Construction of a new prisoner elevator, holding cells, and interior space alterations for the U.S. Marshals service at the U.S. Mahon courthouse in fort worth, TX.

Ended Awarded Last action

Contract number
47PH0821F0003
Awardee
Awarding agency
Obligated
$9,898,998

Award facts

Contract value 100% obligated
$9,898,998.00 Current and potential, with all options
Completion date 100% complete
  • Current, with exercised options
  • Potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 3 offers Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Fort Worth, TX 76102, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope PS0024 · MOD issued to extend completion date. Task order is for construction services to improve security, including a new elevator and holding cells, at the mahon… $0
Supplemental Agreement for work within scope PS0023 · Task order is for construction services to upgrade the security at mahon courthouse in fort worth, TX, including new prisoner elevator and holding cells. MOD is… $0
Supplemental Agreement for work within scope PS0022 · Task order is for construction services for renovations to upgrade security at the mahon courthouse in fort worth, TX. Modification is a no-cost time… $0
Supplemental Agreement for work within scope PS0021 · Task order for construction services to install new security elements at the mahon courthouse in fort worth, TX, including new elevator and holding cells for US… $65,654
Other Administrative Action PA0020 · Task order is for construction services to improve security at the mahon courthouse in fort worth, TX. MOD is administrative change to accounting string. $0
Supplemental Agreement for work within scope PS0019 · Task order for construction services to provide security upgrades to the mahon courthouse in fort worth, TX. Upgrades include new elevator and prisoner cells.… $0
Supplemental Agreement for work within scope PS0018 · Task order is for construction services to renovate mahon courthouse in fort worth to improve security. Modification issued to address changes in the work (rfis… $123,452
Supplemental Agreement for work within scope PS0017 · Task order is for renovations for U.S. Marshals service at US mahon courthouse in fort worth, TX. Renovations focus on security upgrades including new… $29,482
Supplemental Agreement for work within scope PS0016 · Task order for construction services to upgrade security at mahon courthouse in fort worth, TX. MOD issued to address unforeseen issues that arose during… $106,648
Supplemental Agreement for work within scope PS0015 · MOD to acknowledge government caused delay and incorporate far 52.222-55. Task order is for construction services to update security at the mahon courthouse… $0
Supplemental Agreement for work within scope PS0014 · MOD issued to address changes resulting from rfis 097-159 and for 3RD floor removal/reinstallation of lighting and additional conduit for low voltage system.… $190,814
Supplemental Agreement for work within scope PS0013 · MOD issued to incorporate changes that have come from rfis 057-096. Task order for construction services to upgrade security at the mahon courthouse in fort… $96,518
Supplemental Agreement for work within scope PS0012 · MOD to address differing conditions in the plenum space 3RD floor - mechanical, electrical, fire protection systems impacted. Task order for construction to… $109,266
Supplemental Agreement for work within scope PS0011 · MOD issued to remove asbestos-containing material and perform related floor leveling. Task order is for construction services to upgrade security, including new… $29,178
Supplemental Agreement for work within scope PS0010 · Modification issued to incorporate piping location change due to unforeseen conditions. Task order is for construction services to upgrade the security,… $11,458
Other Administrative Action PA0008 · Administrative modification issued to correct funding allocation. Task order is for construction services to upgrade the security, including a new prisoner… -$57,213
Supplemental Agreement for work within scope PS0009 · Task order for construction services at mahon courthouse in fort worth, TX. MOD incorporates additional abatement of asbestos-containing materials found… $64,689
Supplemental Agreement for work within scope PS0007 · Task order is for construction services to install security upgrades at the mahon courthouse in fort worth, TX. Modification issued to incorporate various… $89,458
Supplemental Agreement for work within scope PS0006 · Modification is to change temporary location of IT server, change from CAT6 to CAT6A and other IT requirements for the interior space alterations. Task order is… $38,033
Supplemental Agreement for work within scope PS0005 · Modification to include additional structural steel for HVAC roof penetrations as a result of request for information 001. Task order is for construction… $18,050
Supplemental Agreement for work within scope PS0004 · Task order is for construction services to incorporate security upgrades at the mahon courthouse in fort worth, TX. Modification is issued to include… $2,206
Supplemental Agreement for work within scope PS0003 · MOD to include asbestos abatement in the construction areas. Task order is for security upgrades at the mahon courthouse in fort worth, TX. $33,305
Supplemental Agreement for work within scope PS0002 · Modification issuing full notice to proceed. Task order is for construction services to incorporate security upgrades at the mahon courthouse in fort worth, TX. $0
Other Administrative Action PA0001 · Administrative modification to reallocate funding. Task order is for construction services at the mahon courthouse in fort worth, TX. $0
Original award $8,948,000
Show all 25

About this award

Hensel Phelps Construction Co. was awarded a $9,898,998 firm fixed price delivery order by the General Services Administration's Public Buildings Service Region 7 to perform construction of a new prisoner elevator, holding cells, and interior space alterations for the U.S. Marshals Service at the U.S. Mahon Courthouse in Fort Worth, Texas. The project is to be completed by December 2023 without a set-aside designation. Hensel Phelps utilized several subcontractors, including HP Ecological Services for asbestos abatement, Perry & Perry Builders for structural and miscellaneous steel as a self-certified small disadvantaged business, Flynn BEC LP for roofing and metal panels, and Professional Service Industries for air quality management and testing. The delivery order was awarded under GSA's Region 7 Construction MATOC 2015-2020 multiple-award task order contract vehicle.

Quick answers

Who was awarded contract 47PH0821F0003?

47PH0821F0003 was awarded to Hensel Phelps Construction CO. by Region 7 (Public Buildings Service) on January 11, 2021.

How much is contract 47PH0821F0003 worth?

The government has obligated $9,898,998 on 47PH0821F0003.

Is contract 47PH0821F0003 an order under another contract?

Yes. 47PH0821F0003 is a delivery order under GS07P15HHD7027, an indefinite delivery contract, on PBS Region 7 Construction MATOC 2015-2020.

Was contract 47PH0821F0003 competed?

The extent of competition for 47PH0821F0003 was full and open competition. The government received 3 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award