FY24 BRL B2 generator construction - replace and install 2 power generators.
Active Awarded Last action
- Contract number
- 12805B24F0134
- Awardee
-
Firelake Construction Inc. UEI VNKJEMRCA424
- Awarding agency
-
Central Program Planning Coordination and Support
Agricultural Research Service, Department of Agriculture
- Obligated
- $4,023,052
Award facts
- Opportunity
-
- 12805B24Q0244 Solicitation number
- Contract value 99% obligated
-
- $4,023,052.08 Current, with exercised options
- $4,083,924.08 Potential, with all options
- Completion date 88% complete
- Current and potential, with all options
- Contracting staff
- NAICS code
- 238220 Plumbing, Heating, and Air-Conditioning Contractors
- PSC
- Z1AA Maintenance Of Office Buildings
- Set-aside
- Woman-Owned Small Business
- Competition
- Full and Open Competition after exclusion of sources Negotiated Proposal / Quote
- Pricing
- Firm Fixed Price
- Place of performance
- North River, ND 58102, USA
- Legislative mandates
-
- Davis-Bacon Act FAR subpart 22.4
- Employment Eligibility Verification (E-Verify) FAR subpart 22.18
- Service Contract Inventory FAR subpart 4.17
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Supplemental Agreement for work within scope | $153,963 | |
| Other Administrative Action | $0 | |
| Supplemental Agreement for work within scope | $50,681 | |
| Exercise an Option | $512,851 | |
| Supplemental Agreement for work within scope | $295,978 | |
| Supplemental Agreement for work within scope | $68,801 | |
| Supplemental Agreement for work within scope | $147,079 | |
| Original award | $2,793,699 |
About this award
Firelake Construction Inc., an Economically Disadvantaged Women-Owned Small Business (EDWOSB) and certified Women-Owned Small Business (WOSB), was awarded a delivery order on July 9, 2024, for $4,083,924.08 to replace and install two 400-kilowatt power generators and associated automatic transfer switchgear controller at a facility in North River, North Dakota, with ultimate completion February 2, 2027. The order is set aside for women-owned small businesses and carries firm fixed price terms.
Place of performance is North River, North Dakota. The order was structured as a capital construction and infrastructure upgrade project spanning generator procurement, installation of paralleling switchgear and load bank equipment, electrical distribution system modifications, roofing replacement, site demolition and concrete work, mechanical systems integration (gas piping, steam systems, condensate piping, trench drains), and asbestos abatement. Subcontractors included Agassiz Mechanical Inc. for gas and steam piping and mechanical installation, Tecta America Corp for roof replacement and flashing systems, Gast Construction Company Inc. for structural steel and carpentry framing, and VCI Environmental Inc. for asbestos abatement, with additional subcontractors performing concrete and asphalt site work.
Service Contract Inventory reporting shows $1.043 million invoiced across fiscal years 2024 and 2025. FY2025 (the most recent period) reflected 1.0 FTEs and 2,094 contractor hours at a derived government-paid hourly rate of $485.27 per hour. Firelake subcontracted 66 percent of reported hours across six subcontractors in FY2025, down from $43 thousand invoiced on 55 hours (at $781.81 per hour) in FY2024.
Subawards
| Subcontractor | Amount | Awarded |
|---|---|---|
| Agassiz Mechanical Inc. | $1,000 | |
| Subcontractor not on record | $4,000 | |
| Subcontractor not on record | $18,340 | |
| Agassiz Mechanical Inc. | $19,960 | |
| Subcontractor not on record | $10,827 | |
| Tecta America Corp | -$2,270 | |
| Subcontractor not on record | $4,802 | |
| Gast Construction Company Inc. | -$18,933 | |
| Subcontractor not on record | -$182 | |
| Subcontractor not on record | $328,479 | |
| Subcontractor not on record | $169,265 | |
| Subcontractor not on record | $49,974 | |
| Agassiz Mechanical Inc. | $40,150 | |
| VCI Environmental, Inc. | $52,000 | |
| Subcontractor not on record | $1,215,588 | |
| Tecta America Corp | $66,152 | |
| Gast Construction Company Inc. | $229,494 | |
| Subcontractor not on record | $221,174 | |
| Agassiz Mechanical Inc. | $158,135 | |
| FM Asphalt LLC | $28,600 |
Show all 20
Quick answers
Who was awarded contract 12805B24F0134?
12805B24F0134 was awarded to Firelake Construction Inc. by Central Program Planning Coordination and Support (Agricultural Research Service) on July 9, 2024.
How much is contract 12805B24F0134 worth?
The government has obligated $4,023,052 on 12805B24F0134. Its potential value, with all options, is $4,083,924.
Is contract 12805B24F0134 an order under another contract?
Yes. 12805B24F0134 is a delivery order under 12805B21D0001, an indefinite delivery contract.
Was contract 12805B24F0134 competed?
The extent of competition for 12805B24F0134 was full and open competition after exclusion of sources. It was set aside: Woman-Owned Small Business.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award