Neal smith federal building, DES moines, IA. Renovate existing office space for the IRS on the 3RD floor and the executive office of the united states attorney (eousa) on the 4TH floor.
Ended Awarded Last action
- Contract number
- 47PG0222F0043
- Awardee
-
Boyd Jones Construction Co UEI L9GMV4Q9KWU6
- Awarding agency
-
Region 6
Public Buildings Service, General Services Administration
- Obligated
- $8,985,008
Award facts
- Contract value 100% obligated
- $8,985,007.58 Current and potential, with all options
- Completion date 100% complete
-
- Current, with exercised options
- Potential, with all options
- NAICS code
- 236220 Commercial and Institutional Building Construction
- Set-aside
- No set-aside
- Competition
- Full and Open Competition · 2 offers Multiple Award, Fair Opportunity
- Pricing
- Firm Fixed Price
- Place of performance
- Des Moines, IA 50309, USA
- Legislative mandates
-
- Davis-Bacon Act FAR subpart 22.4
- Employment Eligibility Verification (E-Verify) FAR subpart 22.18
- Service Contract Inventory FAR subpart 4.17
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Supplemental Agreement for work within scope | $8,181 | |
| Supplemental Agreement for work within scope | $59,588 | |
| Supplemental Agreement for work within scope | $3,524 | |
| Supplemental Agreement for work within scope | $22,169 | |
| Other Administrative Action | $0 | |
| Supplemental Agreement for work within scope | $3,143 | |
| Supplemental Agreement for work within scope | $4,850 | |
| Supplemental Agreement for work within scope | $5,000 | |
| Supplemental Agreement for work within scope | $1,316 | |
| Supplemental Agreement for work within scope | $1,752 | |
| Supplemental Agreement for work within scope | $8,928 | |
| Other Administrative Action | $0 | |
| Supplemental Agreement for work within scope | $8,203 | |
| Supplemental Agreement for work within scope | $4,708 | |
| Supplemental Agreement for work within scope | $9,280 | |
| Supplemental Agreement for work within scope | $297,049 | |
| Supplemental Agreement for work within scope | $14,008 | |
| Supplemental Agreement for work within scope | $19,383 | |
| Supplemental Agreement for work within scope | $35,978 | |
| Supplemental Agreement for work within scope | $1,644 | |
| Supplemental Agreement for work within scope | $4,310 | |
| Supplemental Agreement for work within scope | $83,129 | |
| Supplemental Agreement for work within scope | $5,798 | |
| Supplemental Agreement for work within scope | $4,248 | |
| Supplemental Agreement for work within scope | $3,434 | |
| Supplemental Agreement for work within scope | -$13,219 | |
| Supplemental Agreement for work within scope | $7,160 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $10,566 | |
| Supplemental Agreement for work within scope | $49,552 | |
| Supplemental Agreement for work within scope | $73,326 | |
| Other Administrative Action | $0 | |
| Other Administrative Action | $0 | |
| Original award | $8,248,000 |
Show all 34
About this award
Boyd Jones Construction Co was awarded an $8.99 million firm fixed-price delivery order on June 10, 2022, to renovate office space for the Internal Revenue Service on the third floor and the Executive Office of the United States Attorney on the fourth floor of the Neal Smith Federal Building in Des Moines, Iowa. A subsequent modification added improvements to building efficiency through additional duct and louver connections. The contract, which was scheduled for completion on June 15, 2024, was issued under the GSA Heartland Region 6 Design Build Indefinite Delivery/Indefinite Quantity program (2020-2025), a master contract vehicle with a potential value of $100 million to provide construction services across several Midwestern states. The award carried no set-aside designation and was funded through a civilian federal agency under GSA Region 6.
The delivery order engaged multiple subcontractors across various scopes of work, including Sargent Metal Fabricators Inc., Bee-Clean US Holdings LLC (Heritage Building Maintenance division), Heartland Window Treatments Inc., and Latimer Associates Inc. (Latitude Signage + Design division). As of May 30, 2023, progress on subcontracted work varied significantly, with one subcontract reported at 75 percent completion as of August 2023, while several others remained at zero percent completion, indicating ongoing execution of the renovation scope throughout the project timeline.
Subawards
| Subcontractor | Amount | Awarded |
|---|---|---|
| Corn States Metal Fabricators, Inc. | $1,143,351 | |
| Corn States Metal Fabricators, Inc. | $1,173,261 | |
| Skold Door & Floor Company Inc. | $5,300 | |
| Skold Door & Floor Company Inc. | $5,300 | |
| Subcontractor not on record | $137,074 | |
| Subcontractor not on record | $166,070 | |
| Subcontractor not on record | $84,655 | |
| Subcontractor not on record | $84,655 | |
| Sargent Metal Fabricators Inc. | $18,695 | |
| Sargent Metal Fabricators Inc. | $18,695 | |
| Bee-Clean US Holdings, LLC | $5,885 | |
| Bee-Clean US Holdings, LLC | $5,885 | |
| Subcontractor not on record | $108,910 | |
| Subcontractor not on record | $108,910 | |
| Heartland Window Treatments, Inc. | $48,034 | |
| Heartland Window Treatments, Inc. | $48,034 | |
| Heartland Window Treatments, Inc. | $48,034 | |
| Subcontractor not on record | $271,274 | |
| Subcontractor not on record | $47,394 | |
| Subcontractor not on record | $271,274 | |
| Heartland Window Treatments, Inc. | $48,034 | |
| Subcontractor not on record | $45,840 | |
| Latimer Associates, Inc. | $40,809 | |
| Latimer Associates, Inc. | $40,809 | |
| Subcontractor not on record | $559,978 | |
| Subcontractor not on record | $559,978 | |
| 1ST Interiors, Inc. | $1,176,951 | |
| 1ST Interiors, Inc. | $1,182,527 | |
| Lawrence Fabric Structures Inc. | $64,520 | |
| Architectural Arts Millwork LLC | $424,077 | |
| Lawrence Fabric Structures Inc. | $64,520 | |
| Architectural Arts Millwork LLC | $410,367 | |
| Elite Glass & Metal, LLC | $248,497 | |
| Bartlett Electric Inc. | $1,751,615 | |
| Elite Glass & Metal, LLC | $248,497 | |
| Subcontractor not on record | $160,510 | |
| Subcontractor not on record | $160,510 | |
| Bartlett Electric Inc. | $1,746,147 | |
| Corn States Metal Fabricators, Inc. | $1,143,351 | |
| Corn States Metal Fabricators, Inc. | $1,173,261 | |
| Peitzmeier Demolition And Concrete Cutting, Inc. | $235,011 | |
| Subcontractor not on record | $181,291 | |
| Subcontractor not on record | $181,291 | |
| Peitzmeier Demolition And Concrete Cutting, Inc. | $235,011 |
Show all 44
Quick answers
Who was awarded contract 47PG0222F0043?
47PG0222F0043 was awarded to Boyd Jones Construction Co by Region 6 (Public Buildings Service) on June 10, 2022.
How much is contract 47PG0222F0043 worth?
The government has obligated $8,985,008 on 47PG0222F0043.
Is contract 47PG0222F0043 an order under another contract?
Yes. 47PG0222F0043 is a delivery order under 47PG0220D0005, an indefinite delivery contract, on GSA Heartland R6 Design Build IDIQ 2020-2025.
Was contract 47PG0222F0043 competed?
The extent of competition for 47PG0222F0043 was full and open competition. The government received 2 offers.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award