Recovery - construction manager as constructor (CMC) for the FBI field office build-out and miscellaneous improvements project at the patrick V. Mcnamara federal building, detroit, michigan.

Ended Awarded Last action

Contract number
GSP0510GB5004
Awardee
Awarding agency
Obligated
$19,954,533

Award facts

Contract value 100% obligated
$19,954,533.00 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 5 offers Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Detroit, MI 48226, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope PSD5 · Supplemental modification to the FBI office build out and miscellaneous improvements project at the patrick mcnamara federal building, detroit, michigan.… $0
Supplemental Agreement for work within scope PSD4 $0
Supplemental Agreement for work within scope PSD3 · Supplemental modification to the american recovery reinvestment act task order for office build out and miscellaneous improvements to the federal bureau of… $2,043
Other Administrative Action PAD2 · This modification is being issued to change the funding on two previous modifications. $0
Supplemental Agreement for work within scope PSC9 · This modification is being issued to credit modification PS42. -$13,989
Supplemental Agreement for work within scope PSD1 · This modificaiton is being issued to add basement conduit revisions. $0
Supplemental Agreement for work within scope PSC8 · This modificaiton is being issued to provide blinds in the west lobby, and marker board paint. $12,445
Supplemental Agreement for work within scope PSC7 · This modification is being issued to adjust the layout on level 22 and 23. $15,123
Supplemental Agreement for work within scope PSC5 · This modification is being issued to incorproate the following work: 1. CE5068-R1, PCO 810117R1 (11/15/13) - on february 14, 2012 you were provided… $0
Other Administrative Action PAC6 · This modification is being issued to change the contracting officer. $0
Supplemental Agreement for work within scope PSC4 · This modification is being issued to incorproate the following: 1. CE5174, PCO 810241 (10/28/13) - replace the currently installed VCT tile with carpeting per… $0
Supplemental Agreement for work within scope PSC3 · This modification is being issued to add dielectric breaks at the existing stairwell. $0
Supplemental Agreement for work within scope PSC2 · This modification is being issued to add OGA space on level 25. $54,625
Supplemental Agreement for work within scope PSC1 · This modification is being issued to turn room 2309 in a one hour rated enclosure. $0
Other Administrative Action PAB9 · This administrative action was created to change the accounting for modifications PSB7 & PSB8 $0
Supplemental Agreement for work within scope PSB8 · This modification is being issued to move a thermostat. $0
Supplemental Agreement for work within scope PSB7 · This modificaton is being issued to incorproate the following scopes of work: 1. CE5096-R1, PCO 810105R1 (7/11/13) - provide and install exit sign and revisions… $0
Supplemental Agreement for work within scope PSB6 · This modification is being issued to incoprorate GSA's portion of the mechanically fastened gaskets. $0
Supplemental Agreement for work within scope PSB5 · This modification is being issued to incorporate the following scopes of work: 1. CE5009-R1, PCO 810021R1 (5/22/13) - on february 14, 2012 you were provided… $0
Supplemental Agreement for work within scope PSB4 · This modification is being issued to incorproate the following scopes of work: 1) install door stops at all new restrooms 2) change glass type to glass type… $0
Supplemental Agreement for work within scope PSB3 · This modification is being issued to incorporate the following scopes of work: 1) investigate and perform all accrediation items needed for levels 24 & 19. 2)… $0
Supplemental Agreement for work within scope PSB2 · This modification is being issued to incorporate OGA revisions per bulletin 16 on level 24 only. $50,000
Supplemental Agreement for work within scope PSB1 · This modification is being issued to incorporate the following work: 1) convert modification PSA8 from a price to be determined later to a firm fixed price 2)… $0
Supplemental Agreement for work within scope PSA9 · This modification is being issued to incorporate the following work: 1) relocate the sensors to AC controllers 2) provide a credit for revisions to the… $0
Supplemental Agreement for work within scope PSA8 · This modification is being issued to incorporate bulltin 5 and 5.1.E $0
Supplemental Agreement for work within scope PSA7 · This modification was issued to incorporate the following scopes of work: 1. CE5137, PCO 810193 (1/31/13) - remove pull station and intercom cross-tie from… $0
Supplemental Agreement for work within scope PSA6 · This modification is being issued to provide and install a glass door with a side light. $18,055
Supplemental Agreement for work within scope PSA5 · This modification is being issued to incorporate the following scopes of work: 1. CE5131, PCO 810191 (10/22/12) - relocate existing camera outside the level 1… $0
Supplemental Agreement for work within scope PSA3 · This modification is being issued to convert modification PS56 to a firm fixed price. $0
Supplemental Agreement for work within scope PSA2 · This modification is being issued to install temporary heating in the level 1 west. $11,300
Supplemental Agreement for work within scope PSA4 · This modification is being issued to add the permanent heating solution to the level 1 west. $0
Supplemental Agreement for work within scope PSA1 · This modification is being issued to install two tankless water heaters in the mens and womens bathrooms in the level 1 west lobby. $0
Supplemental Agreement for work within scope PS99 · This modification is being issued to add voip outlets on levels 1, 24 & 25, along with 2 new cameras on level 23. $8,934
Supplemental Agreement for work within scope PS98 · This modification is being issued to convert the price to be determined later for the sealant and foil construction information guide to a firm fixed price. $0
Supplemental Agreement for work within scope PS97 · This modification is being issued to incorporate the following scopes of work: 1. CE5128, PCO 810184 (10/3/12) - infill the level 24 existing core closet… $0
Supplemental Agreement for work within scope PS96 · This modification is being issued to convert modification PS45 from a price to be determined later to a firm fixed price. $0
Supplemental Agreement for work within scope PS92 · This modification is being issued to provide and install the missing circuit for the fire alarm loads. $0
Supplemental Agreement for work within scope PS94 · This modification is being issued to convert bulletin 6 from a price to be determined later to a firm fixed price modification. $0
Supplemental Agreement for work within scope PS93 · This modification is being issued to convert bulletin 7 from a price to be determined later to a firm fixed price. $0
Supplemental Agreement for work within scope PS95 · This modification is being issued to convert the price to be determined later modification to relocate the south turnstile at the level 1 west plaza to a firm… $0
Supplemental Agreement for work within scope PS91 · This modification is being issued to award the balance of bulletin 3. $0
Supplemental Agreement for work within scope PS90 · This modification is being issued to fill the walker duct on level 23. $5,728
Supplemental Agreement for work within scope PS89 · This modification is being issued to incorporate the following scopes of work: 1) bulletin 12 2) infill the walker duct on level 23 $0
Other Administrative Action PA88 · This modification is being issued to correct the fiscal year in the funding string for modifications PS84 & 85. $0
Supplemental Agreement for work within scope PS84 · This modification is being issued to provide electrical revisions to the pantries on levels 21-25. $0
Supplemental Agreement for work within scope PS85 · This modification is being issued to incorporate the following scopes of work: 1) flooring revisions and temporary door relocations on level 22 2) additional… $4,038
Other Administrative Action PA87 · This administrative modification was issued to change the contracting officer. $0
Supplemental Agreement for work within scope PA86 · This modification is being issued to change the ADN used on PS75. $0
Supplemental Agreement for work within scope PS73 · This modification is being issued to incorporate the following scopes of work: 1) furnish and install and additional data drop 2) provide 3 additional power… $4,412
Supplemental Agreement for work within scope PS81 · This modification is being issued to perform modifications to the substation and substation breakers. $0
Show 40 more

Latest 50 listed here. See the rest on GovTribe.

About this award

This federal contract award, with ID GS05P09GBD0037|GSP0510GB5004, was issued by the General Services Administration (GSA) Region 5 to the prime contractor Clark Construction Group, LLC. The $19,954,533.00 Firm Fixed Price contract is for Construction Manager as Constructor (CMC) services to support the build-out and improvements project for the Federal Bureau of Investigation (FBI) field office located at the Patrick V. McNamara Federal Building in Detroit, Michigan. The contract has an ultimate completion date of August 1, 2014 and does not utilize any set-aside designations. The parent company of the prime contractor is Clark Enterprises, Inc.

Quick answers

Who was awarded contract GSP0510GB5004?

GSP0510GB5004 was awarded to Clark Construction Group, LLC by Region 5 (Public Buildings Service) on November 5, 2009.

How much is contract GSP0510GB5004 worth?

The government has obligated $19,954,533 on GSP0510GB5004.

Is contract GSP0510GB5004 an order under another contract?

Yes. GSP0510GB5004 is a delivery order under GS05P09GBD0037, an indefinite delivery contract.

Was contract GSP0510GB5004 competed?

The extent of competition for GSP0510GB5004 was full and open competition. The government received 5 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award