Grouse creek road relocation road no. 280 and resurfacing option item one

Ended Awarded Last action

Contract number
1282B122F0053
Awardee
Awarding agency
Obligated
$1,340,393

Award facts

Contract value 100% obligated
$1,340,392.99 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
Funding agency
Region 4 - Intermountain Region Forest Service, Department of Agriculture
Set-aside
No set-aside
Competition
Full and Open Competition after exclusion of sources · 2 offers Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Kingston, ID 83839, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope P00008 · The purpose of this modification is to direct: 1. Clean-up of raveling failed cut slopes 13+50 32+00. 2. Placement of riprap at a fill failure. 3. Roadway… $104,589
Supplemental Agreement for work within scope P00007 · The purpose of this modification is to: 1. Increase cubic yards for subbase placement. 2. Increase geotextile. 3. Increase riprap. $133,788
Supplemental Agreement for work within scope P00006 · The purpose of this modification is to: 1. Add two culverts to the base contract. 2. Add three culverts to the option item. $29,416
Additional Work (new agreement, FAR part 6 applies) P00005 · The purpose of this modification is to: 1. Direct work for unforeseen site conditions - adding subbase to stabilize the soil for drivability and longevity of… $145,545
Other Administrative Action P00004 $52,941
Supplemental Agreement for work within scope P00003 · This project consists of the repair of two fill failures and installation of two 18 inch x 40 foot culverts. $0
Exercise an Option P00002 · Option 01 to aggregate surface 1.7 miles of road, calcium chloride 1.7 miles and replace two culverts. $179,098
Other Administrative Action P00001 $0
Original award $695,017

About this award

The Department of Agriculture Forest Service awarded a firm-fixed-price delivery order for $1,340,392.99 to Stone Ridge Construction, Inc., doing business as SR Construction Inc., a for-profit HUBZone small business. The contract is for the relocation and resurfacing of Grouse Creek Road No. 280 in Kingston, Idaho, with a completion date of November 15, 2024. SR Construction specializes in construction, maintenance, and repair services for roads, bridges, and infrastructure, primarily supporting the Forest Service's land management across national forests and grasslands. This award is likely part of the Forest Service's Region 1 - Region 4 Forest Engineering and Road Maintenance (FERM) Blanket Purchase Agreement, a $50 million multiple-award contract for road and bridge work. SR Construction also holds other Forest Service regional IDIQs and MOTOCs to quickly deliver its capabilities on an as-needed basis.

Quick answers

Who was awarded contract 1282B122F0053?

1282B122F0053 was awarded to Stone Ridge Construction, Inc. by Operations Center Intermountain (Economic Recovery Operations) on September 29, 2022.

How much is contract 1282B122F0053 worth?

The government has obligated $1,340,393 on 1282B122F0053.

Which agency awarded contract 1282B122F0053?

Operations Center Intermountain (Economic Recovery Operations) awarded 1282B122F0053, with funding from Region 4 - Intermountain Region (Forest Service).

Is contract 1282B122F0053 an order under another contract?

Yes. 1282B122F0053 is a delivery order under 12034319D0031, an indefinite delivery contract.

Was contract 1282B122F0053 competed?

The extent of competition for 1282B122F0053 was full and open competition after exclusion of sources. The government received 2 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award