Delivery Order FA300208D0012-TG03
Award Date 7/31/13
Potential Completion Date 11/6/14
Potential Value $989K
Funding Federal Agency
Contracting Federal Agency
Awardee
Ultimate Awardee
Not listed PSC Category
Set-Aside Type
No Set-Aside Used
Federal Contract Vehicle
Extent Competed
Full and Open Competition
Major Defense Program
Not listed Pricing Type
Firm Fixed Price
Place of Performance
Maumee, OH 43537, USA
Solicitation Procedures
Multiple Award, Fair Opportunity
Number Of Offers Received
32
Legislative Mandate
Not listed National Interest Action
Not listed Research Type
Not listed Primary Consortia Member
Not listed Similar Awards
- The Department of the Air Force Air Combat Command awarded a $101,508 firm fixed price delivery order to Ice Technical Services Inc. to install a fan coil unit in Room SL1.106, Building B1000 at Offutt Air Force Base in Nebraska. The work is to be performed between September 2020 and May 2021 at the base, which serves as headquarters for both the United States Strategic Command and the 55th Wing of the Air Force's Space Command. No major subcontractors or set aside designations were identified...
- The U.S. Air Force awarded a delivery order valued at $1.13M to Bhate Environmental Associates, Inc. (BEA) on September 29, 2023, for the Upgrade Dual Source Electrical Power project at Offutt Air Force Base in Nebraska. This contract, designated as a Total Small Business set-aside with an ultimate completion date of March 31, 2026, falls under the Air Force Regional Engineering and Construction - Central 2016-2021 indefinite delivery vehicle. The work involves upgrading dual power and...
- The U.S. Air Force's Air Combat Command awarded a $430.9M delivery order to Nielsen Baumert Engineering, Inc. on March 3, 2025, for architectural and engineering design services related to the replacement of power and distribution switchgear, transformers, fuses, enclosures, relays, controls, and cabling across three substations (Rooms 801, 144, and 299) in Building 457 at Offutt Air Force Base, Nebraska. The contract carries a firm fixed price structure with no small business set-aside...
- The U.S. Air Force's Air Combat Command has awarded a $393,818 firm fixed-price delivery order to Omaha Public Power District (OPPD) for the burial of secondary-side electric utility infrastructure serving Generals Row at Offutt Air Force Base in Nebraska. The contract, awarded on September 17, 2025, is scheduled for completion by May 15, 2026, and carries no small business set-aside designation. OPPD, a locally-owned public utility entity registered in the System for Award Management since...
- The Department of the Air Force Air Combat Command awarded Ice Technical Services Inc. a $1,163,885.51 firm fixed price delivery order contract to renovate a portion of Lower Level 3 in Building 1000 at Offutt Air Force Base, Nebraska, to construct a control room and break room. The work includes renovation of a portion of Lower Level 3 in Building 1000 to construct a Control Room and Break Room. The period of performance is from September 20, 2022 through July 21, 2023 at Offutt Air Force...
- This is a firm fixed-price delivery order awarded by the Air Combat Command (ACC), a U.S. Air Force major command, to Mowa-Barlovento Joint Venture A, a minority-owned, Native American, and small disadvantaged business. The $6,614,497.00 contract is for the repair of electrical substation B565 at Offutt Air Force Base in Nebraska. The contract is part of the Air Force Regional Engineering and Construction - Central 2016-2021 indefinite delivery/indefinite quantity (IDIQ) contract vehicle. No...
- The Department of the Air Force Air Combat Command awarded Omaha Public Power District, doing business as Oppd, a $880,807 firm fixed price delivery order to replace heat pumps at Building B187 at Offutt Air Force Base in Nebraska. As the prime contractor, Oppd will deliver and install new heat pumps for the facility under the terms of the contract, which runs from September 2021 through November 2022. The funding for this project comes through the Air Force's facilities sustainment, restoration...
- Turner Construction Company received a $784.4 million firm fixed-price definitive contract from the U.S. Army Corps of Engineers, Engineering District Omaha (ENDIST) to design and construct a Non-Kinetic Operations (NKO) facility and Defense Courier Station (DCS) at Offutt Air Force Base in Nebraska, with ultimate completion targeted for January 2, 2028. This no-set-aside award supports critical Department of Defense infrastructure modernization efforts, delivering approximately 30,844 square...
- This delivery order, valued at $863,493.84, was awarded on a firm fixed price basis by the Department of the Air Force Air Combat Command to Pergravis LLC. The purpose is to replace capacitors and fans for 24 GE uninterruptible power source systems at Offutt Air Force Base, Nebraska in support of Strategic Command operations. Funding is provided by the Air Force for continuity of critical power conditioning and interface equipment supporting the Command's missions. As the prime, Pergravis will...
- The Department of the Air Force Air Combat Command (DOD - United States Air Force) awarded a $331,475 firm fixed price delivery order contract to Omaha Public Power District, doing business as Oppd, to conduct a Utility Feasibility Study at Offutt Air Force Base, Nebraska. The contract has a period of performance starting on September 26, 2022 through November 18, 2022. No subcontractors were identified. The delivery order is for Oppd to study the utility infrastructure at Offutt AFB and provide...
- FA300208D0012Indefinite Delivery Contract
- FA300208D0012-TG03Delivery Order
- UPGRADE POWER BLDG 578, OFFUTT AFB
Posted 7/31/13
Name | Description | Solicitation Number | FederalAgency | Type | PostedDate |
|---|---|---|---|---|---|
SATOC | FA3002-06-R-0001 | Department of the Air Force Materiel Command Installation and Mission Support Center Installation Contracting Agency | Award Notice 1/1 | 7/28/05, 12:00 AM |
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| 5 | Supplemental Agreement for work within scope | $0 | 12/11/14 | |
| 4 | Other Administrative Action | $0 | 8/11/14 | |
| 3 | Supplemental Agreement for work within scope | $25.7k | 7/29/14 | |
| 2 | Supplemental Agreement for work within scope | $0 | 6/26/14 | |
| 1 | Supplemental Agreement for work within scope | $0 | 3/4/14 |