Proposed project includes the removal of the existing 72" RCP at the crossing of the tributary of cyper CRK and FSR 610A. Also included is this culvert's replacement with a new 18'10"X5'8"…

Ended Awarded Last action

Contract number
12445224F0063
Awardee
Awarding agency
Obligated
$302,420

Award facts

Opportunity
  • 12445224R0039 Solicitation number
Contract value 100% obligated
$302,420.00 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
Set-aside
No set-aside
Competition
Competed under SAP Simplified Acquisition
Pricing
Firm Fixed Price
Place of performance
Edgefield, SC, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope P00003 · The purpose of this modification is for unanticipated rock excavation needed to install the new culvert. Also addressed are variations in some of the quantities… $27,720
Supplemental Agreement for work within scope P00002 · The purpose of this modification is to extend the POP 45 days changing the end date from 4/29/25 to 6/13/25 $0
Supplemental Agreement for work within scope P00001 · The purpose of this modification is to correct the POP end date of this task order to end 4/29/25 instead of the 5-year IDIQ end date in 2029. $0
Original award $274,700

About this award

The U.S. Forest Service awarded a $302,420 firm fixed-price delivery order to F D Riley & Sons Inc., a small South Carolina-based road maintenance and construction contractor, for culvert replacement and associated work at a tributary crossing on Forest Service Road 610A near Edgefield, South Carolina. The project involves removing an existing 72-inch reinforced concrete pipe and replacing it with an 18'10" by 5'8" aluminized steel plate arch culvert. This delivery order represents a modification to expand the scope to address unanticipated rock excavation requirements needed for the new culvert installation and to adjust certain cost line items and extend the project completion date to August 15, 2025.

F D Riley & Sons Inc. is a long-standing contractor in the Forest Service's Southern Region, operating under two significant small business set-aside indefinite delivery contracts valued at $10 million and $900,000 respectively, through which the agency issues task orders for infrastructure improvements across the Francis Marion and Sumter National Forests. The current delivery order is issued under no specific set-aside designation and reflects the contractor's established expertise in critical transportation infrastructure management, including road resurfacing, culvert replacement, and drainage improvements that support public land access and forest management operations.

Description

Proposed project includes the removal of the existing 72" RCP at the crossing of the tributary of cyper CRK and FSR 610A. Also included is this culvert's replacement with a new 18'10"X5'8" aluminized steel plate arch WIT

Quick answers

Who was awarded contract 12445224F0063?

12445224F0063 was awarded to F D Riley & Sons Inc. by Forest Service (Department of Agriculture) on September 18, 2024.

How much is contract 12445224F0063 worth?

The government has obligated $302,420 on 12445224F0063.

Is contract 12445224F0063 an order under another contract?

Yes. 12445224F0063 is a delivery order under 12445224D0024, an indefinite delivery contract.

Was contract 12445224F0063 competed?

The extent of competition for 12445224F0063 was competed under sap.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award