USDA-nitc air side economizing (B0835903)

Ended Awarded Last action

Contract number
GSP0610GZ5008
Awardee
Awarding agency
Obligated
$9,939,311

Award facts

Contract value 100% obligated
$9,939,311.00 Current and potential, with all options
Completion date 100% complete
  • Current, with exercised options
  • Potential, with all options
Funding agency
Office of the Chief Information Officer Department of Agriculture
NAICS code
236220 Commercial and Institutional Building Construction
PSC
Not on record
Set-aside
No set-aside
Competition
Full and Open Competition · 5 offers Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Kansas City, MO 64114, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope PS26 · Bldg: MO0134ZZ USDA 8930 ward pkway kansas city, MO 64114 PCN: B1096851 description: GS-06P-07-GYD-0033/GS-p-06-10-GZ-5008/PS26 PS25 per the scope of work… $12,078
Supplemental Agreement for work within scope PS25 · Bldg: MO0134ZZ USDA 8930 ward pkway kansas city, MO 64114 PCN: B1096851 GS-06P-07-GYD-0033/GS-p-06-10-GZ-5008/PS25 PS25 per the scope of work attached and… -$48,956
Supplemental Agreement for work within scope PS23 $141,511
Supplemental Agreement for work within scope PS24 · Bldg: MO0134ZZ USDA 8930 ward pkway kansas city, MO 64114 PCN: B1096851 description: GS-06P-07-GYD-0033/GS-p-06-10-GZ-5008/PS24 PS24 per the scope of work… $37,261
Supplemental Agreement for work within scope PS22 · Bldg: MO0134ZZ USDA 8930 ward pkway kansas city, MO 64114 PCN: B1096851 GS-06P-07-GYD-0033/GS-p-06-10-GZ-5008/PS22 PS22 per the scope of work attached and… $56,908
Supplemental Agreement for work within scope PS21 $87,361
Supplemental Agreement for work within scope PS20 $38,751
Supplemental Agreement for work within scope PS19 $16,708
Supplemental Agreement for work within scope PS18 · Bldg: MO0134ZZ USDA 8930 ward pkway kansas city, MO 64114 PCN: B1096851 description: GS-06P-07-GYD-0033/GS-p-06-10-GZ-5008/PS18 per the scope of work attached… -$3,428
Supplemental Agreement for work within scope PS17 -$82,222
Supplemental Agreement for work within scope PS16 $183,165
Supplemental Agreement for work within scope PS15 · Bldg: MO0134ZZ USDA 8930 ward pkway kansas city, MO 64114 PCN: B1096851 GS-06P-07-GYD-0033/GS-p-06-10-GZ-5008/PS15 per the scope of work attached and hereby… $103,397
Change Order PC12 · RWA# B1096851 GS-06P-07-GYD-0033/GS-p-06-10-GZ-5008/PC12 this is a zero $ MOD, adding scope only to the existing PDL of $40,000. Sequential order of p# reversed… $0
Supplemental Agreement for work within scope PS14 · PCN: B0835903/B1096851 USDA data center expansion nitc phase 1 & 2 8930 ward pkwy kansas city, MO 64114 GS-06P-07-GYD-0033/GS-p-06-10-GZ-5008/PS14 RWA# B1096851… $1,830
Change Order PC13 · PDL NTE 40,000 to remove and relocate items in the existing data center. $40,000
Supplemental Agreement for work within scope PS11 $22,770
Supplemental Agreement for work within scope PS10 · PCN: B0835903/B1096851 USDA data center expansion nitc phase 1 & 2 8930 ward pkwy kansas city, MO 64114 GS-06P-07-GYD-0033/GS-p-06-10-GZ-5008/PS10 this… $6,595,025
Supplemental Agreement for work within scope PS09 · Provide pdus, static transfer switches and materials associated with units 601,602,701 and 702. Extend lead time 56 calendar days $368,296
Other Administrative Action PA08 · Modification PA08 is issued to add 35 calendar days to the project which was agreed to as part of PS07, but omitted on the SF30, page 1 of modification PS07.… $0
Supplemental Agreement for work within scope PS07 · Provide costs and time associated with RFI#25 to replace panel in the taperoom, inculded filling the entire panel with 80A breakers $12,346
Supplemental Agreement for work within scope PS06 · Cost associated with RFI #22 and RFI #23 and elimination of allowance cost for temporary cooling $1,207
Supplemental Agreement for work within scope PS05 · Credit associated with eletrical work related to crac #16 and cost for work associated with pump insulation, conduit replacement and refurbishment of electrical… $1,923
Supplemental Agreement for work within scope PS04 · Provide work for USDA - OIG data center and nitc data center $266,985
Supplemental Agreement for work within scope PS03 · Provide and install additional chiller and provide materials and labor to install footings $243,336
Supplemental Agreement for work within scope PS02 · Provide credit for revised drawings regarding supplemental cooling that was submitted by tapanam associates on 1/8/2010 -$172,315
Supplemental Agreement for work within scope PS01 · Firm fix price the GMP of construction phase services options 1-5 -$605
Original award $2,015,979
Show all 27

Quick answers

Who was awarded contract GSP0610GZ5008?

GSP0610GZ5008 was awarded to Mccown Gordon Construction, L.L.C. by Region 6 (Public Buildings Service) on November 12, 2009.

How much is contract GSP0610GZ5008 worth?

The government has obligated $9,939,311 on GSP0610GZ5008.

Which agency awarded contract GSP0610GZ5008?

Region 6 (Public Buildings Service) awarded GSP0610GZ5008, with funding from Office of the Chief Information Officer (Department of Agriculture).

Is contract GSP0610GZ5008 an order under another contract?

Yes. GSP0610GZ5008 is a delivery order under GS06P07GYD0033, an indefinite delivery contract.

Was contract GSP0610GZ5008 competed?

The extent of competition for GSP0610GZ5008 was full and open competition. The government received 5 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award