Delivery Order AG0261C120011-AG0261D120072

Award Date 8/23/12
Potential Completion Date 8/22/13
Potential Value $13K
Ultimate Awardee
Not listed
Federal Contract Vehicle
Set-Aside Type
Total Small Business
Extent Competed
Full and Open Competition after exclusion of sources
Major Defense Program
Not listed
Pricing Type
Firm Fixed Price
Place of Performance
Boise, ID 83709, USA
Solicitation Procedures
Negotiated Proposal / Quote
Number Of Offers Received
5
Legislative Mandate
Davis Bacon Act
National Interest Action
Not listed
Research Type
Not listed
Primary Consortia Member
Not listed
Similar Awards
The U.S. Department of Agriculture Forest Service awarded a $16,409.25 firm fixed price delivery order to Michael Baird Construction, LLC, a small business prime contractor, for additional site work at the Elk Creek location. This task order was set aside for small businesses and was issued under the Forest Service's regional maintenance, construction, and emergency response programs. Michael Baird Construction, LLC is an experienced provider of construction, repair, and remodeling services to...
Michael Baird Construction, LLC was awarded a firm fixed price delivery order against an indefinite delivery vehicle to perform sewer repairs at a Forest Service warehouse in Boise, Idaho. Valued at $11,198.14, the task order was issued by the Department of Agriculture's Forest Service Intermountain Region under its maintenance program. As a small business prime contractor, Michael Baird will complete the work by May 15, 2015 to support the agency's infrastructure improvement goals. Michael...
Michael Baird Construction, LLC was awarded a $13,808 firm fixed price delivery order against its indefinite delivery vehicle with the U.S. Department of Agriculture Forest Service. The delivery order, AG-0261-C-13-0005 BNF MAINT TASK ORDER #021, is for landmark office maintenance tasks to be performed in Boise, Idaho by June 17, 2015. As a prime contractor, Michael Baird Construction holds two active IDVs with the Forest Service worth a combined potential value of $14 million to provide ongoing...
This is a firm-fixed price delivery order awarded by the Department of Agriculture Forest Service R4-Intermountain Region to Michael Baird Construction, LLC, a limited liability company, for roof replacements on ranger and fire management officer houses at the D6-L KRASSEL Ranger District in McCall, Idaho. The contract has a potential value of $134,385.49 and was completed on April 23, 2019. Michael Baird Construction is an experienced prime contractor that has performed a variety of facility...
This $596,979.92 firm fixed price delivery order was awarded by the U.S. Department of Agriculture Forest Service to Michael Baird Construction, LLC, a for-profit limited liability company, to remodel the Stanley Ranger Station in Stanley, Idaho. The work includes installing a security system at the ranger station and replacing flooring at the Northfork facility. Michael Baird Construction is an experienced prime contractor for the Forest Service, having completed a variety of facility...
This federal contract award, with ID 1240LR21D0001|1240LT23F0008, was issued by the U.S. Department of Agriculture Forest Service, Intermountain Region, to Michael Baird Construction, LLC, a for-profit limited liability company based in Cambridge, Idaho. The $378,701.38 fixed-price delivery order contract is for the GAOA-D4 BURGDORF GS DM PHASE 2 project, which involves deferred maintenance work at the Burgdorf Guard Station. The contract has no set-aside designation. Michael Baird Construction,...
This task order for the Elk Creek Building Rehabilitation project was awarded to Michael Baird Construction, LLC, a small business prime contractor. The $15,396.89 firm fixed price contract was issued by the United States Department of Agriculture (USDA) Forest Service's Intermountain Region. The work involves construction, repair, and remodeling services to support the Forest Service's facility improvement and deferred maintenance goals across National Forests and Grasslands in Idaho and...
This firm fixed price delivery order for $15,499.94 was awarded by the U.S. Department of Agriculture Forest Service to Michael Baird Construction, LLC on March 10, 2015. The order is being issued under Task Order #025 of the agency's Third Fork Well maintenance tasking contract to replace the existing pump at the well. The work will be performed in Boise, Idaho with a completion date of May 15, 2015. Michael Baird Construction holds two additional indefinite delivery vehicles with the Forest...
This federal contract award, valued at $81,830.58, was made by the U.S. Department of Agriculture Forest Service, Region 4 - Intermountain Region, to Michael Baird Construction, LLC, a small business prime contractor. The contract is for lead-based paint (LBP) removal and abatement work, with a completion date of September 30, 2018. Michael Baird Construction, LLC specializes in construction, repair, and remodeling services for federal agencies, particularly the Forest Service, and has performed...
The Department of Agriculture Forest Service awarded a $221,848.65 firm fixed price delivery order contract to Michael Baird Construction, LLC, a small business contractor, for the Krassel District Office Roof Remodel project in McCall, Idaho. This work is being performed under the Forest Service's regional maintenance, construction, and emergency response programs. Michael Baird Construction holds multiple active indefinite delivery vehicles with the Forest Service Intermountain Region, with...
  • AG0261C120011
    Indefinite Delivery Contract
  • AG0261C120011-AG0261D120072
    Delivery Order

This is a firm fixed price delivery order awarded by the U.S. Department of Agriculture Forest Service to Michael Baird Construction, LLC, a limited liability company, for maintenance work at the Lester Creek Guard Station in Boise, Idaho. The contract, valued at $13,108.59, was set aside for small business firms. Michael Baird Construction, a construction, repair, and remodeling services provider, has previously held multiple prime contracts with the Forest Service across the Intermountain Region to perform facility improvements, infrastructure maintenance, and hazardous tree removal projects at national forests and grasslands. The work under this delivery order likely supports the agency's deferred maintenance and recreation infrastructure goals. Additionally, Michael Baird Construction holds two active indefinite delivery contracts with the Forest Service's Intermountain Region, valued up to $14 million combined, to provide ongoing construction, repair, and demolition services.

Generated 6/5/24, 10:00 AM