Delivery Order 75N99020D00023-75N99026F00005
Award Date 5/11/26
Potential Completion Date 11/7/26
Potential Value $30K
Funding Federal Agency
Contracting Federal Agency
Ultimate Awardee
Not listed NAICS Category
PSC Category
Set-Aside Type
No Set-Aside Used
Federal Contract Vehicle
- Not listed
Extent Competed
Full and Open Competition
Major Defense Program
Not listed Pricing Type
Firm Fixed Price
Place of Performance
Poolesville, MD 20837, USA
Solicitation Procedures
Multiple Award, Fair Opportunity
Number Of Offers Received
3
Legislative Mandate
Service Contract Act
National Interest Action
Not listed Research Type
Not listed Primary Consortia Member
Not listed Similar Awards
- The National Institute of Diabetes and Digestive and Kidney Diseases issued a $56,791 delivery order to RMF Engineering, Inc., P.C. on March 2, 2026, under the NIH Architect Engineering MATOC for test and inspection services related to a solar array panel inverter fire investigation and remediation study. The NIH Architect Engineering MATOC is a $400 million indefinite-delivery/indefinite-quantity contract administered by the Department of Health and Human Services that enables architecture,...
- The National Institutes of Health issued a $79,733.29 delivery order to CFR Engineering Consultants, Inc. on July 31, 2024, under the NIH AE MATOC for a data center renovation study in Building 10, Rooms B1D513 and B1D511. The NIH AE MATOC is a multiple-award indefinite-delivery contract supporting architectural and engineering services for NIH facilities. Place of performance is Bethesda, Maryland. The order is set aside for total small business. Ultimate completion date is May 20, 2025. The...
- The National Institutes of Health issued a $78,470.56 delivery order to CFR Engineering Consultants, Inc. on January 21, 2026, under the NIH AE MATOC for commissioning authority services at Building 37 in Bethesda, Maryland. The NIH AE MATOC is a multiple-award indefinite delivery contract for architectural and engineering services across NIH facilities. Performance is at Bethesda, MD 20892, with an ultimate completion date of July 21, 2026. The order is priced on a firm fixed price basis. CFR...
- The National Institutes of Health issued a $70,364 delivery order to Global Engineering Solutions, Inc. on October 1, 2025, under the NIH Architect Engineering MATOC for commissioning services on the Building 31A 6th Floor renovation project. The NIH Architect Engineering MATOC is a $400 million indefinite-delivery, indefinite-quantity contract vehicle supporting architectural, engineering, construction quality management, and commissioning services across NIH facilities. Place of performance is...
- NIH Construction issued a delivery order to Global Engineering Solutions, Inc. on August 24, 2021, under the NIH Architect Engineering MATOC for design services supporting renovation of Building 5, Lab B1-38 and Office B1-38A at the National Institute of Diabetes and Digestive and Kidney Diseases facility. The order ceiling is $139,951.27, firm fixed price. The NIH Architect Engineering MATOC is a $400 million indefinite-delivery, indefinite-quantity vehicle supporting architectural,...
- The National Institutes of Health issued a $135,230 delivery order to Global Engineering Solutions, Inc. on September 30, 2025, under the NIH Architect Engineering MATOC for commissioning services supporting Building 5 building envelope repairs at the NIH campus in Bethesda, Maryland. The NIH Architect Engineering MATOC is a $400 million indefinite-delivery, indefinite-quantity vehicle for architectural, engineering, and construction quality management services across NIH facilities. Place of...
- The National Institutes of Health issued a delivery order to Global Engineering Solutions, Inc. on April 15, 2026, with a ceiling value of $49,387 under the NIH Architect Engineering MATOC for commissioning support services at its Bethesda, Maryland campus. The NIH Architect Engineering MATOC is a $400 million indefinite-delivery, indefinite-quantity vehicle for architectural, engineering, construction quality management, commissioning, and facility assessment services. This delivery order...
- The National Institutes of Health issued a $44,528.14 delivery order to Summer Consultants, Inc. on August 14, 2024, under the NIH Architect Engineering MATOC for commissioning services supporting laboratory renovation and hibernaculum installation in Building 49. The NIH Architect Engineering MATOC is a standing vehicle for architect-engineer services across multiple NIH campuses. Place of performance is Bethesda, Maryland. The order carries a firm fixed price and an ultimate completion date of...
- The National Institutes of Health issued a $81,567.84 delivery order to CFR Engineering Consultants, Inc. on February 8, 2023, under the NIH AE MATOC for design services of an exhaust system static pressure design in Building T10B. The NIH AE MATOC is a multiple award indefinite delivery contract. Place of performance is Bethesda, Maryland. The order is firm fixed price with an ultimate completion date of October 8, 2023. CFR Engineering Consultants is a small business specializing in...
- The National Institutes of Health issued a delivery order to Global Engineering Solutions, Inc. on May 19, 2025, with a ceiling value of $16,876.00, under the NIH Architect Engineering MATOC for commissioning services on Building 49 variable frequency drive replacement. The NIH Architect Engineering MATOC is a $400 million indefinite-delivery, indefinite-quantity vehicle supporting architectural, engineering, construction quality management, commissioning, and facility assessment services across...
- 75N99020D00023Indefinite Delivery Contract
- 75N99020D00023-75N99026F00005Delivery Order
The National Institute of Diabetes and Digestive and Kidney Diseases issued a $30,032 delivery order to CFR Engineering Consultants, Inc. on May 11, 2026, under the NIH AE MATOC for commissioning services on Building 49 renovations at Poolesville, MD. The NIH AE MATOC is a multiple-award indefinite-delivery task order contract supporting architectural and engineering services across NIH facilities. Commissioning is a critical function to the Building 49 renovations. Ultimate completion date is November 7, 2026. The order is priced on a firm fixed price basis with no set-aside.
Generated 6/26/26, 9:56 AM
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| Not listed | Not listed | $30.0k | 5/11/26 |