National deep energy retrofit project goodfellow complex 4300 goodfellow ST. Louis, missouri project description: trane is responsible for the investigation of, and application for, all available…

Ended Awarded Last action

Contract number
GSP0613GZ0005
Awardee
Awarding agency
Obligated
$13,203,579

Award facts

Contract value 100% obligated
$13,203,579.01 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
NAICS code
541330 Engineering Services
Set-aside
No set-aside
Competition
Full and Open Competition · 14 offers Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
St. Louis, MO 63120, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Funding Only Action PO29 · Goodfellow federal complex, ST. Louis, MO this modification has been issued to complete the buyout of this espc contract. $7,379,776
Funding Only Action PO28 · Goodfellow federal complex, ST. Louis, MO modification is hereby issued to obligate $636,790.00 for payback period 8 of the energy savings performance contract. $636,790
Supplemental Agreement for work within scope PS26 · Goodfellow federal complex, ST. Louis, MO. The purpose of this modification is to incorporate the following clause: 52.223-99 ensuring adequate covid-19… $0
Funding Only Action PO25 · Goodfellow federal complex, ST, louis, MO modification is hereby issued to obligate $622,759.00 for payback period 07 of the energy savings performance… $622,759
Supplemental Agreement for work within scope PS24 · Non-IDV section 889 modification. $0
Other Administrative Action PA23 · Goodfellow federal complex, 4300 goodfellow blvd, ST. Louis, MO. PA19 is issued to correct funding code internally and add a digit. $0
Funding Only Action PO22 · Modification PO18 is hereby issued to obligate $595,667.00 for payback period 06 of the espc at the goodfellow federal complex, 4300 goodfellow blvd., ST.… $609,054
Funding Only Action PO21 · 1. Modification PO17 is hereby issued to obligate $595,667.00 for payback period 05 of the espc at the goodfellow federal complex, 4300 goodfellow blvd., ST.… $595,667
Funding Only Action PO20 $582,591
Funding Only Action PO19 · Goodfellow federal complex, ST. Louis, MO espc contract (energy usage improvements) 1. Modification PO15 is hereby issued to obligate $569,818.00 for payback… $569,818
Other Administrative Action PS14 · Goodfellow federal complex, ST. Louis, MO this modification is issued to update the goodfellow federal complex contract environmental conditions language. $0
Funding Only Action PO12 · Goodfellow federal complex, ST. Louis, MO espc contract (energy usage improvements) 1. Modification P012 is hereby issued to obligate $557,340 for payback… $557,340
Supplemental Agreement for work within scope PS13 · Goodfellow federal complex, ST. Louis, MO the modification documents the final reconciliation of changes made under the espc project for this site. $0
Other Administrative Action PS11 · For other functions - incorporate the occu-TEC report titled "asbestos air, lead air, and lead dust investigation reportr" dated march 4, 2016 into the espc… $0
Supplemental Agreement for work within scope PO10 · For other functions - incorporate additional environmental language at the goodfellow complex, 4300 goodfellow, ST. Louis, MO $0
Other Administrative Action PO07 · For other function - no cost modification to incorporate environmental language at the goodfellow federal complex, 4300 goodfellow blvd, ST. Louis, MO $0
Other Administrative Action PO06 $27,852
Other Administrative Action PA05 $0
Other Administrative Action PO04 · Nation deep energy retofit project, goodfellow federal complex, 4300 goodfellow blvd., ST. Louis, MO - modification PO04 is issued to pay trane u.s, INC. (DBA… $207,516
Funding Only Action PO03 · National deep energy retrofit project, goodfellow federal complex, 4300 goodfellow blvd. ST. Louis, MO this modification is to account for and fund the 1ST year… $545,151
Other Administrative Action PA02 · Nation deep energy retofit project, goodfellow federal complex, 4300 goodfellow blvd., ST. Louis, MO this modification has two changes; 1. Assignment of… $0
Other Administrative Action PA01 $0
Original award $869,265
Show all 23

Description

National deep energy retrofit project goodfellow complex 4300 goodfellow ST. Louis, missouri project description: trane is responsible for the investigation of, and application for, all available system benefit, standard offer program, or other financial incentives or rebates that may be available to GSA for the projects or energy conservation measures (ecms) implemented. Trane will coordinate with any applicable authority including utility, state agency, commission, or local authority as required to capture the benefit of such incentives or rebates for the project. Trane shall also be responsible for any interconnection agreements or other agreements that are required to connect solar, wind, or other renewable energy ecms, including net metering or tariff agreements.

Quick answers

Who was awarded contract GSP0613GZ0005?

GSP0613GZ0005 was awarded to Trane U.s. Inc. by Region 6 (Public Buildings Service) on September 30, 2013.

How much is contract GSP0613GZ0005 worth?

The government has obligated $13,203,579 on GSP0613GZ0005.

Is contract GSP0613GZ0005 an order under another contract?

Yes. GSP0613GZ0005 is a delivery order under DEAM3609GO29044, an indefinite delivery contract, on DOE Energy Savings Performance Contracts 2008-2019 (ESPC).

Was contract GSP0613GZ0005 competed?

The extent of competition for GSP0613GZ0005 was full and open competition. The government received 14 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award