Task order is issued in the firm-fixed price amount of $716,000 to provide construction services to the pedestrian reengineering project located at the morley gate lpoe, nogales, AZ.

Ended Awarded Last action

Contract number
GSP0712HH5027
Awardee
Awarding agency
Obligated
$892,565

Award facts

Contract value 100% obligated
$892,565.46 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Funding agency
Customs and Border Protection Department of Homeland Security
NAICS code
236220 Commercial and Institutional Building Construction
PSC
Y1AZ Construction Of Other Administrative Facilities And Service Buildings
Set-aside
No set-aside
Competition
Full and Open Competition · 3 offers Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Nogales, AZ 85628, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope PS18 · Modification is issued to account for the lapse in appropriations. No time or cost modification. Work performed in nogales, AZ $0
Supplemental Agreement for work within scope PS17 · Modification is issed to add additional work at morley gate pertaining to deadlocks, stainless steel push buttons and table, angel supports and extrusion… $43,091
Supplemental Agreement for work within scope PS16 · Modification is issued to extend the completion date to september 30, 2013 at no additional cost. Work is located in nogales, AZ. $0
Supplemental Agreement for work within scope PS15 · Modification PS15 is issued to assess liquidated damages (LDS) for the pedestrian reengineering project, morley gate land port of entry (LPOE), AZ. MCC… -$43,260
Supplemental Agreement for work within scope PS14 · Modification PS14 is issued to extend the period of performance from july 31, 2013 to august 30, 2013 due to unresolved functional problems with the sally… $0
Supplemental Agreement for work within scope PS13 · Modification PS13 is issued to extend the period of performance from june 15, 2013 to july 31, 2013 due to unresolved functional problems with the sally port… $0
Supplemental Agreement for work within scope PS12 · Modification PS12 is issued to provide additional metal fabrication for the fencing for the morley gate pedestrian crossing project, nogales, arizona. In… $23,488
Other Administrative Action PA11 · PA11 is an administrative modification to change RWA from N0892111 to N0549082. $0
Supplemental Agreement for work within scope PS10 · Modification PS10 is issued to add additional 12 strand multi-mode fiber optic between deconcini and morley gate lpoes. $937
Supplemental Agreement for work within scope PS09 · Modification PS09 is issued to extend the period of performance by 13 calendar days, from november 19, 2012 to december 2, 2012 due weather delays. This is a… $0
Supplemental Agreement for work within scope PS07 · Modification PS07 is issued authorizing MCC to repair conduit, and electrical and data line due to a runaway train accident at the morley gate land port of… $7,934
Supplemental Agreement for work within scope PS08 · Modification PS08 is issued authorizing addition of a new gate and opening in the low pedestrian fencing at the morley gate lpoe. $1,922
Supplemental Agreement for work within scope PS06 · Modification PS06 is issued authorizing change request CCD 02 for outbound revisions, to add power and data at the outbound processing, create a sally port to… $37,620
Supplemental Agreement for work within scope PS05 · Modification PS05 is issued authorizing MCC construction to perform construction services for unforeseen subsurface conditions for the morley gate lpoe,… $32,541
Supplemental Agreement for work within scope PS04 · Add requirements for "pot holing". $5,668
Other Administrative Action PA03 · Administrative MOD to correct printing errors on MOD PS02. $0
Supplemental Agreement for work within scope PS02 · Modification to move gas lines and add third party testing $66,623
Supplemental Agreement for work within scope PS01 · Modification PS01 is issued to change the language in paragraph 4.1.D, page 17 (personnel security requirements), of the RFP document and DDD wage… $0
Original award $716,000
Show all 19

Quick answers

Who was awarded contract GSP0712HH5027?

GSP0712HH5027 was awarded to MCC Construction Corporation by Region 7 (Public Buildings Service) on March 8, 2012.

How much is contract GSP0712HH5027 worth?

The government has obligated $892,565 on GSP0712HH5027.

Which agency awarded contract GSP0712HH5027?

Region 7 (Public Buildings Service) awarded GSP0712HH5027, with funding from Customs and Border Protection (Department of Homeland Security).

Is contract GSP0712HH5027 an order under another contract?

Yes. GSP0712HH5027 is a delivery order under GS07P09HHD0007, an indefinite delivery contract.

Was contract GSP0712HH5027 competed?

The extent of competition for GSP0712HH5027 was full and open competition. The government received 3 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award