Task order issued for design-build construction services for the PDN - pedestrian reengineering project, EL paso lpoe, TX.

Ended Awarded Last action

Contract number
GSP0710HH5164
Awardee
Awarding agency
Obligated
$2,138,988

Award facts

Contract value 100% obligated
$2,138,988.31 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Funding agency
Customs and Border Protection Department of Homeland Security
NAICS code
236220 Commercial and Institutional Building Construction
PSC
Not on record
Set-aside
Competitive 8(a)
Competition
Full and Open Competition after exclusion of sources · 1 offer Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
El Paso, TX 79901, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope PS24 · Modification PS24 is issued to extend the period of performance from august 7, 2012 to november 15, 2012 due to scheduling conflicts in completing the remaining… $0
Supplemental Agreement for work within scope PS23 · Modification PS23 is issued to extend the period of performance from july 15, 2012 to august 7, 2012 due to the change in the mounting of the stanchion signage.… $0
Supplemental Agreement for work within scope PS22 · Modification issued to extend the period of performance from june 15, 2012 to july 15, 2012 to accommodate construction delays due to CBP (client agency)… $0
Supplemental Agreement for work within scope PS21 · Modification PS21 is issued authorizing V & R construction to perform additional construction work: 1.outdoor pavement striping at south revolving doors.… $52,060
Supplemental Agreement for work within scope PS20 · Modification PS20 is issued to extend the period of performance from december 31, 2011 to march 30, 2012 due to construction and delivery delays in completion… $0
Supplemental Agreement for work within scope PS19 · Modification PS19 is issued to extend the period of performance from 11/30/2011 to 12/31/2011. $0
Supplemental Agreement for work within scope PS16 · Modification PS16 is issued to definitize change order PC11 from a NTE amount of $13,474 to the firm-fixed price amount of $14,277. $803
Supplemental Agreement for work within scope PS17 · Modification PS17 is issued to definitize change order PC12 from a not-to-exceed amount to the firm-fixed price amount of $7,200. $0
Supplemental Agreement for work within scope PS18 · Modification PS18 is issued as a deduction to V & R construction in the amount of -$22,322.95 for the deletion of the north exit demolition and removal of… -$22,323
Supplemental Agreement for work within scope PS15 · Modification PS15 is issued to extend the period of performance from october 20, 2011 to november 30, 2011, due to parts shipment delays for the revolving doors… $0
Supplemental Agreement for work within scope PS14 · Modification (PS14) is issued to extend the period of performance from september 19, 2011 to october 20, 2011, due to unforeseen delays in the completion of the… $0
Supplemental Agreement for work within scope PS13 · Modification PS13 is issued to extend the period of performance from august 19, 2011 to september 19, 2011, due to unforeseen construction delays. This is a… $0
Change Order PC12 · Change order modification PC12 is issued as V & R construction's notice to proceed for a not to exceed amount of $7,200 for additional electrical conduit work… $7,200
Change Order PC11 · Change order modification PC11 is issued as V & R's notice to proceed for a not to exceed amount of $13,474 to install walk off mats and related accessories… $13,474
Supplemental Agreement for work within scope PS10 · Modification PS10 is issued for an equitable adjustment to remove the storefront above the center opening at the south entry. $2,427
Supplemental Agreement for work within scope PS09 · Modification PS09 is issued for additional electrical work and demolition in response to RFI 34 and RFI 37. $2,248
Supplemental Agreement for work within scope PS08 · Modification PS08 is issued to assess liquidated damages in the amount of $17,892 and to extend the task order end date to june 2, 2011. -$17,892
Supplemental Agreement for work within scope PS07 · Modification PS07 is issued for the demolition and replacement of concrete at the south entry to level existing concrete for revolving doors. $24,846
Supplemental Agreement for work within scope PS06 · Modification PS06 is issued to fabricate and install aluminum storefront and install support at the south entry. $33,038
Supplemental Agreement for work within scope PS05 · Modification PS05 is issued for additional construction services required in support of the new unisys equipment. $51,759
Other Administrative Action PA04 · Modification issued to reassign contracting officers $0
Supplemental Agreement for work within scope PS03 · Modification PS03 is $306
Supplemental Agreement for work within scope PS02 · MOD issued to change voice annunciators from english only to BI-lingual; the change the daktronics led displays from indor to outdoor; and the change the… $13,434
Supplemental Agreement for work within scope PS01 · Modification PS01 is issued to reduce the value of the task order by $93,100 for GSA's acceptance of deductive alternates # 1 and # 2 in the amounts of $7,500… -$93,100
Original award $2,070,709
Show all 25

Quick answers

Who was awarded contract GSP0710HH5164?

GSP0710HH5164 was awarded to V & R Drywall, Inc. by Region 7 (Public Buildings Service) on July 27, 2010.

How much is contract GSP0710HH5164 worth?

The government has obligated $2,138,988 on GSP0710HH5164.

Which agency awarded contract GSP0710HH5164?

Region 7 (Public Buildings Service) awarded GSP0710HH5164, with funding from Customs and Border Protection (Department of Homeland Security).

Is contract GSP0710HH5164 an order under another contract?

Yes. GSP0710HH5164 is a delivery order under GS07P08HHD0037, an indefinite delivery contract.

Was contract GSP0710HH5164 competed?

The extent of competition for GSP0710HH5164 was full and open competition after exclusion of sources. The government received 1 offer. It was set aside: Competitive 8(a).

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award