Delivery Order GS05P15FAD0006-47PF0017F0168
Award Date 8/21/17
Potential Completion Date 7/18/18
Potential Value $63K
Federal Agency
Ultimate Awardee
Not listed NAICS Category
PSC Category
Federal Contract Vehicle
Set-Aside Type
No Set-Aside Used
Extent Competed
Full and Open Competition after exclusion of sources
Major Defense Program
Not listed Pricing Type
Firm Fixed Price
Place of Performance
Cincinnati, OH 45202, USA
Solicitation Procedures
Multiple Award, Fair Opportunity
Number Of Offers Received
1
Legislative Mandate
Not listed National Interest Action
Not listed Research Type
Not listed Primary Consortia Member
Not listed Similar Awards
- The General Services Administration Public Buildings Service issued a delivery order to Elevar Design Group Inc. on June 1, 2026, under its Total Small Business set-aside for architect-engineering services at the John Weld Peck Federal Building in Cincinnati, Ohio, with a ceiling value of $87,080.40 and a firm fixed price. Elevar Design Group is a minority-owned, Hispanic American-owned small disadvantaged business. Work is performed in Cincinnati, OH 45202, with ultimate completion by...
- This delivery order, valued at $43,174.96, was awarded on August 20, 2021, to Elevar Design Group Inc. (doing business as SFA Architects, Inc.), a Cincinnati-based architectural and engineering firm and certified minority-owned small business. The task order is issued under the General Services Administration (GSA) Region 5 Indefinite Delivery Indefinite Quantity (IDIQ) contract vehicle "PBS OH IN IL Architect Engineering Services 2017-2022" and is designated as a Total Small...
- This federal contract award was made by the General Services Administration (GSA) Region 5 to Elevar Design Group Inc., doing business as SFA Architects, Inc., a minority-owned, Hispanic American-owned, small disadvantaged business. The $97,200.92 firm-fixed-price delivery order is for architectural design services related to the roof replacement project at the JW Peck Main building located at 550 Main Street in Cincinnati, Ohio. The work is being performed under the PBS OH IN IL Architect...
- This delivery order, awarded on August 3, 2023, to Elevar Design Group Inc. (doing business as SFA Architects, Inc.), extends the design task order period of performance for the John Weld Peck Federal Building in Cincinnati, Ohio through April 10, 2026, aligning the design phase with the existing construction services timeline. The contract carries a ceiling value of $75.4K and is structured as a firm fixed-price delivery order under the GSA Region 5 Architect Engineering Services indefinite...
- The U.S. Department of Homeland Security (DHS) awarded a $50,780.52 firm-fixed-price delivery order contract to Elevar Design Group Inc., doing business as SFA Architects, Inc., for architectural and engineering (A&E) services related to the office refresh design for the John Weld Peck Federal Building in Cincinnati, Ohio. This contract is a task order under the General Services Administration's (GSA) 2017-2022 PBS OH IN IL Architect Engineering Services indefinite delivery, indefinite...
- This contract, awarded by the General Services Administration (GSA) Region 5, provides pre-construction services for the modernization of the John Weld Peck Federal Building in Cincinnati, Ohio. The $15,478,282.60 firm-fixed-price task order contract includes work related to ceilings, lighting, electrical, HVAC, roofing, fire and life safety, restrooms, an emergency generator, and perimeter security. The prime contractor is Pepper Construction Group LLC, a subsidiary of Pepper Const Co Of In....
- This is a firm fixed-price delivery order contract awarded by the General Services Administration (GSA) to Perspectus Architecture LLC, a for-profit architecture and engineering services firm based in Cleveland, Ohio. The contract is for the design of offices for the Federal Bureau of Prisons located in the John Weld Peck Federal Building in Cincinnati, Ohio. The contract has a ceiling value of $38,028.51 and a completion date of May 9, 2025. This delivery order is part of the GSA's Public...
- The U.S. General Services Administration (GSA) awarded a firm-fixed-price delivery order to Elevar Design Group Inc., doing business as SFA Architects, Inc., a minority-owned, Hispanic American-owned, small disadvantaged business, to replace packaged cooling units at the John Weld Peck Federal Building in Cincinnati, Ohio. The contract, valued at $32,830.42, is an administrative modification to update accounting strings for the original contract. Elevar Design Group specializes in architectural,...
- The General Services Administration awarded a delivery order valued at $131,410.76 to Imeg Consultants Corp. for architect-engineer design services related to the HVAC and motor control replacement project at the John Weld Peck Federal Building in Cincinnati, Ohio. This modification adds services to support the facility's mechanical systems upgrade, with an ultimate completion date of June 19, 2026. The award was issued under the PBS OH IN IL Architect Engineering Services 2017-2022...
- The U.S. Army Corps of Engineers awarded a $151,501 firm fixed-price delivery order to Elevar Design Group Inc. (doing business as SFA Architects, Inc.) on December 18, 2025, for architectural and engineering services supporting workplace reconfiguration at the Peck Federal Building in Cincinnati, Ohio. The contract, which carries a Total Small Business set-aside designation, is scheduled for completion by July 6, 2026. Elevar Design Group is a Cincinnati-based, minority-owned small...
- GS05P15FAD0006Indefinite Delivery Contract
- GS05P15FAD0006-47PF0017F0168Delivery Order
THIS IS FOR THE AE DESIGNS OF THE UPPER ROOF REPLACEMENT AT THE JOHN WELD PECK FEDERAL BUILDING IN CINCINNATI, OHIO.
Posted 8/21/17
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| PA0002 | Other Administrative Action | $0 | 5/25/18 | |
| PA0001 | Other Administrative Action | $0 | 1/4/18 | |
| Not listed | Not listed | $63.1k | 8/21/17 |