IRS 7TH floor buildout, edith green-wendell wyatt federal building, portland or

Ended Awarded Last action

Contract number
47PL0125F0017
Awardee
Awarding agency
Obligated
$432,226

Award facts

Opportunity
  • EQ10PCPD250001 Solicitation number
Contract value 100% obligated
$432,226.38 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
Funding agency
Internal Revenue Service Department of the Treasury
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 6 offers Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Portland, OR 97204, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope PS0002 · Internal revenue service. Modification PS02 is issued to provide for necessary door hardware installation. 1220 SW 3RD AVE, portland, or 97204. $3,521
Other Administrative Action PA0001 · MOD PA0001 is required to change the contracting officer. $0
Original award $428,706

About this award

The Internal Revenue Service issued a delivery order to RJK Construction LLC on January 7, 2025, under the Region 10 Public Buildings Service South MATOC with a ceiling value of $432,226.38 for door hardware installation and buildout work at the Edith Green-Wendell Wyatt Federal Building, Portland, Oregon.

RJK Construction is an EDWOSB, 8(a) Program Participant, and WOSB. This order was issued under the Total Small Business set-aside. Place of performance is Portland, Oregon (97204). Ultimate completion is scheduled for April 3, 2026. The work is priced firm fixed price.

Mckinstry Co LLC is performing mechanical design, mechanical engineering, and fire protection services as a subcontractor. Soderstrom Architects, LTD is providing architectural design services including 35%, 65%, 95%, and 100% submittal phases and construction documents. A third subcontractor is furnishing dust containment, framing, drywall, and door frame installation work per the GSA statement of work dated November 15, 2024.

Subawards

Subcontractor Amount Awarded
Mckinstry Co LLC IRS 7TH FLOOR BUILDOUT, EDITH GREEN-WENDELL WYATT FEDERAL BUILDING, PORTLAND OR Furnish material, labor, supplies, and equipment as necessary to provide… $119,577
Soderstrom Architects, LTD IRS 7TH FLOOR BUILDOUT, EDITH GREEN-WENDELL WYATT FEDERAL BUILDING, PORTLAND OR Provide 35%, 65%, 95% & 100% Submittal and Architectural Design Services… $23,600
Subcontractor not on record IRS 7TH FLOOR BUILDOUT, EDITH GREEN-WENDELL WYATT FEDERAL BUILDING, PORTLAND OR Furnish material, labor, supplies, and equipment as necessary to provide Dust… $42,935

Quick answers

Who was awarded contract 47PL0125F0017?

47PL0125F0017 was awarded to RJK Construction LLC by Region 10 (Public Buildings Service) on January 7, 2025.

How much is contract 47PL0125F0017 worth?

The government has obligated $432,226 on 47PL0125F0017.

Which agency awarded contract 47PL0125F0017?

Region 10 (Public Buildings Service) awarded 47PL0125F0017, with funding from Internal Revenue Service (Department of the Treasury).

Is contract 47PL0125F0017 an order under another contract?

Yes. 47PL0125F0017 is a delivery order under 47PL0124D0009, an indefinite delivery contract, on Region 10 Public Buildings Service South MATOC.

Was contract 47PL0125F0017 competed?

The extent of competition for 47PL0125F0017 was full and open competition after exclusion of sources. The government received 6 offers. It was set aside: Total Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award