This task order is awarded to provide for design/build services for the interior repairs and renovations at the JJ pickle federal building in austin, TX

Ended Awarded Last action

Contract number
GSP0717HH0015
Awardee
Awarding agency
Obligated
$27,240,663

Award facts

Contract value 100% obligated
$27,240,662.74 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 2 offers Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Austin, TX 78701, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope PS26 · This modification is to pay the contractor the agreed to settlement amount for request for equitable adjustments *reas" submitted for the JJ pickle federal… $1,500,000
Other Administrative Action PA25 · Administrative modification to change the designated billing office for the JJ pickle federal building interior upgrades, austin, TX. $0
Supplemental Agreement for work within scope PS24 · The purpose of this modification is to compensate the contractor for the settlement of request for equitable adjustment (REA) #20 'compensable daily rate… $121,860
Supplemental Agreement for work within scope PS23 $67,084
Definitize Change Order PS22 $136,194
Supplemental Agreement for work within scope PS21 · J.J. Pickle federal building, austin, texas phase II: interior design build renovations and alterations. The purpose of this modification is to compensate the… $15,921
Change Order PC19 · The purpose of this modification is to address above ceiling electrical work for life safety and noncompliant code discrepancies above suspended ceiling on… $188,264
Supplemental Agreement for work within scope PS17 · MOD PS17 is to make above ceiling code corrections on floors 3 & 6 of the JJ pickle federal building, austin, texas in accordance with the attached scope of… $236,115
Supplemental Agreement for work within scope PS16 $255,450
Supplemental Agreement for work within scope PS15 -$15,028
Definitize Change Order PS14 $44,698
Other Administrative Action PA13 -$2,860,828
Other Administrative Action PA12 $2,860,828
Supplemental Agreement for work within scope PS11 $0
Change Order PC10 $117,228
Change Order PC09 · J.J. Pickle federal building, austin, texas phase II: interior design build renovations and alterations the purpose of this modification is to address above… $95,113
Supplemental Agreement for work within scope PC08 -$263,065
Supplemental Agreement for work within scope PS07 · This modification is issued to delete all construction work associated with the stairwell handrails, as specified in the SOW, appendix a.3 - fire protection and… -$66,074
Change Order PS06 · This deduct modification is issued to delete in its entirety the requirement to perform an ARC flash analysis in the JJ pickle federal building in austin, TX. -$60,102
Other Administrative Action PA05 · This administrative modification corrects the designated billing office codes. $0
Other Administrative Action PA04 · This administrative modification is issued to change the designated billing office and designated billing office address codes. $0
Supplemental Agreement for work within scope PC03 · JJ pickle federal building - austin, TX this modification changes the move for ICE from swing space in the federal building to swing space in the thornberry… $3,142
Supplemental Agreement for work within scope PS02 · This modification is issued to delete the requirement to build out the temporary space in the homer thornberry building (thornberry) and to swing the IRS from… -$138,247
Exercise an Option PS01 · JJ pickle federal building in austin, TX exercise option #4 to add ARC flash analysis $60,102
Original award $24,942,007
Show all 25

About this award

This is a firm fixed-price delivery order awarded by the General Services Administration (GSA) to The Robins & Morton Group, a nationally ranked general contractor, to provide design/build services for interior repairs and renovations at the JJ Pickle Federal Building in Austin, TX. The task order, valued at $27,240,662.74, was issued under the PBS Region 7 Construction Multiple Award Task Order Contract (MATOC) 2015-2020. This IDIQ contract vehicle was awarded by GSA's Region 7 to allow for construction services at federal facilities within the region. The Robins & Morton Group has experience as a prime contractor on various federal construction projects, including medical facilities, courthouses, and overseas military construction. This delivery order does not have a set-aside designation.

Quick answers

Who was awarded contract GSP0717HH0015?

GSP0717HH0015 was awarded to The Robins & Morton Group by Region 7 (Public Buildings Service) on March 3, 2017.

How much is contract GSP0717HH0015 worth?

The government has obligated $27,240,663 on GSP0717HH0015.

Is contract GSP0717HH0015 an order under another contract?

Yes. GSP0717HH0015 is a delivery order under GS07P15HHD7028, an indefinite delivery contract, on PBS Region 7 Construction MATOC 2015-2020.

Was contract GSP0717HH0015 competed?

The extent of competition for GSP0717HH0015 was full and open competition. The government received 2 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award