N1797008 usao 4_5TH floor reno MO0050ZZ 400 e 9TH ST, kansas city MO 64106 design-build services to replace floor and wall covering in the designated spaces.

Ended Awarded Last action

Contract number
47PG0220F0059
Awardee
Awarding agency
Obligated
$1,195,437

Award facts

Contract value 100% obligated
$1,195,437.00 Current and potential, with all options
Completion date 100% complete
  • Current, with exercised options
  • Potential, with all options
Funding agency
US Attorney's Offices Offices Boards and Divisions, Department of Justice
Set-aside
No set-aside
Competition
Full and Open Competition · 4 offers Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Kansas City, MO 64106, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Funding Only Action PA0008 · This is an administrative modification to add a betterment number to the accounting strings. $0
Supplemental Agreement for work within scope PS0007 · MOD PS07 is for additional work for: N1797008 whittaker usao carpet and paint 400 e. 9TH street kansas city, MO $17,475
Supplemental Agreement for work within scope PS0006 · N1797008 whitaker usao 4TH & 5TH FL renovation MOD p-6 PS06 is for work to associated to repair for flooding damage $228,182
Supplemental Agreement for work within scope PS0005 $91,723
Supplemental Agreement for work within scope PS0004 · Charles evans whittaker courthouse - 400 e 9TH ST, kansas city, MO 64106 - PS04 is issued to firm price settle PC03. Which was a not-to-exceed change order to… -$5,178
Change Order PS0003 · PC03 is to accommodate the emergency services to mitigate water damage in the construction area for N1797008 usao whittaker usch. $40,000
Other Administrative Action PO0001 · In accordance with the agreement, section I.C., the government issues notice to proceed (NTP) with this fully executed modification. Time extended: 75… $0
Original award $823,235

About this award

The Department of Justice Offices Boards and Divisions US Attorney's Offices awarded a $1.2 million firm fixed price delivery order contract to Rand Construction Company for design-build services to replace floor and wall coverings in designated spaces at 400 E 9th St, Kansas City, MO. Rand will serve as the prime contractor and has subcontracted portions of the work to Whitley Construction Company for demolition and installation of doors, frames and hardware and new walls and ceilings. Insco Industries will remove wallcoverings, perform skim coating and painting. John A Marshall Co will handle furniture moving, flooring demolition and installation, and furniture reinstallation. The period of performance is from August 31, 2020 through July 14, 2021 at the Kansas City location to modernize spaces supporting the US Attorney's Office operations.

Quick answers

Who was awarded contract 47PG0220F0059?

47PG0220F0059 was awarded to Rand Construction Company by Region 6 (Public Buildings Service) on August 31, 2020.

How much is contract 47PG0220F0059 worth?

The government has obligated $1,195,437 on 47PG0220F0059.

Which agency awarded contract 47PG0220F0059?

Region 6 (Public Buildings Service) awarded 47PG0220F0059, with funding from US Attorney's Offices (Offices Boards and Divisions).

Is contract 47PG0220F0059 an order under another contract?

Yes. 47PG0220F0059 is a delivery order under GS06P16GZD7011, an indefinite delivery contract.

Was contract 47PG0220F0059 competed?

The extent of competition for 47PG0220F0059 was full and open competition. The government received 4 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award