and 3rd floor chambers of the Monroe Federal Courthouse in Monroe, Louisiana. The $1,181,750.30 contract has an ultimate completion date of April 30, 2025 and is a task order under the $150 million PBS Region 7 Construction Design Build 2019 indefinite delivery/indefinite quantity (IDIQ) contract...
This federal contract award, valued at $29,597,510.00, was issued by the Department of Homeland Security to the Ross Group Construction Corporation, LLC for capital security program and courts construction services at the United States Courthouse in Alexandria, Louisiana. The contract is a delivery order under the Region 7 General Construction with Design Build Capabilities Indefinite Delivery Vehicle (IDV), a $700 million multiple-award contract held by the Ross Group. Major subcontractors on...
Rowe-Cbfs JV, LLC has been awarded a firm fixed price delivery order against an unmentioned contract vehicle by the General Services Administration Public Buildings Service Region 7. The $18,210 task order is for the repair of two failed roof drains in the basement of the Alexandria Federal Courthouse in Alexandria, Louisiana with work to be completed between March 16, 2022 and July 15, 2022. No set aside designation was applied to this procurement. The funding agency, GSA PBS Region 7, oversees...
This is a firm fixed price delivery order contract awarded by the General Services Administration's Public Buildings Service (GSA PBS) to Hensel Phelps Construction CO. for $15,444,733.00 to perform capital security upgrades and new courtroom construction at the Monroe U.S. Courthouse in Louisiana. The project does not have a set-aside designation. As a prime contractor, Hensel Phelps has received multiple delivery orders from GSA PBS under the agency's Region 7 Construction Multiple Award...
The General Services Administration Public Buildings Service Region 2 (GSA - PBS) awarded a delivery order contract to Integrated Construction Enterprises Inc. for the FOR OTHER FUNCTIONS PLAZA AND STAIRS WATERPROOFING PROJECT at the Daniel P. Moynihan United States Courthouse located in New York, New York. This was a firm fixed price contract that ran from February 28, 2017 to November 28, 2017 for waterproofing projects on the plaza and stairs of the courthouse building. The place of...
The General Services Administration Public Buildings Service Region 7 awarded a $4,272.80 firm fixed price delivery order contract to Rowe-Cbfs JV, LLC of Alexandria, Louisiana for emergency repair of roof pipes at the Alexandria U.S. Courthouse in Alexandria, Louisiana. The completion date for the repairs is July 2, 2021. No set-aside provisions were applied to this award made under an existing vehicle to address immediate facility maintenance needs. The place of performance is the courthouse...
This federal contract award was issued by the General Services Administration (GSA) Public Buildings Service Region 7 to the architecture and design firm M. Arthur Gensler JR. & Associates, Inc. (doing business as Gensler) for design services related to the capital security and court components of the Monroe Federal Courthouse in Monroe, Louisiana. The $1,384,254.16 firm-fixed-price delivery order contract does not utilize any small business set-aside programs. Gensler has a robust federal...
This federal contract award is a lease (Contract Type: Delivery Order) with a fixed price and economic price adjustment pricing type, valued at $1,232.00, awarded to the City of Monroe, doing business as the Monroe Water Department, a U.S. local government entity in Louisiana. The award has no set-aside designation and the ultimate completion date is September 30, 2007. The City of Monroe has received Community Development Block Grants (CDBG) from the Department of Housing and Urban...
The federal contract award is for the CSP Remaining Work 507 Renovation Project at the Monroe Federal Building in Monroe, Louisiana. The contract was awarded to Wright Bros LLC, doing business as WB Construction, a minority-owned small disadvantaged business based in Alabama. The delivery order contract has a firm fixed price of $158,911.81 and is set for completion by April 28, 2025. The contract is a civilian agency award from the General Services Administration (GSA) Region 7. Wright Bros LLC...
This is a Delivery Order awarded to the City of Monroe, Michigan, doing business as the Monroe Water Department, a U.S. local government entity. The $1,232.00 fixed-price contract with economic price adjustment was awarded on January 1, 2008 for a federal lease. The Place of Performance is Louisiana, USA, and the Ultimate Completion Date is September 30, 2008. This contract award was not set aside. The City of Monroe has received multiple Community Development Block Grants (CDBG) from the...
  • GS07P99HHD0134
    Indefinite Delivery Contract
  • GS07P99HHD0134-GSP0714UT5015
    Delivery Order

- WATERPROOF EXTERIOR WALLS IN BASEMENT, MONROE FEDERAL COURTHOUSE, BLDG# LA0029ZZ; MONROE, LA

Posted 1/30/14, 12:00 AM