Renovation of U.S. Citizenship and immigration services 1ST and 4TH floors of the J.W. Peck federal building, columbus, OH.

Ended Awarded Last action

Contract number
GSP0513FB0097
Awardee
Awarding agency
Obligated
$1,547,163

Award facts

Contract value 100% obligated
$1,547,162.59 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
NAICS code
236220 Commercial and Institutional Building Construction
PSC
Z2AA Repair Or Alteration Of Office Buildings
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 2 offers Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Cincinnati, OH 45202, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Other Administrative Action PA20 · Administrative modification to cancel modifications PS18 and PA19 in comprizon.suite. $1,094
Other Administrative Action PA19 · Administrative modification issued to change the budget activity from modification PS18 from BA80 to BA54. $0
Supplemental Agreement for work within scope PS18 · This modification issues a credit back to the RWA for guard service not used and outlets not installed. -$1,094
Supplemental Agreement for work within scope PS17 · This modification is issued to add additional speaker strobes and modify exit signs for fire and life safety requirements. Place of performance: peck federal… $3,585
Supplemental Agreement for work within scope PS16 · Modification issued to assess liquidated damages for work not completed by the project substantial completion date. Place of performance: peck federal building,… -$16,125
Supplemental Agreement for work within scope PS15 · This modification is issued to add wall branding in the waiting room and wall painting in private offices. Place of performance: peck federal building, 550 main… $21,728
Supplemental Agreement for work within scope PS14 · This modification is issued to extend the column finish to the tops of the columns that were previously above ceiling level. Place of performance: peck… $14,392
Supplemental Agreement for work within scope PS13 · This modification firms the price-to-be-determined later amount from modification PS08, replaces a broken float from liebert unit, and includes multiple… $4,845
Supplemental Agreement for work within scope PS12 $21,535
Supplemental Agreement for work within scope PS11 · This modification is issued add additional items withing the scope of the project. Items include signage package, door hardware changes, and wall extensions.… $24,428
Supplemental Agreement for work within scope PS10 · This modificaiton is issued to expedite door shipment to meet the project schedule. Location of performance: peck federal building, 550 main street, cincinnati,… $3,157
Supplemental Agreement for work within scope PS09 · This modification is issued to incorporate additional work within the scope of the project including data cabling modifications, drain pan and lighting… -$453
Supplemental Agreement for work within scope PS08 · This modification is being issued to add work in install a domestic hot water heater to service the 4TH floor space. Location of performance: peck federal… $21,673
Supplemental Agreement for work within scope PS07 · This modification is issued to incorporate additional work within the scope of the project. Location of performance: peck federal building, 550 main street,… $25,086
Supplemental Agreement for work within scope PS06 · This modification is issued to incorporate additional security items and door veneer change. Location of performance: peck federal building, 550 main street,… $11,962
Supplemental Agreement for work within scope PS05 · Modification issued to incorporate 5 change orders into the contract requirements including wall covering, HVAC, restroom layout and wall modifications.… $35,403
Supplemental Agreement for work within scope PS04 · Modification is issued to incorporate lighting and ceiling modifications, resulting in a credit to the contract. Location of performance: peck federal building,… -$1,132
Supplemental Agreement for work within scope PS03 · Modification for work within scope: extension of water line to service computer room air conditioning unit on 1ST floor. $2,938
Supplemental Agreement for work within scope PS02 · This modification incorporates construction design changes. -$14,483
Supplemental Agreement for work within scope PS01 · Modification issued to change hardware items within the scope of the project. $3,784
Original award $1,384,840
Show all 21

Quick answers

Who was awarded contract GSP0513FB0097?

GSP0513FB0097 was awarded to Jeffrey Carr Construction, Inc. by Region 5 (Public Buildings Service) on September 17, 2013.

How much is contract GSP0513FB0097 worth?

The government has obligated $1,547,163 on GSP0513FB0097.

Is contract GSP0513FB0097 an order under another contract?

Yes. GSP0513FB0097 is a delivery order under GS05P11FBD0027, an indefinite delivery contract.

Was contract GSP0513FB0097 competed?

The extent of competition for GSP0513FB0097 was full and open competition after exclusion of sources. The government received 2 offers. It was set aside: Total Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award