Delivery Order 12339518D0003-12339518F0020
Award Date 9/11/18
Potential Completion Date 8/20/19
Potential Value $66K
Federal Agency
Awardee
Ultimate Awardee
Not listed NAICS Category
Federal Contract Vehicle
- Not listed
Set-Aside Type
No Set-Aside Used
Extent Competed
Full and Open Competition after exclusion of sources
Major Defense Program
Not listed Pricing Type
Firm Fixed Price
Place of Performance
Harrisonburg, VA 22801, USA
Solicitation Procedures
Multiple Award, Fair Opportunity
Number Of Offers Received
3
Legislative Mandate
Service Contract Act
National Interest Action
Not listed Research Type
Not listed Primary Consortia Member
Not listed Similar Awards
- The U.S. Department of Agriculture Forest Service awarded a $219,160 firm fixed price delivery order to Ketchikan Ready-Mix & Quarry, Inc. to remove and dispose of an existing corrugated metal pipe on Road 3036 at milepost 0.27 in Coffman Cove, Alaska and replace it with a 55-foot structural plate arch culvert composed of a corrugated metal arch and concrete footings. The contractor will also restore the streambed upstream and downstream. There was no set-aside designation for this award...
- The Department of Agriculture Forest Service awarded a $274,427 firm fixed price definitive contract to Cp&G Construction LLC, doing business as Cp&G, to complete construction of Forest Service Road 404 Cane Creek Culvert Replacement in Georgetown, South Carolina. The solicitation sought replacement of an existing 10'9" x 6'7" x 47' culvert with a new 19' x 8'2" x 46' structural plate aluminum arch culvert. With a period of performance of 180 calendar days, the...
- This is a firm fixed-price federal contract awarded by the U.S. Department of Agriculture Forest Service to M R Construction, a small disadvantaged and HUBZone certified business, to replace a culvert on Forest Service road 40N39 that crosses Kelly Gulch in the Klamath National Forest near Etna, California. The contract, valued at $475,417.50, involves installing a 15-foot span by 6-foot 7-inch rise multi-plate arch culvert with a simulated streambed to allow for aquatic organism passage. This...
- The United States Department of Agriculture Forest Service awarded a $804,530 firm fixed price delivery order contract to Rock-N-Road Construction Inc. to perform back loop aquatic organism passage construction work in Petersburg, Alaska. The work consists of removing an existing culvert on Road 3030110 at milepost 0.28 and replacing it with a 49 foot steel bridge and constructing a new simulated streambed, as well as removing an existing culvert on Road 30 and constructing the required...
- This contract, awarded by the U.S. Department of Agriculture Forest Service to Patton Excavation, a for-profit Subchapter S corporation, replaces two Civilian Conservation Corps (CCC)-era culverts and constructs two temporary bypass roads with temporary bridges on Mulky Gap Road in Gainesville, Georgia. The contract, which has a firm-fixed-price of $494,564.34, does not have a set-aside designation. The work was originally solicited as a competitive, unrestricted contract opportunity. The...
- The U.S. Department of the Interior's Bureau of Land Management (BLM), Montana-Dakotas Region awarded a $169,200.00 firm fixed-price purchase order contract to RF Construction LLC, a small business, for the GAOA DRY FORK ROAD CULVERT REPLACEMENT project in Malta, MT. The contract, which has a completion date of September 30, 2025, requires the replacement of an existing set of two corrugated steel pipe (CSP) culverts with a single CSP culvert with polymer coating, step beveled end sections,...
- The Department of Agriculture Forest Service R8-Southern Region awarded a firm-fixed price contract to Anderson Contracting LLC, a certified HUBZone small business, for the DELTA NF ROAD 717 CULVERT REPLACEMENT project. The $104,260.80 contract involves replacing two 60-inch corrugated metal pipe culverts and four 30-inch roadside ditch culverts, including site work such as excavation, riprap installation, and seeding. The project is located near Holly Bluff, Mississippi and is set aside for...
- The U.S. Department of Agriculture Forest Service awarded a $98,117.80 firm fixed price delivery order contract to Jack Bowen Excavating of Mt Tabor, Vermont. The contract calls for the replacement of an existing five-foot diameter culvert with a new seven-foot, three-inch wide by five-foot, three-inch high by seventy-eight-foot long aluminized steel pipe arch culvert. Additional work includes removal of an existing temporary bridge and its relocation. The contract was awarded on April 26,...
- The Bureau of Land Management Oregon-Washington awarded a $321,875 firm fixed price delivery order against the BLM Horizontal Repair and Construction Services Multiple Award Task Order Contract to West Coast Contractors Inc. to replace culverts on tributaries to Crooked Creek in Linn County, Oregon as part of the BLM Northwest Oregon District's Goal Achievement Award program. The purpose of this project is to improve aquatic organism passage through culvert replacement. West Coast Contractors...
- This contract was awarded by the U.S. Department of Agriculture's Forest Service R6-Pacific Northwest Region to Am Excavating LLC, a for-profit partnership, to carry out the "THREE WESTSIDE CULVERT REPLACEMENT - TASK ORDER" project. The contract was issued as a Firm Fixed Price Delivery Order against the parent IDIQ contract "WANF Road Construction 2016-2021". The project involves culvert replacement and related construction services within the Kettle Falls, Washington area...
- 12339518D0003Indefinite Delivery Contract
- 12339518D0003-12339518F0020Delivery Order
REMOVE AND REPLACE 3 CULVERTS ON BECK ACCESS ROAD
Posted 9/11/18
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| P00003 | Other Administrative Action | $0 | 8/20/19 | |
| P00002 | Supplemental Agreement for work within scope | $8.2k | 7/1/19 | |
| P00001 | Other Administrative Action | $0 | 2/15/19 | |
| Not listed | Not listed | $57.5k | 9/11/18 |