The purpose of this task order is to provide oversight of the early remedial design (RD) and partial consent decree (PCD) remedial action (RA) activities at the chevron questa mine site (site)

Active Awarded Last action

Contract number
68HERH21F0042
Awardee
Awarding agency
Obligated
$2,088,312

Award facts

Opportunity
  • 68HERH20Q0082 Solicitation number
Contract value 100% obligated
$2,088,312.37 Current and potential, with all options
Completion date 84% complete
Current and potential, with all options
NAICS code
562910 Remediation Services
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 7 offers Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Reston, VA 20190, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Exercise an Option P00017 · Exercise option and obligation incremental funding. $349,849
Other Administrative Action P00016 · The purpose of this modification is to add oliver bernal as the alternate tocor for region 6 ESO task order title: chevron questa mine site. $0
Exercise an Option P00015 · ESO task order title: chevron questa mine site the purpose of this modification is to exercise the option from november 22, 2025 to november 21, 2026 using FY25… $456,449
Other Administrative Action P00014 · ESO task order title: chevron questa mine site MOD 14 - change primary invoice approving official to jason breech $0
Exercise an Option P00013 · ESO task order title: chevron questa mine site $448,293
Supplemental Agreement for work within scope P00012 · ESO task order title: chevron questa mine site modification no. P00012 is for supplemental agreement for work within scope $142,999
Exercise an Option P00011 · ESO task order title: chevron questa mine site the purpose of modification no. P00011 is to exercise and fully fund option period 3. $172,460
Other Administrative Action P00010 · ESO task order title: chevron questa mine site the purpose of this modification is to issue administrative changes (invoice approvers). $0
Exercise an Option P00009 · RAF ESO task order title: chevron questa mine site (site) the purpose of modification no. 9 is to exercise and fully fund option period 2. $170,078
Funding Only Action P00007 · This modification hereby DE-obligates the funding and expenditure limits by $168,464.02 from $348,184.01 to $179,719.99 total task order funding. Funding is… -$168,462
Funding Only Action P00008 · This modification hereby RE-obligates the funding and expenditure limits by $168,464.02 from $179,719.99 to $348,184.01 total task order funding. $168,462
Other Administrative Action P00006 · This modification is hereby issued to approve the remedial action letter dated january 13, 2022 request for change in key personnel assigned project manager… $0
Other Administrative Action P00005 · The purpose of this task order modification is to correct the period of performance on page 2 of modification #P00004 dated 11/03/2021 due to a typographic… $0
Exercise an Option P00004 · The purpose of this task order modification is to exercise option 1 and provide funding and increase expenditure limits in the amount of $168,462.02 from… $168,462
Other Administrative Action P00003 · The purpose of this task order modification is to change the contracting officer from latrice haggerty to chanel colbert. $0
Other Administrative Action P00002 · The purpose of this task order modification is to delegates henry thompson as invoice payment official and chanel colbert as administrative contract… $0
Other Administrative Action P00001 · The purpose of this task order modification request is to change project site number from 06DLBE01 to 06DLBE00. $0
Original award $179,722
Show all 18

About this award

EPA Region 6 issued a delivery order to Hydrogeologic, Inc., a minority-owned Asian-Pacific American small business, on November 22, 2020, with a ceiling value of $2,088,312.37 under the EPA Remedial Acquisition Framework: Environmental Services and Operations (ESO) for oversight of early remedial design and partial consent decree remedial action activities at the Chevron Questa Mine Site.

The order is set-aside for Total Small Business and carries a firm fixed-price structure. Place of performance is Reston, VA. Ultimate completion is scheduled for November 21, 2027.

Service Contract Inventory reporting on this order shows a labor footprint that scaled from 0.1 FTEs and 142 contractor hours in FY2021 ($60 thousand invoiced) to 0.4 FTEs in FY2025 ($201 thousand invoiced). Derived government-paid hourly rates declined across the period, averaging $424.50/hr in FY2021, dropping to $86.41/hr in FY2023, and recovering to $238.76/hr in FY2024. In FY2025, Hydrogeologic self-performed all reported work with no subcontractors engaged.

Quick answers

Who was awarded contract 68HERH21F0042?

68HERH21F0042 was awarded to Hydrogeologic, Inc. by EPA Region 6 (Regional Offices) on November 22, 2020.

How much is contract 68HERH21F0042 worth?

The government has obligated $2,088,312 on 68HERH21F0042. Its current value, with exercised options, is $2,088,312.

Is contract 68HERH21F0042 an order under another contract?

Yes. 68HERH21F0042 is a delivery order under 68HE0118D0006, an indefinite delivery contract, on EPA Remedial Acquisition Framework: Environmental Services and Operations (ESO) (ESO).

Was contract 68HERH21F0042 competed?

The extent of competition for 68HERH21F0042 was full and open competition after exclusion of sources. The government received 7 offers. It was set aside: Total Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award