Delivery Order AID669I1700004-72066919F00001
Award Date 8/5/19
Potential Completion Date 9/8/22
Potential Value $268K
Federal Agency
Awardee
Ultimate Awardee
Not listed NAICS Category
Federal Contract Vehicle
Set-Aside Type
No Set-Aside Used
Extent Competed
Full and Open Competition after exclusion of sources
Major Defense Program
Not listed Pricing Type
Firm Fixed Price
Place of Performance
Enterprise Square, Corner of Front and, Nelson St, Monrovia, Liberia
Solicitation Procedures
Multiple Award, Fair Opportunity
Number Of Offers Received
5
Legislative Mandate
Not listed National Interest Action
Not listed Research Type
Not listed Primary Consortia Member
Not listed Similar Awards
- This is a firm fixed price delivery order awarded by the U.S. Agency for International Development (USAID) Liberia to Solid Rock Investment Inc., a minority-owned business, for the repairs of the St. Paul River Bridge to Zorzor section (Lot #2) of the Emergency Maintenance Road Works Project in Bong and Lofa Counties, Liberia. The contract has a potential value of $1,145,031.95 and a completion date of April 30, 2018. It is not set aside for any particular business type. The contract was awarded...
- This is a $565,486.68 Firm Fixed Price delivery order awarded by the U.S. Agency for International Development (USAID) to Solid Rock Investment Inc. for the rehabilitation of the Waka Town-Jonny Tutu Road (7.125 km) in Grand Bassa, Liberia. The award is part of the USAID Liberia Roads and Vertical Structures contract vehicle and is for construction works under the Roads and Vertical Structures program. The award has an ultimate completion date of October 27, 2018 and does not have a set-aside...
- This federal contract was awarded by the U.S. Agency for International Development (USAID) to SAM Shawki Fawaz Entrepreneur Inc., a for-profit organization, to rehabilitate three sections of farm-to-market roads in Bong County, Liberia. The contract, which has a potential value of $481,457.01, is a Firm Fixed Price Delivery Order under the USAID Liberia Roads and Vertical Structures Master IDIQ (Indefinite Delivery/Indefinite Quantity) contract. The contract does not have a set-aside...
- The U.S. Agency for International Development (USAID) Liberia has awarded a Firm Fixed Price Delivery Order contract to Westwood Corporation, a for-profit organization, for the construction of a borewell at the new LIPA building and a lined drain at the sealed roads in Gbarnga and Ganta cities in Liberia. The contract, which has a potential value of $290,638.00, is part of the USAID Liberia Roads and Vertical Structures major program and does not have a set-aside designation. The contract was...
- The U.S. Agency for International Development (USAID) awarded a firm fixed-price delivery order to 21st Century Engineering & Construction Company for the construction of a girls' dormitory and water and sanitation facilities in Liberia. The $276,847.58 contract is part of the USAID Liberia Roads and Vertical Structures program and is intended to increase equitable access for visually impaired learners through the new dormitory and WASH facility. The award did not use a set-aside, and the...
- This federal contract award, valued at $794,982.41, was issued by the United States Agency for International Development (USAID) Liberia to B And Sons Transport / Construct Ion Services, Inc., a non-profit organization. The contract is for the emergency maintenance of the Gbarnga to St. Bridge Road in Bong County, Liberia, under the USAID Liberia Roads and Vertical Structures contract vehicle. The contract type is a Firm Fixed Price Delivery Order, with a completion date of May 31, 2018. The...
- This firm fixed price delivery order was awarded by the U.S. Agency for International Development (USAID) Liberia to SAM Shawki Fawaz Entrepreneur Inc., a for-profit organization, for the emergency maintenance of the Zorzor to Voinjama road. The $1,878,328.95 contract is part of USAID's Liberia Roads and Vertical Structures master IDIQ contract, which funds the construction and maintenance of roads and vertical structures. The award does not have a set-aside designation and was made on April 19,...
- This is a firm fixed-price delivery order awarded by the U.S. Agency for International Development (USAID) Liberia to SAM Shawki Fawaz Entrepreneur Inc., a for-profit organization, for emergency road maintenance and improvement works on the Voinjama-Foya Road in Liberia. The contract, valued at $1,197,243.73, is part of USAID's larger Liberia Roads and Vertical Structures contract vehicle and is focused on ensuring vehicular access between the two cities during the rainy season. The work...
- This is a Federal contract award made by the U.S. Agency for International Development (USAID) to Phoenicia Architecture & Construction, a for-profit organization. The contract, valued at $321,942.24, is a Definitive Contract with a Firm Fixed Price pricing type. The purpose of the contract is to design and create a positive public image of the USAID Sorlumba Biomass Energy Project in Liberia, which is intended to provide assistance to the communities of Liberia. The contract does not have a...
- This is a firm fixed-price definitive contract awarded by the U.S. Mission in Liberia, a civilian agency, to Stable Outcomes Liberia Incorporated, a woman-owned small disadvantaged business. The contract, valued at $306,772.00, is for the Kwendin Biomass Energy Project PP-03, which aims to create a positive public image of the United States Agency for International Development (USAID) program in Liberia. The contract does not have a set-aside designation and is scheduled for completion on...
- USAID Liberia Roads and Vertical StructuresMaster IDIQ
- AID669I1700004Indefinite Delivery Contract
- AID669I1700004-72066919F00001Delivery Order
This federal contract was awarded by the U.S. Agency for International Development (USAID) Liberia to Solid Rock Investment Inc. to construct a Forest Conservation Hall at the Liberia Forest Training Institute. The contract is a Firm Fixed Price Delivery Order under the USAID Liberia Roads and Vertical Structures master IDIQ contract, with a potential value of $268,075.68. The contract does not have a set-aside designation and the period of performance runs through September 8, 2022. This award supports USAID's high-level program for Roads and Vertical Structures Construction Works in Liberia.
Generated 3/21/24, 8:18 PM
Name | Description | Solicitation Number | FederalAgency | Type | PostedDate |
|---|---|---|---|---|---|
The purpose of this contract is to provide construction services for road and general vertical infrastructure works throughout Liberia. | SOL-669-16-000006 | US Agency for International Development Liberia | Solicitation 1/1 | 8/12/16, 10:49 AM |
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| P00007 | Other Administrative Action | ($3k) | 9/8/22 | |
| P00006 | Change Order | $0 | 7/28/21 | |
| P00005 | Other Administrative Action | $0 | 6/28/21 | |
| P00004 | Other Administrative Action | $0 | 5/24/21 | |
| P00003 | Change Order | $16.7k | 3/18/21 |