Recovery CMC services to modernize the john W. Peck federal building, cincinnati, ohio. The project includes exterior renovation, including window and glazing replacement, tuck-pointing and…

Ended Awarded Last action

Contract number
GSP0509GB5045
Awardee
Awarding agency
Obligated
$27,511,991

Award facts

Contract value 100% obligated
$27,511,990.53 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Competitive Delivery Order · 20 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Cincinnati, OH 45202, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope PS69 · Arra building modernization cincinnati, ohio JW peck federal building this modification deducts the remaining unbilled balance of the contract. -$5,000
Supplemental Agreement for work within scope PS68 · GS-05P-09-GB-D-0015/GS-P-05-09-GB-5045/PS68/PN9E02354 construction manager as constructor (CMC) services for the modernization of the john weld peck federal… $550,000
Supplemental Agreement for work within scope PS67 · GS-05P-09-GB-D-0015/GS-P-05-09-GB-5045/PS67/PN9E02354 construction manager as constructor (CMC) services for the modernization of the john weld peck federal… $0
Supplemental Agreement for work within scope PS66 · GS-05P-09-GB-D-0015/GS-P-05-09-GB-5045/PS66/PN9E02354 construction manager as constructor (CMC) services for the modernization of the john weld peck federal… $0
Supplemental Agreement for work within scope PS65 · GS-05P-09-GB-D-0015/GS-P-05-09-GB-5045/PS65/PN9E02354 construction manager as constructor (CMC) services for the modernization of the john weld peck federal… $0
Supplemental Agreement for work within scope PS64 · GS-05P-09-GB-D-0015/GS-P-05-09-GB-5045/PS64/PN9E02354 construction manager as constructor (CMC) services for the modernization of the john weld peck federal… $0
Supplemental Agreement for work within scope PS63 · GS-05P-09-GB-D-0015/GS-P-05-09-GB-5045/PS63/PN9E02354 construction manager as constructor (CMC) services for the modernization of the john weld peck federal… $0
Supplemental Agreement for work within scope PS62 · Peck federal building, cincinnati, ohio this modification incorporates the settlement agreement between GSA and the contractor. $0
Supplemental Agreement for work within scope PS61 · Peck federal building, cincinnati, ohio this modification increases an allowance for temporary heating. $295
Supplemental Agreement for work within scope PS60 · Peck federal building, cincinnati, ohio this modification provides for changes to the HVAC and fire protection systems as well as a change to an egress door. $0
Supplemental Agreement for work within scope PS59 · Peck federal building, cincinnati, ohio this modification increases the value of the tenant displacement allowance. $250,000
Supplemental Agreement for work within scope PS58 $5,509
Supplemental Agreement for work within scope PS57 · Peck federal building, cincinnati, ohio this modification provides for interior and exterior changes. $296,308
Supplemental Agreement for work within scope PS56 · Peck federal building, cincinnati, ohio this modification extends the contract to 30 january 2014 and adds funding for abatement and interior work. $1,356,298
Supplemental Agreement for work within scope PS55 $0
Supplemental Agreement for work within scope PS52 $0
Supplemental Agreement for work within scope PS51 · Peck federal building, cincinnati, ohio this modification provides for changes to the HVAC system. $0
Supplemental Agreement for work within scope PS54 · This modification provides for paint in a tenant space. Cincinnati, ohio, peck federal building. $2,599
Supplemental Agreement for work within scope PS53 · Peck federal building, cincinnati, ohio this modification creates an allowance to temporarily fix heat related issues through the winter. $130,000
Supplemental Agreement for work within scope PS50 · Peck federal building, cincinnati, ohio this modification provides security changes for a tenant. $0
Supplemental Agreement for work within scope PS48 $157,255
Supplemental Agreement for work within scope PS41 · Peck federal building, cincinnati, ohio this modification provides for handicap access to tenant space. $0
Supplemental Agreement for work within scope PS45 · Peck federal building, cincinnati, ohio this modification changes fire alarm devices in two rooms. $0
Supplemental Agreement for work within scope PS43 · Peck federal building, cincinnati, ohio this modificaion omits the electrical refurbishment of the switchgear. $0
Supplemental Agreement for work within scope PS46 · Peck federal building, cincinnati, ohio this modification is for paint and carpeting in a tenant space. $184,668
Supplemental Agreement for work within scope PS47 $0
Supplemental Agreement for work within scope PS44 $118,442
Supplemental Agreement for work within scope PS42 $0
Supplemental Agreement for work within scope PS40 $0
Supplemental Agreement for work within scope PS39 · Peck federal building, cincinnati, ohio this modification provides for changes in a tenant space. $0
Change Order PC38 · Peck federal building, cincinnati, ohio this modification changes the specifications regarding partnering. $0
Supplemental Agreement for work within scope PS37 · Peck federal building, cincinnati, ohio this modification provides for changes to the exterior work, fire alarm, HVAC, and tenant spaces. $0
Supplemental Agreement for work within scope PA36 · Peck federal building, cincinnati, ohio this modification incorporates pepper's updated cost accounting standards $0
Supplemental Agreement for work within scope PS33 · Peck federal building, cincinnati, ohio changes to the air handling system in the building. $0
Supplemental Agreement for work within scope PS34 · Peck federal building, cincinnati, ohio changes to ductwork and thermostats. $0
Supplemental Agreement for work within scope PS35 · Peck federal building, cincinnati, ohio modifications to air handling units. $0
Supplemental Agreement for work within scope PS31 · Peck federal building, cincinnati, ohio revisions to corridor entrances to office space (ALCOVES). $0
Supplemental Agreement for work within scope PS30 · Peck federal building, cincinnati, OH instead of installing door hardware, turn hardware over to GSA. $0
Supplemental Agreement for work within scope PS29 · Peck federal building, cincinnati, OH provide updated mechanical controls for an office. $0
Supplemental Agreement for work within scope PS32 · Peck federal building, cincinnati, ohio changes to sprinklers on the second floor. $0
Supplemental Agreement for work within scope PA28 · This modification changes funding coding for PS24. Peck federal building, cincinnati, ohio $0
Change Order PC27 · This change is to provide updated mechanical controls to the peck FB. $3,349
Supplemental Agreement for work within scope PS26 · This change is to demo existing ductwork in the peck FB. $17,536
Supplemental Agreement for work within scope PS25 · This modification is to provide space temperature sensors in the J. W. Peck FB. $2,622
Supplemental Agreement for work within scope PS24 · This change order is to establish an allowance to provide window film to the sidelights of the peck federal building. $922
Supplemental Agreement for work within scope PS21 · This change order is for a credit to modify the door hardware at the peck FB. -$8,742
Supplemental Agreement for work within scope PS23 · This change order alters the exterior restoration cleaner for the limestone at the peck FB. $8,232
Supplemental Agreement for work within scope PS22 · This change order is to deleter requirement for exterior limestone sealant. -$16,574
Supplemental Agreement for work within scope PS20 · Change order to provide temporary carpet protection to peck FB. $16,057
Supplemental Agreement for work within scope PS18 · To provide window blinds in the peck federal building. $185,443
Show 40 more

Latest 50 listed here. See the rest on GovTribe.

About this award

This is a $27,511,990.53 firm fixed-price delivery order awarded by the General Services Administration (GSA) Region 5 to Pepper Construction Group LLC, a for-profit organization, for renovation and modernization services at the John W. Peck Federal Building in Cincinnati, Ohio. The project includes exterior renovations such as window and glazing replacement, tuck-pointing, cleaning, roof replacement, and penthouse surface repairs. This contract does not have a set-aside designation.

Description

Recovery CMC services to modernize the john W. Peck federal building, cincinnati, ohio. The project includes exterior renovation, including window and glazing replacement, tuck-pointing and cleaning, replacement of the main roof, and penthouse surface repairs.

Quick answers

Who was awarded contract GSP0509GB5045?

GSP0509GB5045 was awarded to Pepper Construction Group LLC by Region 5 (Public Buildings Service) on September 9, 2009.

How much is contract GSP0509GB5045 worth?

The government has obligated $27,511,991 on GSP0509GB5045.

Is contract GSP0509GB5045 an order under another contract?

Yes. GSP0509GB5045 is a delivery order under GS05P09GBD0015, an indefinite delivery contract.

Was contract GSP0509GB5045 competed?

The extent of competition for GSP0509GB5045 was competitive delivery order. The government received 20 offers.

On GovTribe

See this award's full record