Recovery - this arra project is being awarded to boyd jones construction for the high performance green building project at the sioux city FB and courthouse on 320 6TH ST in sioux city, IA. With…

Ended Awarded Last action

Contract number
GSP0610GZ5033
Awardee
Awarding agency
Obligated
$2,190,930

Award facts

Contract value 100% obligated
$2,190,930.00 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 4 offers Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Sioux City, IA 51108, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Other Administrative Action PA25 · Action executed to correct comprizon: modification PA25 is hereby issued to deobligate monies intended to be deobligated with the execution of PS24. PS24 was… -$6,022
Supplemental Agreement for work within scope PS24 · PS24 is hereby issued to deobligate arra funds not required in the execution of this contract/project. $3,011
Supplemental Agreement for work within scope PS23 · Provide VFD override of all ahus. To be accessed through the BAS, provide VFD override function at the workstation. This function will provide the building with… $0
Supplemental Agreement for work within scope PS22 · Modification PS22 of contract GS-06P-07-GYD-0042/GS-P-06-10-GZ-5033 for the high performance green building project (IIA00017) at the sioux city FB at 316-320… $0
Change Order PC21 · In accordance with the construction contract clauses for adjustments, gsam 552.243-71 and far 52.243-4, you are directed to proceed with the work described in… $0
Supplemental Agreement for work within scope PS19 · Modification PS19 of contract GS-06P-07-GYD-0042/GS-P-06-10-GZ-5033 for the high performance green building project (IIA00017) at the sioux city FB at 316-320… $0
Supplemental Agreement for work within scope PS20 · Modification PS20 of contract GS-06P-07-GYD-0042/GS-P-06-10-GZ-5033 for the high performance green building project (IIA00017) at the sioux city FB at 316-320… $0
Supplemental Agreement for work within scope PS18 · Modification PS18 of contract GS-06P-07-GYD-0042/GS-P-06-10-GZ-5033 for the high performance green building project (IIA00017) at the sioux city FB at 316-320… $0
Supplemental Agreement for work within scope PS17 · Modification PS17 of contract GS-06P-07-GYD-0042/GS-P-06-10-GZ-5033 for the high performance green building project (IIA00017) at the sioux city FB at 316-320… $0
Supplemental Agreement for work within scope PS16 · Modification PS16 of contract GS-06P-07-GYD-0042/GS-P-06-10-GZ-5033 for the high performance green building project (IIA00017) at the sioux city FB at 316-320… $0
Supplemental Agreement for work within scope PS15 · Modification PS15 of contract GS-06P-07-GYD-0042/GS-P-06-10-GZ-5033 for the high performance green building project (IIA00017) at the sioux city FB at 316-320… $0
Supplemental Agreement for work within scope PS14 · Modification PS14 of contract GS-06P-07-GYD-0042/GS-P-06-10-GZ-5033 for the high performance green building project (IIA00017) at the sioux city FB at 316-320… $0
Supplemental Agreement for work within scope PS13 · Modification PS13 of contract GS-06P-07-GYD-0042/GS-P-06-10-GZ-5033 for the high performance green building project (IIA00017) at the sioux city FB at 316-320… $0
Supplemental Agreement for work within scope PS12 · Modification PS12 to contract # GS-06P-07-GYD-0042/GS-P-06-10-GZ-5033 is hereby issued to execute the following: reconnect existing lighting controls install… $0
Change Order PC11 · Due to rising flood waters, modification PC11 to contract # GS-06P-07-GYD-0042/GS-P-06-10-GZ-5033 is hereby issued to execute the following: evacuation of… $0
Supplemental Agreement for work within scope PS10 · Modification PS10 to contract # GS-06P-07-GYD-0042/GS-P-06-10-GZ-5033 is hereby issued to execute the following: upgrade from 40T crane to a 90T crane remove… $0
Supplemental Agreement for work within scope PS09 · Modification PS09 to contract # GS-06P-07-GYD-0042/GS-P-06-10-GZ-5033 is hereby issued to execute the following: provide one 1.1 ton portable cooling unit… $0
Supplemental Agreement for work within scope PS08 · Modification PS08 to contract # GS-06P-07-GYD-0042/GS-P-06-10-GZ-5033 is hereby issued to execute the following: provide chemicals for chilled water loop refill… $0
Supplemental Agreement for work within scope PS07 · Modification PS07 to contract # GS-06P-07-GYD-0042/GS-P-06-10-GZ-5033 is a no-cost (DRAW-DOWN) modification to provide temporary cooling for tenants while… $0
Supplemental Agreement for work within scope PS06 · Modification PS06 is hereby issued to formally declare the substantial completion date for contract #GS-06P-07-GYD-0042/GS-P-06-10-GZ-5033. Per the schedule… $0
Supplemental Agreement for work within scope PS05 · Modification PS05 is hereby issued to formally declare the substantial completion date for contract #GS-06P-07-GYD-0042/GS-P-06-10-GZ-5033. Per the schedule… $0
Supplemental Agreement for work within scope PS04 · Modification PS04 of contract GS-06P-07-GYD-0042/GS-P-06-10-GZ-5033 for the high performance green building project (IIA00017) at the sioux city FB at 316-320… $361,786
Other Administrative Action PA03 · PA03 - change C.O. $0
Other Administrative Action PA02 · Recovery - sioux city FB and courthouse at 320 6TH ST in sioux city, IA - PA02, for delivery order GS-06P-07-GYD-0042/GS-P-06-10-GZ-5033, is hereby issued to… $0
Supplemental Agreement for work within scope PS01 · Recovery - this arra project is called the high performance green building, for the sioux city, IA federal building and courthouse located at 320 6TH ST. $118,655
Original award $1,713,500
Show all 26

About this award

This federal contract award, GS06P07GYD0042|GSP0610GZ5033, was made by the General Services Administration (GSA) Region 6 to Boyd Jones Construction Co, a construction company based in Omaha, Nebraska. The $2,190,930.00 firm fixed price delivery order is for a high performance green building project at the Sioux City, Iowa U.S. Courthouse. The project involves retro-commissioning services and installation of high-efficiency HVAC and lighting upgrades, as well as advanced metering for energy and water, based on the findings of a retro-commissioning report. This award is part of the GSA Heartland Region 6 Design Build Indefinite Delivery Indefinite Quantity (IDIQ) contract, which has a potential value of $100 million and runs from 2020-2025. The project is funded through the American Recovery and Reinvestment Act (ARRA) and is not a set-aside contract.

Description

Recovery - this arra project is being awarded to boyd jones construction for the high performance green building project at the sioux city FB and courthouse on 320 6TH ST in sioux city, IA. With this project, the GSA is procuring retro-commissioning services and installing high energy efficient HVAC and lighting upgrades at the sioux city, iowa U.S. Courthouse. These services will be in accordance with the report of findings published by the retro-commissioning agent. The GSA will also install advance metering for all energy sources and water. Various scope items will be identified by the retro-commissioning report and ranked based on building need, energy and water conservation and payback potential. Highest ranking scope items that fall within the provided funding will be implemented, and the remaining scope will be included as options.

Quick answers

Who was awarded contract GSP0610GZ5033?

GSP0610GZ5033 was awarded to Boyd Jones Construction Co by Region 6 (Public Buildings Service) on February 22, 2010.

How much is contract GSP0610GZ5033 worth?

The government has obligated $2,190,930 on GSP0610GZ5033.

Is contract GSP0610GZ5033 an order under another contract?

Yes. GSP0610GZ5033 is a delivery order under GS06P07GYD0042, an indefinite delivery contract.

Was contract GSP0610GZ5033 competed?

The extent of competition for GSP0610GZ5033 was full and open competition. The government received 4 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award