Cooling tower replacement project for the U.S. Customhouse located at 610 south canal street in chicago, illinois. Contract GS-05P-13-SI-d-0089, order 47PF0019F0029. Your proposal dated september…

Ended Awarded Last action

Contract number
47PF0019F0029
Awardee
Awarding agency
Obligated
$501,510

Award facts

Contract value 100% obligated
$501,510.43 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition after exclusion of sources · 4 offers Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Chicago, IL 60607, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Other Administrative Action PA0003 · Contract GS-05P-13-SI-d-0089, order 47PF0019F0029. Cooling tower replacement project at the united states customhouse located at 610 south canal street in… $0
Supplemental Agreement for work within scope PS0002 · Cooling tower replacement project for the customhouse at 610 south canal street in chicago illinois. Modification PS0002 in amount of $21,501.43 approved to… $21,510
Other Administrative Action PA0001 $0
Original award $480,000

About this award

The General Services Administration (GSA) awarded a Firm Fixed Price Delivery Order to Master Design Build LLC, doing business as MDB, for a Cooling Tower Replacement Project at the U.S. Customhouse in Chicago, Illinois. The contract, valued at $501,510.43, was awarded on December 11, 2018 and has a period of performance of 180 calendar days from the Notice to Proceed. MDB, a Minority Owned, Veteran Owned, and Service-Disabled Veteran Owned business, will provide design and construction services to replace the cooling tower at the federal facility. This contract was not set aside for any small business program.

Description

Cooling tower replacement project for the U.S. Customhouse located at 610 south canal street in chicago, illinois. Contract GS-05P-13-SI-d-0089, order 47PF0019F0029. Your proposal dated september 11, 2018, in the total price of $480,000.00, submitted in response to request for proposal dated august 20, 2018, is hereby accepted and awarded in accordance with the terms and conditions of the RFP, amendment no 01 dated september 4, 2018, amendment no 02 dated september 7, 2018, and your IDIQ contract GS-05P-13-SI-d-0089. The period of performance for the completion of this work is 180 calendar days after issuance of on-site notice to proceed. The contract period is currently set at december 6, 2018 through june 4, 2019. This date may change depending on the actual date that the on-site notice to proceed is issued.

Quick answers

Who was awarded contract 47PF0019F0029?

47PF0019F0029 was awarded to Master Design Build LLC by Region 5 (Public Buildings Service) on December 11, 2018.

How much is contract 47PF0019F0029 worth?

The government has obligated $501,510 on 47PF0019F0029.

Is contract 47PF0019F0029 an order under another contract?

Yes. 47PF0019F0029 is a delivery order under GS05P13SID0089, an indefinite delivery contract.

Was contract 47PF0019F0029 competed?

The extent of competition for 47PF0019F0029 was full and open competition after exclusion of sources. The government received 4 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award