Delivery Order 140R6021D0003-140R6023F0005
Award Date 12/7/22
Potential Completion Date 12/31/26
Potential Value $1.9M
Federal Agency
Awardee
Ultimate Awardee
Not listed NAICS Category
PSC Category
Federal Contract Vehicle
- Not listed
Set-Aside Type
No Set-Aside Used
Extent Competed
Full and Open Competition
Major Defense Program
Not listed Pricing Type
Firm Fixed Price
Place of Performance
Helena, MT 59601, USA
Solicitation Procedures
Negotiated Proposal / Quote
Number Of Offers Received
Not listed
Legislative Mandate
Walsh Healy Act
National Interest Action
Not listed Research Type
Not listed Primary Consortia Member
Not listed Similar Awards
- This is a delivery order awarded by the Bureau of Reclamation, a civilian agency within the U.S. Department of the Interior, to Andritz Hydro Corp, an Austrian company that specializes in hydropower equipment and services. The $1,898,300.00 firm-fixed-price contract is for the MT-CF POWERPLANT GENERATOR TASK ORDER 3 and has a period of performance ending on July 30, 2025. The contract does not have a set-aside designation. Andritz Hydro Corp is a prime contractor for the Bureau of Reclamation...
- <p>The Department of the Interior Bureau of Reclamation (DOI) awarded a $1,630,700 Firm Fixed Price Delivery Order to Andritz Hydro Corp as the Prime Contractor. The Delivery Order is for CF POWERPLANT GENERATOR services to be provided in Helena, Montana between December 5th, 2022 and December 31st, 2026. Andritz Hydro Corp will deliver CF POWERPLANT GENERATOR services under this Delivery Order as the Prime Contractor.</p>
- This is a $355,251 firm fixed-price delivery order contract awarded by the Department of the Interior's Bureau of Reclamation to Andritz Hydro Corp, an Austrian firm that specializes in hydropower equipment and services. The contract is for the delivery of N1 facing plates, with a performance period ending on January 10, 2020. Andritz Hydro Corp has a history of providing turbine, generator, and other hydropower-related components and services to the Bureau of Reclamation and the Army Corps of...
- The Department of the Interior's Bureau of Reclamation awarded a firm-fixed-price delivery order to Andritz Hydro Corp, an Austrian hydropower infrastructure manufacturer and service provider, for the repair of the Paradox Gate at the Hoover Dam. The $466,800.00 order was issued under the Bureau's $18.8 million single-award Indefinite Delivery, Indefinite Quantity (IDIQ) contract for generator rewind and refurbishment services at the Canyon Ferry Powerplant in Montana. Andritz Hydro Corp has a...
- The Department of the Interior Bureau of Reclamation awarded a $2.25 million firm fixed price delivery order to Andritz Hydro Corp under the agency's indefinite delivery/indefinite quantity contract vehicle. The order is for MT-CF POWERPLANT GENERATOR 1 TASK ORDER work to be performed in Helena, Montana. The Bureau of Reclamation utilizes IDIQ contracts to maintain, repair, and upgrade components at hydroelectric power plants across the western United States as part of its mission to manage...
- This is a delivery order contract awarded by the Bureau of Reclamation, a civilian agency within the U.S. Department of the Interior, to Andritz Hydro Corp, an Austrian-owned company that specializes in hydropower equipment and services. The contract, valued at $464,725.00, is for the supply of bushings for KA3A and KA5A GSU (Generator Step-Up) transformers. The contract has an ultimate completion date of November 30, 2025 and is a firm fixed-price type. Andritz Hydro Corp, as the prime...
- This is a federal contract award from the Bureau of Reclamation, a civilian agency within the U.S. Department of the Interior, to Andritz Hydro Corp, an Austrian company specializing in hydropower equipment and services. The award, valued at $2,716,615.00, is for the overhaul of an A9 turbine. The contract is a Delivery Order with a Firm Fixed Price pricing type, awarded on May 25, 2021, with a completion date of November 25, 2023. The award does not have a set-aside designation. Andritz Hydro...
- The Department of the Interior Bureau of Reclamation (DOI) awarded a $1,653,900.02 firm fixed price delivery order to Andritz Hydro Corp as the prime contractor. The delivery order is for MT - CF PP GENERATOR DELIVERY ORDER 3 and will be performed in Helena, MT 59601 between August 24, 2023 and August 19, 2024. Andritz Hydro Corp will provide generator delivery services to the DOI as the prime contractor on this order. No applicable subcontractors were identified in the information provided.
- This is a delivery order issued under the Bureau of Reclamation's Turbine and Generator Hydroelectric Component Manufacturing and Rehabilitation Indefinite Delivery/Indefinite Quantity (IDIQ) contract. The $105,741 firm-fixed-price task order was awarded to Andritz Hydro Corp, an Austrian company specializing in hydropower equipment, to provide N3 current transformer refurbishment services. The work will be performed in Boulder City, Nevada, and the period of performance runs through February...
- This federal contract award to Andritz Hydro Corp, an Austrian-owned company, was issued by the U.S. Army Corps of Engineers. The $4,647,086.70 fixed-price contract with economic price adjustment is for the delivery of water turbines, water wheels, and associated components. The contract has an ultimate completion date of September 15, 2018. This award is part of a larger Indefinite Delivery Contract (IDC) worth up to $18.8 million that Andritz Hydro Corp holds with the Bureau of Reclamation for...
- 140R6021D0003Indefinite Delivery Contract
- 140R6021D0003-140R6023F0005Delivery Order
The Department of the Interior's Bureau of Reclamation awarded a $1,863,000.00 firm-fixed-price delivery order to Andritz Hydro Corp, an Austrian company that provides hydropower infrastructure services, for the installation and field testing of a generator stator core and armature winding. This task order, which has a completion date of December 31, 2026, is not associated with a set-aside program. Andritz Hydro Corp has previously delivered generator components, performed turbine modernization, and provided other services related to hydroelectric facilities for the Bureau of Reclamation and the Army Corps of Engineers through prime contracts and task orders under indefinite delivery/indefinite quantity (IDIQ) vehicles.
Generated 4/4/24, 9:01 AM
Name | Description | Solicitation Number | FederalAgency | Type | PostedDate |
|---|---|---|---|---|---|
Task Order - installation and field testing of the | 140R6023F0005 | Department of the Interior Bureau of Reclamation | Award Notice 1/1 | 12/13/22, 6:13 PM |
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| P00001 | Other Administrative Action | $0 | 4/3/24 | |
| Not listed | Not listed | $1.9m | 12/7/22 |