Construct addition for research f/20079 - afrl/STO at wpafb, OH

Ended Definitive Contract Awarded Last action

Contract number
W912QR22C0017
Awardee
Awarding agency
Obligated
$8,263,084

Award facts

Opportunity
Contract value 100% obligated
$8,263,084.00 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 2 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
WPAFB, OH 45433, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope A00012 · CR 0011-2 water infiltration, part II final base minor construction B79 $7,384
Supplemental Agreement for work within scope A00011 · CR 009 g street GEO grid furnish and install GEO grid material base (minor construction) B79 $36,094
Supplemental Agreement for work within scope A00010 · CR 0012 regrade soil -regrade existing soil CR 0013 return air ducts rooms 162-168 install additional return air duct B79 $251,322
Supplemental Agreement for work within scope A00009 · CR 0010 crac return dampers B79 $44,782
Change Order A00008 · CR 011-1 water infiltration, part i NTP bldg 79 wpafb $15,000
Supplemental Agreement for work within scope A00007 · CR08 server room door hardware changes $13,087
Supplemental Agreement for work within scope A00006 · CR 007 restroom exhaust base minor construction B79 $32,379
Supplemental Agreement for work within scope A00005 · CR 006 ductwork conflicts base (minor construction) B79 $13,022
Supplemental Agreement for work within scope A00004 · CR 005 restroom changes B79 $5,586
Supplemental Agreement for work within scope A00003 · CR 004 NAC panel relocation base (minor construction) B79 $4,174
Supplemental Agreement for work within scope A00002 · CR 003 138N opening wpafb OH $11,982
Supplemental Agreement for work within scope A00001 · CR 002 abate steam line infill steam tunnel B79 $15,172
Other Administrative Action P00002 · Remove clause 52.229-12 $0
Other Administrative Action P00001 · Issuance of NTP - B79 construction $0
Original award $7,813,100
Show all 15

About this award

This is a $8,263,084.00 firm fixed-price definitive contract awarded by the U.S. Army Corps of Engineers on behalf of the Department of the Air Force to Butt Construction Co Inc. to construct a 10,200 square foot addition to Building 79 at Wright-Patterson Air Force Base in Ohio. The project involves the new construction of a one-story lab and conference room facility, with renovation of existing restrooms and a server room. This was a full and open procurement, with HUBZone contractors eligible for a 10% price evaluation preference. Butt Construction Co Inc. is a for-profit Subchapter S Corporation that specializes in federal construction projects, holding multiple large indefinite delivery/indefinite quantity contracts with the Army Corps of Engineers, Air Force, and Navy.

Quick answers

Who was awarded contract W912QR22C0017?

W912QR22C0017 was awarded to Butt Construction Company, Incorporated by ENDIST Louisville (US Army Corps of Engineers) on March 24, 2022.

How much is contract W912QR22C0017 worth?

The government has obligated $8,263,084 on W912QR22C0017.

Was contract W912QR22C0017 competed?

The extent of competition for W912QR22C0017 was full and open competition. The government received 2 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award