Recovery charles F prevedel federal building 9700 page boulevard overland MO RMO00384 electrical enhancements retrofit and/or replace new on the 4TH & 5TH floors and floors 1-3.

Ended Awarded Last action

Contract number
GSP0610GZ5085
Awardee
Awarding agency
Obligated
$2,616,033

Award facts

Contract value 100% obligated
$2,616,033.00 Current and potential, with all options
Completion date 100% complete
  • Current, with exercised options
  • Potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 4 offers Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Olivette, MO 63132, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope PS07 · Federal records center 9700 page AVE ST. Louis, MO 63132-1547 action is to incorporate specification section 262200 and associated sections into the contract by… $0
Supplemental Agreement for work within scope PS06 $0
Supplemental Agreement for work within scope PS05 · Recovery. Federal records center 9700 page AVE ST. Louis, MO 63132-1547 modification is to assign monies, $30,865.00, which will be drawn down from the owner… $0
Supplemental Agreement for work within scope PS04 $404,353
Supplemental Agreement for work within scope PS03 · Recovery. Federal records center 9700 page AVE ST. Louis, MO 63132-1547 work to be completed under this modification includes but is not limited to:… $30,350
Other Administrative Action PA02 · Federal records center 9700 page AVE ST. Louis, MO 63132-1547 modification is to correct the expiration date and EST. Ultimate completion date in the… $0
Supplemental Agreement for work within scope PS01 · Recovery. Federal records center 9700 page AVE ST. Louis, MO 63132-1547 work to be completed under this modification includes but is not limited to: providing… -$68,570
Original award $2,249,900

About this award

This is a federal contract award to Interface Construction Corporation, a woman-owned small business, by the General Services Administration (GSA) Region 6 for electrical enhancements, retrofits, and replacements on the 4th, 5th, 1st, 2nd, and 3rd floors of the Charles F. Prevedel Federal Building in Overland, Missouri. The firm fixed-price contract, valued at $2,616,033.00, is for the recovery and renovation work on this civilian government facility. The contract was awarded on September 27, 2010 with a completion date of July 1, 2013. Interface Construction Corporation holds several Indefinite Delivery Vehicle (IDV) contracts with the GSA and other agencies, including a $90 million Multiple Award Construction Contract (MACC) with the Air Mobility Command and a $25 million GSA Public Buildings Service contract for the Midwest region, which likely provided the vehicle for this electrical project award. The contract did not utilize any set-aside designations.

Quick answers

Who was awarded contract GSP0610GZ5085?

GSP0610GZ5085 was awarded to Interface Construction Corporation by Region 6 (Public Buildings Service) on September 27, 2010.

How much is contract GSP0610GZ5085 worth?

The government has obligated $2,616,033 on GSP0610GZ5085.

Is contract GSP0610GZ5085 an order under another contract?

Yes. GSP0610GZ5085 is a delivery order under GS06P07GYD0016, an indefinite delivery contract.

Was contract GSP0610GZ5085 competed?

The extent of competition for GSP0610GZ5085 was full and open competition. The government received 4 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award