The purpose of this task order is to obligate $20,550,000.00 for remedial action (sediment removal, year 2-phase) at iron mountain mine superfund site, shasta county, california. The period of…

Ended Awarded Last action

Contract number
EP0045
Awardee
Awarding agency
Obligated
$20,692,769

Award facts

Contract value 100% obligated
$20,692,769.33 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
NAICS code
562910 Remediation Services
Set-aside
No set-aside
Competition
Competitive Delivery Order · 1 offer Architect-Engineer FAR 6.102
Pricing
Time and Materials
Place of performance
Redding, CA 96001, USA

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Funding Only Action 10 · Recovery task order no. 045 for remedial action at iron mountain mine in redding, california. This project concluded on 03/31/10. The purpose of this… -$2,131
Other Administrative Action 9 · The purpose of this modification is to incorporate one (1) work variance notification into this task order and extend the anticipated expiration date from… $0
Other Administrative Action 8 · A & E environmental services $0
Other Administrative Action 7 · The purpose of this modification is to incorporate four (4) work variance notifications into this task order. All other terms and conditions remain unchanged.… $0
Other Administrative Action 6 · The purpose of this modification is to incorporate two (2) work variance notifications into this task order. All other terms and conditions remain unchanged.… $0
Other Administrative Action 5 · The purpose of this modification is to incorporate five work variance notifications into this task order. All other terms and conditions remain unchanged.… $0
Funding Only Action 4 · The purpose of this modification is to obligate incremental funds to the task order in the amount of $20,898.00 for the iron mountain mine superfund site,… $20,898
Funding Only Action 3 · The purpose of this modification is to obligate incremental funds in the amount of $124,002.00 for the iron mountain mine superfund site, shasta county,… $124,002
Other Administrative Action 2 · The purpose of this modification is to incorporate a revised statement of work, dated april 20, 2009, and work plan, dated june 3, 2009 for the iron mountain… $0
Other Administrative Action 1 · Remedial action (sediment removal, year 2-phase) at iron mountain mine superfund site, shasta county, california. The purpose of this modification is to correct… $0
Original award $20,550,000
Show all 11

About this award

This federal contract award, with ID EPS90804|EP0045, was issued by the U.S. Environmental Protection Agency (EPA) Region 9 to the prime contractor Ch2M Hill, Inc. The purpose of this $20,692,769.33 Time and Materials task order is to fund the second phase of remedial action, including sediment removal, at the Iron Mountain Mine Superfund site in Shasta County, California. The work will be performed from April 13, 2009 through March 31, 2010. This task order was issued under the Remedial Action Contract II (RACII) vehicle. The contract does not have a set-aside designation. The parent company of the prime contractor is Ch2M Hill Companies, LTD.

Description

The purpose of this task order is to obligate $20,550,000.00 for remedial action (sediment removal, year 2-phase) at iron mountain mine superfund site, shasta county, california. The period of performance is from 13 april 2009 through 31 january 2010. This work is to implement and support a significant portion of remedial action (RA) selected in september 30, 2004 record of decision (ROD5) for the iron mountain mine (IMM) superfund site in accordance with the remedial design (RD) to dredge contaminated sediments from the spring creek arm of keswick reservoir (SCAKR). Included in the activities under this task order will be the completion of the disposal cell (except for closure activities), purchase of long-lead equipment, and purchase and installation of all piping, pump station and treatment system infrastructure necessary to start phase III in fall 2009. The task order has been issued under remedial action contract II (RACII) on 13 april 2009. For internal tracking purposes, the task order title will be 045-rara-0917. Arra::yes::arra

Quick answers

Who was awarded contract EP0045?

EP0045 was awarded to Ch2M Hill, Inc. by EPA Region 9 (Regional Offices) on April 13, 2009.

How much is contract EP0045 worth?

The government has obligated $20,692,769 on EP0045.

Is contract EP0045 an order under another contract?

Yes. EP0045 is a delivery order under EPS90804, an indefinite delivery contract.

Was contract EP0045 competed?

The extent of competition for EP0045 was competitive delivery order. The government received 1 offer.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award