Hidden lane landfill superfund site

Active Awarded Last action

Contract number
68HE0321F0004
Awardee
Awarding agency
Obligated
$631,638

Award facts

Opportunity
  • 68HE0320Q0038 Solicitation number
Contract value 100% obligated
$631,637.76 Current and potential, with all options
Completion date 86% complete
Current and potential, with all options
NAICS code
562910 Remediation Services
Set-aside
No set-aside
Competition
Full and Open Competition · 1 offer Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Sterling, VA 20165, USA

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Other Administrative Action P00017 · This modification extends the period of performance end date from october 25, 2025 to october 25, 2027 to support the remaining DOR services throughout the… $167,201
Exercise an Option P00016 · This modification exercises option year 4 and adds funds in the amount of $77,591.79 for RD implementation support for designer of record for the waterline RA… $77,592
Funding Only Action P00015 · This modification adds funds for RD implementation support for designer of record for the waterline RA at hidden lane landfill (03MN) OU02 site. $37,841
Other Administrative Action P00014 · This modification changes the primary COR/invoice approver from andreen macfarlane to samir subedi. $0
Other Administrative Action P00013 · This modification changes the primary task order contracting officer's representative (tocor) from austin oelschlager to IAN stewart. Furthermore, the alternate… $0
Other Administrative Action P00012 · This modification changes the COR/invoice approver from lorenzo choudhary-smith to andreen macfarlane. $0
Other Administrative Action P00011 · This modification changes the primary project officer (PO) from lorenzo choudhary-smith to andreen macfarlane. $0
Exercise an Option P00010 · This modification exercises option year 3 from 10/26/2023 to 10/25/2025 and adds funding in the amount of $59,155.82 and changes the tocor from eric charlier to… $59,156
Other Administrative Action P00009 $0
Other Administrative Action P00008 · The purpose of this modification is to extend the base year period of performance end date from 25 OCT 2021 to 25 OCT 2023 and shift funds from option years 1… $0
Other Administrative Action P00007 · The purpose of this modification is to change the tocor (task order contracting officer's representative) from chris vallone to eric charlier. $0
Exercise an Option P00006 · The purpose of this modification is to exercise option year 2 and add funds in the amount of $57,485.63. In addition, the period of performance (POP) end… $57,486
Funding Only Action P00005 · The purpose of this modification is to add funds in the amount of $94,409.20. All other terms and conditions remain unchanged. $0
Other Administrative Action P00004 $0
Change Order P00003 · The purpose of modification P00003 is to process a change order to the task order to extend the POP to 10/25/2025, revise the SOW and add new clins. All other… $50,027
Exercise an Option P00002 · The purpose of modification P00002 is to exercise and incrementally fund option period one of the task order and to extend the POP of line item 6.6.1. All other… $10,663
Other Administrative Action P00001 · The purpose of this modification is to incorporate the attached EPA blanket administrative modification signed by raoul scott on july 30, 2020 and to… $0
Original award $171,673
Show all 18

About this award

This is a modification to a delivery order awarded by the Environmental Protection Agency (EPA) Region 3 under the EPA Remedial Acquisition Framework: Design and Engineering Services (DES) contract. The $631,637.76 contract was originally awarded on October 26, 2020 to EA Engineering, Science, and Technology, Inc., PBC, a for-profit environmental consulting firm. This modification extends the period of performance by 2 years to October 25, 2027 and adds $167,200.74 in additional funding to support the remaining design, oversight, and remediation services for the Hidden Lane Landfill Superfund site cleanup in Sterling, Virginia. The contract is a firm fixed-price delivery order and does not have a set-aside designation.

Subawards

Subcontractor Amount Awarded
Bowman Consulting Group LTD THIS MODIFICATION CHANGES THE PRIMARY TASK ORDER CONTRACTING OFFICER'S REPRESENTATIVE (TOCOR) FROM AUSTIN OELSCHLAGER TO IAN STEWART. FURTHERMORE, THE ALTERNATE… $65,900

Quick answers

Who was awarded contract 68HE0321F0004?

68HE0321F0004 was awarded to EA Engineering, Science, And Technology, Inc., PBC by EPA Region 3 (Regional Offices) on October 26, 2020.

How much is contract 68HE0321F0004 worth?

The government has obligated $631,638 on 68HE0321F0004.

Is contract 68HE0321F0004 an order under another contract?

Yes. 68HE0321F0004 is a delivery order under 68HE0318D0005, an indefinite delivery contract, on EPA Remedial Acquisition Framework: Design and Engineering Services (DES).

Was contract 68HE0321F0004 competed?

The extent of competition for 68HE0321F0004 was full and open competition. The government received 1 offer.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award