Other function - plaza waterproofing membrane replacement design at the howard M. Metzenbaum US courthouse, cleveland, ohio.

Ended Awarded Last action

Contract number
GSP0516SC7026
Awardee
Awarding agency
Obligated
$187,003

Award facts

Contract value 100% obligated
$187,002.86 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
NAICS code
541310 Architectural Services
Set-aside
No set-aside
Competition
Full and Open Competition after exclusion of sources · 1 offer Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Cleveland, OH 44114, USA

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Other Administrative Action PA06 · This modification reduces the scope for the PS02 vertical slab's since that additional design was not needed. The value of the task order is reduced by… -$13,381
Other Administrative Action PA05 · Other function - MOD to extend completion date to allow project manager time to review design submission for the plaza waterproofing project at the howard M.… $0
Other Administrative Action PA04 · Other function - this modification extends the completion date for 100% design documents related to the plaza waterproofing project at the howard M.… $0
Other Administrative Action PA03 · Other function - modification PA03 hereby extends completion date due to reassignment of project to new GSA employee and for revisions and RE-submission of 100%… $0
Supplemental Agreement for work within scope PS02 · Other function - MOD PS02 incorporates additional work within scope for the structural slab design and testing associated with the waterproofing plaza project… $13,381
Supplemental Agreement for work within scope PS01 · Other function - MOD for additional work to complete destructive testing for the waterproofing membrane project at the howard M. Metzenbaum U.S. Courthouse,… $36,315
Original award $150,688

About this award

This is a firm fixed-price delivery order contract awarded by the U.S. General Services Administration (GSA) Region 5 to Perspectus Architecture LLC, a for-profit architecture and engineering services firm. The contract is for the design of plaza waterproofing membrane replacement at the Howard M. Metzenbaum U.S. Courthouse in Cleveland, Ohio. The contract has a ceiling value of $187,002.86 and a completion date of May 30, 2018. This contract was awarded under the GSA Public Buildings Service multiple award IDIQ contract, which provides architecture, engineering, design, and construction services to federal agencies. No set-aside designation was indicated for this award.

Quick answers

Who was awarded contract GSP0516SC7026?

GSP0516SC7026 was awarded to Perspectus Architecture LLC by Region 5 (Public Buildings Service) on January 4, 2016.

How much is contract GSP0516SC7026 worth?

The government has obligated $187,003 on GSP0516SC7026.

Is contract GSP0516SC7026 an order under another contract?

Yes. GSP0516SC7026 is a delivery order under GS05P11SLD0057, an indefinite delivery contract.

Was contract GSP0516SC7026 competed?

The extent of competition for GSP0516SC7026 was full and open competition after exclusion of sources. The government received 1 offer.

On GovTribe