Delivery Order 12467018D0007-12467020F0121
Award Date 9/16/20
Potential Completion Date 4/15/21
Potential Value $35K
Funding Federal Agency
Contracting Federal Agency
Awardee
Ultimate Awardee
Not listed NAICS Category
PSC Category
Set-Aside Type
No Set-Aside Used
Federal Contract Vehicle
- Not listed
Extent Competed
Full and Open Competition after exclusion of sources
Major Defense Program
Not listed Pricing Type
Firm Fixed Price
Place of Performance
Troy, NC 27371, USA
Solicitation Procedures
Multiple Award, Fair Opportunity
Number Of Offers Received
2
Legislative Mandate
Service Contract Act
National Interest Action
Not listed Research Type
Not listed Primary Consortia Member
Not listed Similar Awards
- The Federal Highway Administration awarded a $28.68 million firm fixed-price contract to Vannoy Structural Joint Venture on April 11, 2022, for Project NP-BLRI 2D17, which involves the replacement of the Laurel Fork Bridge on the Blue Ridge Parkway at milepost 248.85 in West Jefferson, North Carolina. The scope of work encompasses precast segmental concrete, structural concrete, post-tensioning systems, reinforcing steel, drilled shafts, temporary bridges, mechanically stabilized earth walls,...
- The Federal Highway Administration awarded a $565.8K firm fixed-price definitive contract to Battle Ridge Builders, LLC for the replacement of a pedestrian trail bridge at Veterans Lake in the Chickasaw National Recreation Area near Sulphur, Oklahoma. The project involves removal of an existing bridge damaged by an April 2024 tornado and installation of a new 130-foot-long, 6-foot-wide prefabricated steel truss bridge with a timber deck. This contract is designated as a Total Small Business...
- The U.S. Department of Transportation Federal Highway Administration awarded a $16,904,107.60 firm fixed price contract to Hamilton Construction Co., a for-profit construction company based in Springfield, Oregon, for the MT FLAP BOR 2980(1), Sun River Bridge Replacement project. The contract involves the construction of a new 3-span, 462-foot long precast-post-tensioned girder bridge with a precast concrete deck, approach embankments, and MSE walls in Augusta, Montana. This infrastructure...
- The Federal Highway Administration awarded a delivery order modification to WSP USA Inc. on March 25, 2025, to provide design services for Project TN NP GRSM 11(5), which involves replacing the Wiley Oakley Drive Crossover Bridge with a new flyover bridge and associated on and off ramps. This modification adds a new contract line item (CLIN 01102) for Phase XI utility integration work in the amount of $533,459.31. The overall contract ceiling value is $3.84 million, with an ultimate completion...
- The USDA Forest Service awarded a $1.2 million firm-fixed price contract to Allegheny Construction Company, Inc. for the Jordan Bridge Project. Under this definitive contract, Allegheny Construction will demolish the existing Jordan Bridge located over the Pedlar River in Natural Bridge, Virginia, and rebuild the bridge. The work must be completed within 210 calendar days in accordance with the terms and specifications outlined in the solicitation. This requirement was set aside entirely for...
- This definitive contract awarded by the Department of Transportation Federal Highway Administration (DOT FHWA) to Adams Contracting LLC is valued at $3.81 million to replace five bridges along Forge Creek Road in the Great Smoky Mountains National Park in Blount County, Tennessee. The work will involve removing existing stone masonry-faced concrete abutments, piers, steel beams, timber decks and curbs on Bridges 1 through 5 and Mill Creek Bridge, and constructing new structures. The solicitation...
- The USDA Forest Service awarded a $730,796 firm fixed price contract to RL Reimers Co. to replace the Eagle Creek Trail Bridge in Mount Hood National Forest, Oregon. The contract was awarded through a total small business set aside solicitation seeking a contractor to demolish the existing 150-foot pedestrian bridge and construct a new prefabricated steel truss structure, including concrete abutments, foundations, and approaches. Key deliverables include demolishing the current bridge and...
- The Federal Highway Administration awarded a $1.64 million delivery order to Kovilic Construction Co Inc. on October 24, 2025, under the Mid-Atlantic Regional Construction Indefinite Delivery Indefinite Quantity (IDIQ) contract. The project, designated VA ERFO FS GWJEF808 2020-2(2), involves finalizing design and executing construction work at Lick Creek Trail Bridge in Ceres, Virginia. The scope includes replacement of the existing trail bridge, construction of temporary access infrastructure...
- This is a firm-fixed price purchase order awarded by the U.S. Department of Agriculture Forest Service to Sierra Sports Marketing, LLC (doing business as Sierra Trail Works) for the design, purchase, delivery, and installation of a 27-foot span glulam timber trail bridge with metal railing for the Carolyn Creek Trail Bridge Project in Spring Creek, Nevada. The contract is valued at $148,335.00 and has a completion date of November 12, 2025. This requirement was solicited as a 100% Total Small...
- This is a $84,777.24 firm fixed-price definitive contract awarded by the USDA Forest Service's Southern Region to Tri-State Company, Inc., a veteran-owned small business, for the replacement of the Roaring Run Trail Bridge located in the George Washington/Jefferson National Forest in Virginia. The contract is funded under the American Recovery and Reinvestment Act (ARRA) Capital Improvement and Maintenance program. There is no set-aside designation for this contract. The work is expected to be...
- 12467018D0007Indefinite Delivery Contract
- 12467018D0007-12467020F0121Delivery Order
THORNBURG TRAIL BRIDGE REPLACEMENT
Posted 9/16/20
Name | Description | Solicitation Number | FederalAgency | Type | PostedDate |
|---|---|---|---|---|---|
IDIQ for Trail Maintenance | 12467018R0077 | Department of Agriculture Forest Service R8-Southern Region | Award Notice 2/2 | 7/23/18, 12:14 PM | |
Trail Maintenance and Constrcution IDIQ | 12467018R0077 | Department of Agriculture Forest Service R8-Southern Region | Award Notice 1/2 | 5/30/18, 6:24 AM |
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| P00002 | Change Order | $5.8k | 3/22/21 | |
| P00001 | Change Order | $0 | 12/28/20 | |
| Not listed | Not listed | $29.1k | 9/16/20 |