Renovation project for the 11TH floor chambers @ BOB casey federal courthouse, 515 rusk avenue, houston, TX

Ended Awarded Last action

Contract number
47PH0525F0013
Awardee
Awarding agency
Obligated
$396,940

Award facts

Opportunity
  • 47PH0524R0107 Solicitation number
Contract value 100% obligated
$396,940.25 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 1 offer Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Houston, TX 77002, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope PS0006 · To modify renovations to judge tipton 11TH floor chambers at the BOB casey federal courthouse as defined in the revised SOW dated 4/30/2026 in houston, TX. $51,163
Supplemental Agreement for work within scope PS0005 · Repair the existing main drainpipe that is causing a drainage problem in the judge's bathroom and kitchen sink at the BOB casey federal courthouse in houston,… $13,250
Supplemental Agreement for work within scope PS0004 · Extend the period of performance of this task order from december 29, 2025 to march 31, 2026. Customer took longer than originally anticipated to make some… $0
Other Administrative Action PA0003 · Update the new vendor code from 271901755 to 994318579 per GSA finance email request. $0
Supplemental Agreement for work within scope PS0002 · To provide abatement and removal services, supply cabinets, provide two additional floor power boxes, install 9 fire alarm speaker/strobes at the BOB casey… $15,570
Supplemental Agreement for work within scope PS0001 · Extend the period of performance of this task order from april 25, 2025 to august 1, 2025. The courts took longer than anticpated to provide details on the… $0
Original award $316,958

About this award

The Administrative Office of the U.S. Courts issued a delivery order to A.R.E. Design & Build, LLC, a HUBZone-certified small business, on October 30, 2024, with a ceiling value of $396,940.25 for renovation of the 11th Floor Chambers at the Bob Casey Federal Courthouse in Houston, Texas.

The order calls for modification of renovations to Judge Tipton's 11th Floor chambers as defined in the revised Statement of Work dated April 30, 2026. Place of performance is Houston, TX 77002. The ultimate completion date is June 30, 2026. The order is priced as firm fixed price with no set-aside designation applied.

Quick answers

Who was awarded contract 47PH0525F0013?

47PH0525F0013 was awarded to A.r.e. Design & Build, LLC by Region 7 (Public Buildings Service) on October 30, 2024.

How much is contract 47PH0525F0013 worth?

The government has obligated $396,940 on 47PH0525F0013.

Which agency awarded contract 47PH0525F0013?

Region 7 (Public Buildings Service) awarded 47PH0525F0013, with funding from Administrative Office of the U.S. Courts.

Is contract 47PH0525F0013 an order under another contract?

Yes. 47PH0525F0013 is a delivery order under 47PH0821D0017, an indefinite delivery contract.

Was contract 47PH0525F0013 competed?

The extent of competition for 47PH0525F0013 was full and open competition. The government received 1 offer.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award