Recovery this project will take place at building #IA0027ZZ, which is the US courthouse at 131 east 4TH street in davenport, IA. The U.S. Courthouse in davenport was built in 1932-1933 and is a tier…

Ended Awarded Last action

Contract number
GSP0610GZ5035
Awardee
Awarding agency
Obligated
$894,588

Award facts

Contract value 100% obligated
$894,588.00 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 2 offers Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Davenport, IA 52801, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope PS14 · RIA00075 - HVAC modifications (ARRA) - U.S. Courthouse - 131 east 4TH street - davenport, IA - PS14 is hereby issued to provide for additional services to assit… $13,395
Other Administrative Action PA13 · PA13 is hereby issued to change the contract expiration date from 4/30/2012 to 11/30/2012. This project was determined substantially complete on 4/1/2011. $0
Supplemental Agreement for work within scope PS12 · PS12 is issued to execute the following 2 items: upgrades to install GFE, install auto air vent $22,815
Supplemental Agreement for work within scope PS11 · Modification PS11 is issued to execute the following 3 items: photo voltaic panels, HVAC controls, advanced metering investigation $6,905
Definitize Change Order PS10 · P9 PS10 US courthouse HVAC davenport, IA IA0027ZZ firm price settlement of PC04 for guard services -$1,584.00 -$1,584
Definitize Change Order PS09 · P2 PS09 US courthouse davenport, IA IA0027ZZ FPS of PC02 ($9,390.00) -$9,390
Change Order PC08 · P8 PC08 HVAC US courthouse, davenport, IA PDL for $8,910.00. $8,910
Definitize Change Order PS06 · P6 PS06 US courthouse davenport, IA IA0027ZZ FFP of PC05 judges chambers FCU desig, FCU falsebacks, AHU piping $12,930.18 $12,930
Supplemental Agreement for work within scope PS07 · P7 PS07 US courthouse davenport, IA IA0027ZZ $3,746 $3,746
Change Order 04R1 · P4 PC04REV1 davenport HVAC davenport, IA IA0027ZZ RIA00075 $3,404.00 $3,404
Change Order PC05 · P5 PC05 US courthouse davenport, IA IA0027ZZ judges chambers FCU design, falsebacks. AHU piping $7,969.82 $7,970
Change Order PC04 · P4 PC04 US courthouse davenport IA IA0027ZZ guard service $6,256.00 $6,256
Other Administrative Action PA03 · P3 PA03 IA0127ZZ HVAC modifications (ARRA) davenport IA extend contract completion date zero dollar $0
Change Order PC02 · PC02 install plaque davenport iowa IA0027ZZ $10000 $10,000
Supplemental Agreement for work within scope PS01 · P1/PS01 US courthouse davenport, IA IA0027ZZ HVAC modifications FFP of GMP $116,042.15 $116,042
Original award $693,189
Show all 16

About this award

This firm-fixed-price delivery order was awarded by the General Services Administration (GSA) Region 6 to Rand Construction Company, doing business as Rand Construction Co Inc., to perform HVAC system replacement and upgrades at the U.S. Courthouse in Davenport, Iowa. The $894,588 contract is part of the American Recovery and Reinvestment Act (ARRA) program aimed at creating jobs, stimulating the economy, and improving the energy efficiency of federal buildings. The project includes replacing the HVAC system, modifying the chilled water piping and distribution system, and installing card readers on six doors. This delivery order is under a larger $100 million indefinite delivery, indefinite quantity (IDIQ) contract the GSA Region 6 awarded to Rand Construction to provide construction services across Iowa, Kansas, Missouri, and Nebraska from 2020 to 2025. The contract does not have a set-aside designation.

Description

Recovery this project will take place at building #IA0027ZZ, which is the US courthouse at 131 east 4TH street in davenport, IA. The U.S. Courthouse in davenport was built in 1932-1933 and is a tier one (1) asset of GSA region 6. This building originally functioned as the U.S. Courthouse and post office. Stemming from the completion of a prospectus project in 2005, IT was converted into a U.S. Courthouse solely occupied by the 8TH district court of southern iowa. The building occupies roughly 74,400 GSF. In 2007, EMC engineers prepared a scope of work (EMC #1C10649-000). This project will be performed in conformance with this RE-commissioning scope of work. The RE-commissioning calls for the HVAC system to be replaced and that the HVAC system components to be revised. This building is still producing revenue and housing satisfied tenants. In order to maintain this satisfaction and extend the life and performance of this building, this project should be completed. The goal of this project is to reduce energy demand, reduce operation and maintenance costs, improve building system control and occupant comfort. As options, the following items will be included in the scope of work: option 1 provide actual construction phase services. Option 2 provide and install revisions to the existing chilled water piping and distribution system. IT will be modified to a variable primary flow system, including revising the existing piping, adding additional controls and adding a VFD to the existing chilled water distribution pumps. Option 3 provide and install card readers to six existing doors, including any door hardware modifications, conduit and wiring. On february 17, 2009, the president signed public law 111-5, the american recovery and reinvestment act of 2009 (ARRA). This project is part of the american recovery and reinvestment act of 2009. This project will adhere to the federal government S mission of creating jobs, placing people back to work stimulating the economy and transforming federal buildings into high performance green buildings. With this project, actions will be taken to decrease energy consumption and decrease the carbon footprint of federal buildings through energy conservation efforts.

Quick answers

Who was awarded contract GSP0610GZ5035?

GSP0610GZ5035 was awarded to Rand Construction Company by Region 6 (Public Buildings Service) on March 2, 2010.

How much is contract GSP0610GZ5035 worth?

The government has obligated $894,588 on GSP0610GZ5035.

Is contract GSP0610GZ5035 an order under another contract?

Yes. GSP0610GZ5035 is a delivery order under GS06P07GYD0051, an indefinite delivery contract.

Was contract GSP0610GZ5035 competed?

The extent of competition for GSP0610GZ5035 was full and open competition. The government received 2 offers.

On GovTribe