Delivery Order EPS90804-68HE0919F0031
- Not listed
- This is a federal contract award from the U.S. Environmental Protection Agency (EPA) Region 9 to CH2M Hill, Inc., a subsidiary of Jacobs Engineering Group Inc., for architect-engineer environmental services in support of the Casmalia Remedial Investigation/Feasibility Study oversight. The contract is a time and materials delivery order with a ceiling value of $1,594,188.22 and an ultimate completion date of May 23, 2021. The contract does not have a set-aside designation. Jacobs Engineering...
- This is a cost-plus-fixed-fee delivery order contract awarded by the U.S. Environmental Protection Agency (EPA) Region 9 to CH2M Hill, Inc., a subsidiary of Jacobs Engineering Group Inc. The contract is for oversight of remedial design, remedial action, operations, maintenance, and monitoring activities at the Casmalia Resources Superfund Site. The purpose of this modification is to update the period of performance. The contract has a ceiling value of $6,063,302.03 and a period of performance...
- This is a $1,322,272.00 cost-plus-fixed-fee delivery order contract awarded by the U.S. Environmental Protection Agency (EPA) Region 9 to Ch2M Hill, Inc., a subsidiary of Jacobs Engineering Group Inc. The contract is for oversight support of the United Heckathorn Superfund Site focused feasibility study, proposed plan, and record of decision. This task order falls under the EPA's Remedial Acquisition Framework: Design and Engineering Services (RAF DES) contract vehicle. The contract does not...
- The U.S. Environmental Protection Agency (EPA) awarded a time and materials contract to Ch2M Hill, Inc., an engineering and construction firm, to provide $152,767.44 in general engineering support services for multiple FY2018 projects. The contract was not set aside and was issued under the EPA's Remedial Acquisition Framework, which is a multiple-award indefinite delivery/indefinite quantity (IDIQ) vehicle that Ch2M Hill holds for design and engineering services at contaminated Superfund sites....
- The Environmental Protection Agency Region 9 awarded a $110,866.92 time-and-materials delivery order contract to CH2M Hill, Inc. for architect-engineer environmental services related to the United Heckathorn Superfund Site in Richmond, California. CH2M Hill, Inc. is a for-profit subsidiary of the larger engineering firm Jacobs Engineering Group Inc. The contract, which was awarded on July 26, 2018, has a completion date of January 1, 2021 and did not use a set-aside designation. As an...
- The U.S. Environmental Protection Agency (EPA) Region 2 has awarded a Cost Plus Fixed Fee Delivery Order task order contract to CH2M Hill, Inc., a subsidiary of Jacobs Engineering Group Inc., for architectural and engineering (A-E) services related to the Gowanus Road area. The contract has a potential value of $1,997,756.00 and a completion date of May 24, 2025. The contract is not set-aside and was awarded on September 11, 2020. Under this task order, CH2M Hill will provide environmental...
- This is a federal contract award to Ch2M Hill, Inc., a subsidiary of Jacobs Engineering Group Inc., for a Remedial Action Contract 2 with the U.S. Environmental Protection Agency (EPA) Region 5. The contract, which has a ceiling value of $437,597,525.99, is a definitive, cost-plus-fixed-fee contract type with an ultimate completion date of March 14, 2021. The contract was awarded on March 15, 2006 and does not have a set-aside designation. Under this contract, Ch2M Hill provides a range of...
- Ch2M Hill, Inc., a subsidiary of Jacobs Engineering Group Inc., received a delivery order valued at $6.12 million from the Environmental Protection Agency (EPA) Region 9 on March 24, 2022, to provide technical support for the Montrose/Del Amo Multi-Site remedial project. This task order, issued under the EPA Remedial Acquisition Framework: Design and Engineering Services (DES) IDIQ contract, adds funding to CLIN 2 and will support EPA oversight activities including remedial investigation,...
- This federal contract award is an extension of the EPA Remedial Acquisition Framework: Design and Engineering Services (DES) contract, a large indefinite delivery/indefinite quantity (IDIQ) vehicle managed by the U.S. Environmental Protection Agency (EPA) Region 9. The purpose of this specific modification is to exercise Option Period 3, extending the period of performance through September 28, 2026. The prime contractor, Ch2M Hill, Inc., a subsidiary of Jacobs Engineering Group Inc., will...
- This contract award from the U.S. Environmental Protection Agency (EPA) Region 9 is for a Remedial Investigation at the Stringfellow site. The $208,479.93 Time and Materials contract was awarded to Ch2M Hill, Inc., a subsidiary of Jacobs Engineering Group Inc. The contract has no set-aside designation. Jacobs is a large, for-profit engineering firm that has received numerous federal contracts and grants, including work with the Department of Defense, NASA, and the EPA on environmental...
- EPS90804Indefinite Delivery Contract
- EPS90804-68HE0919F0031Delivery Order
The U.S. Environmental Protection Agency (EPA) Region 9 awarded a time and materials delivery order contract to CH2M Hill, Inc., a for-profit professional services firm and subsidiary of Jacobs Engineering Group Inc. The contract, valued at $387,108.18, requires CH2M Hill to provide oversight of the remedial design (RD) and related activities at the Casmalia Resources site in California, as specified in the settlement agreement, record of decision, work plans, EPA guidance, and industry standards. The contract does not have a set-aside designation and was awarded on February 25, 2019 with a completion date of March 23, 2021. Jacobs Engineering Group Inc. is the parent company of CH2M Hill, and as a prime contractor, Jacobs holds several indefinite delivery/indefinite quantity (IDIQ) contract vehicles with federal agencies, including the U.S. Army Corps of Engineers and NASA, to provide a range of environmental, engineering, and technical services.
Name | Description | Solicitation Number | FederalAgency | Type | PostedDate |
|---|---|---|---|---|---|
Remedial Action Contract (RAC) II | PR-R9-07-10101 | Environmental Protection Agency Region 9 | Award Notice 1/1 | 5/16/07, 12:00 AM |
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| P00003 | Close Out | ($166k) | 9/16/21 | |
| P00002 | Other Administrative Action | $0 | 10/9/20 | |
| P00001 | Supplemental Agreement for work within scope | $0 | 4/23/20 | |
| Not listed | Not listed | $552.9k | 2/25/19 |