Provide tenant improvements necessary for the usms to expand into vacant space in the northwest corner of the third floor of the robert j dole courthouse

Ended Awarded Last action

Contract number
GSP0609GZ5102
Awardee
Awarding agency
Obligated
$1,088,457

Award facts

Contract value 100% obligated
$1,090,668.00 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
NAICS code
236220 Commercial and Institutional Building Construction
PSC
Not on record
Set-aside
No set-aside
Competition
3 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Kansas City, MO 64106, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Other Administrative Action PA12 · This modification to rectify a modification-numbering error: p-7 (PS07) is for $3826.00 and is hereby called PS10 p-10 (PS10) is for $1618.00 and is hereby… $0
Supplemental Agreement for work within scope PS11 · Modification to install tile around the trash dispenser; fabricate and install piece of metal at each of the return air grilles in training rooms 302 and 328 $1,779
Supplemental Agreement for work within scope PS09 · Modification to utilize existing conduit, reconfigure the resource room, install CAT6 cable, install a microwave shelf extension, and provide wire mold around… $2,401
Supplemental Agreement for work within scope PS08 · Modification to relocate domestic water line, relocate crac unit, and add additional training to room 302 $1,069
Supplemental Agreement for work within scope PS07 · Modification to provide man bars, changing locking system to electric strike; reconfigure resource room, and add & install exhaust fans $1,618
Supplemental Agreement for work within scope PS10 · Modification for additional door frame for training room, type d fixture credit, additional trim work, new sink, and additional garbage disposal $3,829
Supplemental Agreement for work within scope PS05 · Credit for drywall replacement. -$4,690
Supplemental Agreement for work within scope PS06 · Modification to run conduit in the ceiling from reception area to rooms 324 A.O. And 325 B.A. In rooms 324 and 325 provide a j-box and ring and string near each… $817
Supplemental Agreement for work within scope PS04 · Subject contract is hereby modified as follows: this modification is to incorporate the firm-fixed GMP into the subject contract, per the 100% specifications,… $242,868
Other Administrative Action PA03 · Administratvie modification PA03 is issued to correct the award date. $0
Change Order PC02 · PDL for shell work $23,165
Supplemental Agreement for work within scope PS01 · Modifiy the north entrance to meet security requirements $107,976
Original award $707,625
Show all 13

Quick answers

Who was awarded contract GSP0609GZ5102?

GSP0609GZ5102 was awarded to Mccown Gordon Construction, L.L.C. by Region 6 (Public Buildings Service) on September 23, 2009.

How much is contract GSP0609GZ5102 worth?

The government has obligated $1,088,457 on GSP0609GZ5102. Its current value, with exercised options, is $1,090,668.

Is contract GSP0609GZ5102 an order under another contract?

Yes. GSP0609GZ5102 is a delivery order under GS06P07GYD0033, an indefinite delivery contract.

Was contract GSP0609GZ5102 competed?

The government received 3 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award