Architect-engineer environmental services, sulphur bank mercury mine superfund site, lake county, CA. Community involvement (CI)

Ended Awarded Last action

Contract number
68HE0918F0402
Awardee
Awarding agency
Obligated
$91,292

Award facts

Contract value 100% obligated
$91,292.23 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
NAICS code
562910 Remediation Services
Set-aside
No set-aside
Competition
Full and Open Competition after exclusion of sources Architect-Engineer FAR 6.102
Pricing
Time and Materials
Place of performance
Hidden Valley Lake, CA 95467, USA

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope P00009 · Sulphur bank mercury mine community involvement (CI). The purpose of this modification is to DE-obligate unused funds, and closeout this task order in its… -$82,804
Other Administrative Action P00008 · RAC 3 - sulphur bank mercury mine community involvement (CI). This modification incorporates the contractor's net-zero work variance notice #001, dated… $0
Supplemental Agreement for work within scope P00007 · The purpose of this modification is to incorporate a no-cost POP extension and change the POP end date from 01/27/2022 to 7/27/2023. $0
Supplemental Agreement for work within scope P00006 · The purpose of this modification is to incorporate a period of performance end date extension from 04/40/2020 to 01/27/2022 and to change the primary and… $0
Other Administrative Action P00005 · The purpose of this modification is to incorporate far clause 52.204-25 into this task order. $0
Supplemental Agreement for work within scope P00004 · The purpose of this modification is to: 1.incorporate the revised statement of work, dated 5/27/2020. 2.incorporate WPA (REV 3) submitted on 6/23/2020.… $6,431
Supplemental Agreement for work within scope P00003 · The purpose of this modification is to extend the period of performance end date until 4/30/2021. $0
Supplemental Agreement for work within scope P00002 · The purpose of this modification is to update the COR assignments and extend the period of performance until 7/31/2020. $0
Other Administrative Action P00001 $0
Original award $167,665

About this award

This is a federal contract award from the U.S. Environmental Protection Agency (EPA) Region 9 to EA Engineering, Science, and Technology, Inc., PBC, a for-profit environmental consulting and engineering firm. The contract is for $91,292.23 and is for architect-engineer environmental services at the Sulphur Bank Mercury Mine Superfund site in Lake County, California, specifically for community involvement (CI) activities. The contract is a delivery order, with a time and materials pricing type, and an ultimate completion date of July 27, 2023. This award does not have a set-aside designation. EA Engineering is the prime contractor and has performed numerous complex environmental projects for federal agencies, including the EPA, Department of Defense, Army Corps of Engineers, and National Park Service.

Quick answers

Who was awarded contract 68HE0918F0402?

68HE0918F0402 was awarded to EA Engineering, Science, And Technology, Inc., PBC by EPA Region 9 (Regional Offices) on September 13, 2018.

How much is contract 68HE0918F0402 worth?

The government has obligated $91,292 on 68HE0918F0402.

Is contract 68HE0918F0402 an order under another contract?

Yes. 68HE0918F0402 is a delivery order under EPS91401, an indefinite delivery contract.

Was contract 68HE0918F0402 competed?

The extent of competition for 68HE0918F0402 was full and open competition after exclusion of sources.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award