The overall goal of this multi-phase project is to establish a practical procedure, employing automated processes, to monitor track geometry measurements to identify locations with large deviations…
Ended Awarded Last action
- Contract number
- 693JJ618F000165
- Awardee
-
Ensco Inc. UEI DP3FAQE2UGT3
- Awarding agency
-
Federal Railroad Administration
Department of Transportation
- Obligated
- $688,144
Award facts
- Contract value 100% obligated
- $688,144.00 Current and potential, with all options
- Completion date 100% complete
- Current and potential, with all options
- Contracting staff
- NAICS code
- 541715 Research and Development in the Physical, Engineering, and Life Sciences (except Nanotechnology and Biotechnology)
- Set-aside
- No set-aside
- Competition
- Full and Open Competition · 1 offer Multiple Award, Fair Opportunity
- Pricing
- Cost Plus Fixed Fee
- Place of performance
- North Springfield, VA 22151, USA
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $320,845 | |
| Funding Only Action | $217,336 | |
| Original award | $149,963 |
About this award
This federal contract was awarded by the Department of Transportation Federal Railroad Administration to Ensco Inc., doing business as Enscohi, to establish a practical procedure using automated processes to monitor track geometry measurements and identify locations with excessive degradation. The major objectives are to detect, monitor, and report deviations in track geometry metrics that approach safety limits. The $688,144 cost-plus-fixed-fee contract is part of a larger research, development, test, and evaluation vehicle. Ensco, a for-profit technology company, has a history of providing engineering, modeling, and technology solutions to government customers including the Department of Defense and Department of Homeland Security. No set-aside designation was used for this award.
Description
The overall goal of this multi-phase project is to establish a practical procedure, employing automated processes, to monitor track geometry measurements to identify locations with large deviations that suggest excessive degradation rates. The major objectives of this joint initiative are as follows: * identify and report peak-value deviations in track geometry measures, namely profile, alignment, cross-level, warp, twist and gage, that equal or exceed metro-north railroad's (mnrr) maintenance-level thresholds; * continuously monitor the size and growth rate of these identified deviations; * report appropriate severity levels of the track geometry deviations as they approach FRA safety limits or if they are predicted to exceed a safety limit before the next geometry measurement based on the projected rate of increase; * publication of technical reports providing detailed physical explanations that are non-code specific, such that they are capable of being adopted throughout the rail industry.
Quick answers
Who was awarded contract 693JJ618F000165?
693JJ618F000165 was awarded to Ensco Inc. by Federal Railroad Administration (Department of Transportation) on September 28, 2018.
How much is contract 693JJ618F000165 worth?
The government has obligated $688,144 on 693JJ618F000165.
Is contract 693JJ618F000165 an order under another contract?
Yes. 693JJ618F000165 is a delivery order under 693JJ618D000005, an indefinite delivery contract, on Research Development Test and Evaluation.
Was contract 693JJ618F000165 competed?
The extent of competition for 693JJ618F000165 was full and open competition. The government received 1 offer.
On GovTribe
See this award's full record