Delivery Order 127K1120D0014-12441923F0042

Award Date 3/20/23
Potential Completion Date 6/22/23
Potential Value $104K
Funding Federal Agency
Forest Service
Contracting Federal Agency
Operations Center East
Ultimate Awardee
Not listed
Set-Aside Type
No Set-Aside Used
Federal Contract Vehicle
Extent Competed
Full and Open Competition after exclusion of sources
Major Defense Program
Not listed
Pricing Type
Firm Fixed Price
Place of Performance
Pineville, LA, USA
Solicitation Procedures
Negotiated Proposal / Quote
Number Of Offers Received
Not listed
Legislative Mandate
Davis Bacon Act
National Interest Action
Not listed
Research Type
Not listed
Primary Consortia Member
Not listed
Similar Awards
The Department of Agriculture Forest Service Southern Region awarded a $68,652.75 firm fixed price delivery order contract to Buck Carter Construction Company Inc. of Pineville, Louisiana. The contract is for the replacement of culverts in the Winn and Caney Districts and has a completion date of May 31, 2021. No set-aside designation was used for this award made on July 27, 2020 in support of the Forest Service's infrastructure maintenance and improvement programs. Buck Carter Construction...
This is a firm fixed-price delivery order contract awarded to Buck Carter Construction Co, Inc., a for-profit subchapter S corporation based in Louisiana, by the U.S. Department of Agriculture Forest Service's Southern Region. The contract, valued at $53,158.00, is for the replacement of a culvert in Winnfield, Louisiana. This work is being performed under a larger $20 million single-award indefinite delivery contract that Buck Carter Construction holds with the Forest Service for road,...
The U.S. Department of Agriculture Forest Service awarded a $42,800 firm fixed price delivery order contract to Buck Carter Construction Company Inc. for culvert replacements across multiple locations within the Kisatchie National Forest in Provencal, Louisiana. The contract supports culvert replacement efforts throughout the national forest and has a completion date of December 31, 2021. No set-aside designation was applied to this award made by the Forest Service Southern Region office in...
Buck Carter Construction Company Inc. was awarded a firm fixed price delivery order valued at fifty-eight thousand seventy dollars and eighty-five cents ($58,070.85) by the Department of Agriculture Forest Service Southern Region to complete culvert replacement and bridge repairs on the Kisatchie Ranger District of the Kisatchie National Forest in Provencal, Louisiana. The work must be finished by October 31, 2021. No set-aside designation was associated with this contract to replace aging...
The Department of Agriculture Forest Service Southern Region awarded a $21,000 firm fixed price delivery order contract to Buck Carter Construction Company Inc. of Provencal, Louisiana on February 22, 2023. The contract is for replacement of culverts along National Forest System Road 304-2.0 and has a period of performance through October 17, 2023. No set-aside designation was used for this solicitation. The award is associated with highway and road maintenance and repair work conducted by the...
This is a firm-fixed-price delivery order contract awarded by the U.S. Department of Agriculture (USDA) Forest Service, Southern Region, to Buck Carter Construction Co., Inc., a for-profit subchapter S corporation based in Louisiana. The $96,300.00 contract is for the excavation and replacement of culverts on the Caney District. The contract has an ultimate completion date of July 31, 2024 and was awarded on June 7, 2024. There is no set-aside designation for this contract. Buck Carter...
Buck Carter Construction Company Inc. was awarded a firm fixed price delivery order against an unspecified contract vehicle by the Department of Agriculture Forest Service Southern Region. The $34,806.60 potential value contract is for the removal of a damaged culvert and installation of a new culvert at Catahoula District North Tower Road, NFSR 145, in Bentley, Louisiana. No set aside designation was used for this award. Work is to be completed by July 10, 2021 to support the Forest Service's...
The USDA Forest Service Southern Region awarded a $17,468 firm fixed price delivery order contract to Buck Carter Construction Company Inc. of Boyce, Louisiana under the Multiple Award Task Order Contract (MATOC) CULVERT REPLACEMENT 471-0.486. The contract is for culvert replacement work to be completed by June 30, 2021 in Boyce, Louisiana. No set-aside provisions were applied to this award made on July 14, 2020. The MATOC vehicle provides the Forest Service flexibility to issue orders for...
Buck Carter Construction Company Inc. has been awarded a firm fixed price delivery order against the U.S. Department of Agriculture Forest Service for $73,897.35 to excavate and remove an existing 48-inch reinforced concrete pipe and 90-inch corrugated metal pipe, and replace both with aluminized corrugated steel pipe and backfill with select material. The work is to be completed by November 30, 2023 at a location in Pineville, Louisiana. As the prime contractor, Buck Carter Construction will...
This federal contract was awarded by the Department of Agriculture Forest Service R8-Southern Region to Buck Carter Construction Co, Inc., a for-profit subchapter S corporation, for WINN HURRICANE HARVEY RECOVERY ROAD MAINTENANCE. The $354,011.00 firm-fixed price delivery order was issued under the Kisatchie NF Road Maintenance 2017-2019 indefinite delivery, indefinite quantity (IDIQ) contract. The contract involves road maintenance, grading and surfacing, culvert replacements, bridge repairs,...
  • 127K1120D0014
    Indefinite Delivery Contract
  • 127K1120D0014-12441923F0042
    Delivery Order

The Department of Agriculture Forest Service awarded a $103,525 firm fixed price delivery order contract to Buck Carter Construction Company Inc. of Pineville, Louisiana. The contract is for the CALCASIEU/KISATCHIE 421 NFSR CULVERT project to replace or repair culverts. Work is to be completed by June 22, 2023. No set-aside provisions were applied to this award made on March 20, 2023 under the Forest Service's infrastructure maintenance and construction program. Buck Carter Construction will perform the culvert work as prime contractor at the specified location in central Louisiana to help improve roads and bridges under the agency's stewardship of national forests and grasslands.