Recovery - task order for engineering services to restore degraded fishways (i.e. fish ladders) to allow herring and other fish to move to and from upstream spawning areas. There are three fishway…

Ended Awarded Last action

Contract number
AG1320D100016
Awardee
Awarding agency
Obligated
$442,349

Award facts

Opportunity
Contract value 100% obligated
$442,349.00 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
NAICS code
541310 Architectural Services
Set-aside
No set-aside
Competition
Full and Open Competition · 1 offer Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Golden, CO, USA

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Other Administrative Action 8 · This is to decrease work on some projects and increase work on the remaining projects $0
Other Administrative Action 6 · This is an arra order and this modification is to add the arra full text clause. $0
Other Administrative Action 5 · This is for a performance time extension only. $0
Other Administrative Action 4 $0
Funding Only Action 3 · Due funding overide clarification communication delays this MOD was originally MOD #2, but due to lack of time MOD two was changed, therefore most of the… $10,399
Change Order 2 · Task order for engineering services to restore degraded fishways (i.e. fish ladders) to allow herring and other fish to move to and from upstream spawning… $0
Supplemental Agreement for work within scope 1 · Recover this modification added two additional sites 1)lower red brook fishway design and 2) pilgrim lake fishway design. Both are within the scope of work of… $200,000
Original award $231,950

About this award

This is a firm fixed-price delivery order contract awarded by the Northeast Region of the U.S. Department of Agriculture to Kleinfelder Inc., a for-profit organization, to provide engineering services to restore degraded fishways (i.e., fish ladders) in three locations in Barnstable County, Massachusetts. The purpose is to allow herring and other fish to move to and from upstream spawning areas. The total ceiling value of the contract is $442,349.00, and the ultimate completion date is September 30, 2012. This contract is part of the RECOVERY - NATIONWIDE ARCHITECT AND ENGINEERING SERVICES FOR DAMS major program, and no set-aside was used.

Description

Recovery - task order for engineering services to restore degraded fishways (i.e. fish ladders) to allow herring and other fish to move to and from upstream spawning areas. There are three fishway design projects that are located in three towns in barnstable county (cape COD), massachusetts, for this task order. The massachusetts department of fish & game, division of marine fisheries (DMF), has determined these sites need work and has identified the remedial work required. The three sites include: marston mills river fish run barnstable (BA-FP-MMR-2010-4) lower red brook fishway bourne (BO-FP-RB-2) cedar lake falmouth (FA-FP-CL-1)

Quick answers

Who was awarded contract AG1320D100016?

AG1320D100016 was awarded to Kleinfelder Inc. by Northeast Region (National Resources Conservation Service) on September 20, 2010.

How much is contract AG1320D100016 worth?

The government has obligated $442,349 on AG1320D100016.

Is contract AG1320D100016 an order under another contract?

Yes. AG1320D100016 is a delivery order under AG3A75C090020, an indefinite delivery contract.

Was contract AG1320D100016 competed?

The extent of competition for AG1320D100016 was full and open competition. The government received 1 offer.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award