This task order is for all labor and materials for the scope of work associated with installing watertight barriers at the moakley courthouse in boston, MA.

Ended Awarded Last action

Contract number
47PB0023F0200
Awardee
Awarding agency
Obligated
$1,326,449

Award facts

Opportunity
  • 47PB0023R0036 Solicitation number
Contract value 100% obligated
$1,326,449.12 Current and potential, with all options
Completion date 100% complete
  • Current, with exercised options
  • Potential, with all options
Contracting staff
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 1 offer Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Boston, MA 02210, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Other Administrative Action PA0016 · PA00016 is an admin MOD to correct the accounting strings. All other terms remain unchanged. $0
Supplemental Agreement for work within scope PS0015 · The project is extended at no-cost to 05/30/26 to complete punch list items. All other terms and conditions remain unchanged. $0
Supplemental Agreement for work within scope PS0014 · This modification extends the contract at no-cost to 02/27/2026. All other terms and conditions remain unchanged. $0
Supplemental Agreement for work within scope PS0013 · This modification extends the contract completion date to 01/08/2026 for punch-list items. All other terms and conditions remain unchanged. $0
Supplemental Agreement for work within scope PS0012 · Task order #47PB0023F0200 is extended to 11/14/2025 to allow time for the completion of the construction project. The moakley watertight door project takes… $0
Supplemental Agreement for work within scope PS0011 · PS0011 extends the moakley watertight door construction project at the moakley courthouse in boston, MA at no cost to 10/23/2025. The extension is required… $0
Supplemental Agreement for work within scope PS0010 · PS0010 extends the substantial completion date to 09/05/2025 at no-cost. All other terms and conditions remain unchanged. The project is to install watertight… $0
Supplemental Agreement for work within scope PS0009 · PS0009 adds 7,077.55 onto the contract for steel jamb repair and J-box relocation. All other terms and conditions remain unchanged. The work will take place… $7,078
Supplemental Agreement for work within scope PS0008 · PS0009 lifts the partial suspension. All work can continue in accordance with the contract. All other terms and conditions remain unchanged. $0
Supplemental Agreement for work within scope PS0007 · No cost modification for the moakley courthouse perimeter watertight barrier project phase 1 for winter demobilization and contract extension. $0
Supplemental Agreement for work within scope PS0006 · The task order is increased by $23,304.20 for labor and material for construction of adaptations to the design of detail 2 (garage door jamb at dividing pier)… $23,304
Supplemental Agreement for work within scope PS0005 · The task order is increased by $7,843.65 for labor and material to install electrical sub panel at the moakley courthouse in boston, MA. All other terms and… $7,844
Supplemental Agreement for work within scope PS0004 · This modification is to add work associated with RFI's #15, 17, and 18 which includes adding bollards and additional demolition. This modification will add… $75,818
Supplemental Agreement for work within scope PS0003 · This modification will extend the ultimate completion date for the moakley watertight doors construction project in boston, MA from april 24, 2024 to december… $0
Change Order PS0002 · This modification adds CMU grouting and lover change installation to the moakley watertight doors construction project in boston, MA. The contract value is… $34,638
Other Administrative Action PA0001 · PA0001 is an administrative change to change the contracting officer for the moakley watertight project from sotheavy khon to adam katzman. All other terms… $0
Original award $1,177,767
Show all 17

About this award

GSA Region 1 issued a delivery order to City Enterprise Inc. on August 14, 2023, with a ceiling value of $1,326,449.12 under a total small business set-aside for labor and materials to install watertight barriers at the Moakley Courthouse in Boston, Massachusetts.

City Enterprise Inc. is a self-certified small disadvantaged business and economically disadvantaged woman-owned small business. Place of performance is Boston, MA 02210. The order carries a firm fixed price and an ultimate completion date of May 30, 2026. An administrative modification (PA00016) corrected accounting strings; all other terms remain unchanged.

Quick answers

Who was awarded contract 47PB0023F0200?

47PB0023F0200 was awarded to City Enterprise Inc. by Region 1 (Public Buildings Service) on August 14, 2023.

How much is contract 47PB0023F0200 worth?

The government has obligated $1,326,449 on 47PB0023F0200.

Is contract 47PB0023F0200 an order under another contract?

Yes. 47PB0023F0200 is a delivery order under 47PB0018D0025, an indefinite delivery contract.

Was contract 47PB0023F0200 competed?

The extent of competition for 47PB0023F0200 was full and open competition after exclusion of sources. The government received 1 offer. It was set aside: Total Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award