Loon lake storm damage repair phase 2 the purpose of this task order is to before storm damage repair construction services at loon lake campground.

Ended Awarded Last action

Contract number
140L4321F0060
Awardee
Awarding agency
Obligated
$1,022,733

Award facts

Opportunity
Contract value 100% obligated
$1,022,733.00 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 2 offers Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Reedsport, OR 97467, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Close Out P00005 · UDO deobligation & closeout of vertical MATOC task order loon lake storm damage repairs, BLM coos BAY district, oregon -$10,500
Other Administrative Action P00004 · Loon lake storm damage repair phase 2 the purpose of this no-cost administrative modification is to correct a clerical mistake in modification P00003. $0
Change Order P00003 · Loon lake storm damage repair phase 2 the purpose of this modification (P00003) is to: 1- issue a change order (1) for additional safety equipment to be… $8,120
Funding Only Action P00001 · Loon lake storm damage repair phase 2 the purpose of this modification is to correct lines of account in the government's system. -$1,025,113
Funding Only Action P00002 · Loon lake storm damage repair phase 2 the purpose of this modification (P00002) is to RE-obligate all funding lines removed from MOD P00001 in the correct… $1,025,113
Original award $1,025,113

About this award

Hess Contracting LLC, doing business as Hess Construction, has been awarded a $1,033,233 firm fixed price delivery order against the BLM Vertical Repair and Construction Services Multiple Award Task Order Contract (MATOC) by the Bureau of Land Management Oregon-Washington. The purpose of this task order is to provide storm damage repair construction services at the Loon Lake Campground in Reedsport, Oregon before the upcoming season. As part of its mission to manage public lands for multiple uses, the Bureau of Land Management is responsible for maintaining recreational facilities like campgrounds. This total small business set-aside task order will support repairs needed due to storm damage, helping to restore access and ensure visitor safety at the Loon Lake Campground. Work is to be completed by March 2023.

Quick answers

Who was awarded contract 140L4321F0060?

140L4321F0060 was awarded to Hess Contracting LLC by Oregon-Washington Region (Bureau of Land Management) on June 1, 2021.

How much is contract 140L4321F0060 worth?

The government has obligated $1,022,733 on 140L4321F0060.

Is contract 140L4321F0060 an order under another contract?

Yes. 140L4321F0060 is a delivery order under 140L4320D0001, an indefinite delivery contract, on BLM Vertical Repair and Construction Services MATOC.

Was contract 140L4321F0060 competed?

The extent of competition for 140L4321F0060 was full and open competition after exclusion of sources. The government received 2 offers. It was set aside: Total Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award