Fire loop replacement project at building 810 at that denver federal center in lakewood, colorado

Ended Awarded Last action

Contract number
47PJ0023F0308
Awardee
Awarding agency
Obligated
$5,912,414

Award facts

Contract value 100% obligated
$5,912,413.82 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 2 offers Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Denver, CO 80225, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Funding Only Action PA0006 · Modification to deobligate $.01 to close out contract -$0
Other Administrative Action PA0005 · Modification PA0005 is issued to change the contracting officer from sarah callies to shannon sweeney. $0
Supplemental Agreement for work within scope PS0004 · Modification PS0004 is issued to add funding for numerous potential change order requests that were submitted throughout the duration of the building 810 fire… $174,113
Other Administrative Action PA0003 · Modification PA0003 is to update the funding fixed asset VCO00107CO0624AA information from cipimp to improvmnt in the accounting lines of this award. This is an… $0
Supplemental Agreement for work within scope PS0002 · Modification PS0002 is hereby issued for scopes of work to accomplish additional work on the building 810 fire loop project at the denver federal center in… $113,051
Supplemental Agreement for work within scope PS0001 · Funding is added for $488,436.00 for change orders for the hydrant replacement, stormline repair, rail crossing removal, slurry PIT and other items for the fire… $488,436
Original award $5,136,814

About this award

GSA Public Buildings Service Region 8 issued a delivery order to Gilmore Construction Corporation on June 16, 2023, under the Public Buildings Service Region 8 MACC 2021-2026 for fire-loop replacement at Building 810 of the Denver Federal Center in Lakewood, Colorado. The order carried a ceiling value of $5.9 million and closed on December 30, 2024.

Gilmore Construction Corporation is a Denver-based, minority-owned small disadvantaged business. The order was issued under a total small business set-aside. Place of performance is Denver, CO. Work was priced on a firm fixed-price basis. The modification referenced in the award record deobligated $0.01 to close out the contract.

Quick answers

Who was awarded contract 47PJ0023F0308?

47PJ0023F0308 was awarded to Gilmore Construction Corporation by Region 8 (Public Buildings Service) on June 16, 2023.

How much is contract 47PJ0023F0308 worth?

The government has obligated $5,912,414 on 47PJ0023F0308.

Is contract 47PJ0023F0308 an order under another contract?

Yes. 47PJ0023F0308 is a delivery order under 47PJ0021D0019, an indefinite delivery contract, on Public Buildings Service Region 8 MACC 2021-2026.

Was contract 47PJ0023F0308 competed?

The extent of competition for 47PJ0023F0308 was full and open competition after exclusion of sources. The government received 2 offers. It was set aside: Total Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award