Renovation of building 1600, headquarters for the air force mobility command at scott air force base, illinois.

Active Definitive Contract Awarded Last action

Contract number
W912QR22C0002
Awardee
Awarding agency
Obligated
$149,771,384

Award facts

Opportunity
Contract value 91% obligated
  • $150,070,681.24 Current, with exercised options
  • $164,505,764.24 Potential, with all options
Completion date 97% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 2 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
South Dr, Scott AFB, IL 62225, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope A00035 · Change request &*@~CR23 - RFI - AE door hardware changes $323,279
Supplemental Agreement for work within scope A00034 · Contract no. W912QR22C0002 building 1600 renovation $101,232
Supplemental Agreement for work within scope A00033 · CR 0174 wall treatment at window head- bldg 1600 renovations safb $122,059
Supplemental Agreement for work within scope A00032 · Request R121 RFI-0158 add fire dampers 1ST FL CR128 RFI-0485 deck support grid j-p DSC CR131 RFI-0480 loading dock drainage CR133 RFI-0509 edge of slab… $222,771
Supplemental Agreement for work within scope A00031 · CR 151 additional raceway heaving $238,189
Supplemental Agreement for work within scope A00030 · CR 126 REA 004 fireproofing containment - addtl labor needed to remove asbestos fireproofing CR 127 REA 005 existing roof thickness - differing site condition… $457,155
Supplemental Agreement for work within scope A00029 · CR152 excusable weather delay JAN FEB 2025 $0
Supplemental Agreement for work within scope A00028 · CR 79 RFI-0259 VFD cabling CR 82 RFI-0125 telecom backbone sizing CR 114 RFI-0433 overhead door electrical REV CR 115 RFI-0435 existing pier conflict bldg… $190,575
Supplemental Agreement for work within scope P00015 · CXA design review report revisions $598,325
Supplemental Agreement for work within scope A00027 · CR 089 HVAC ductwork changes rfis 25,30,36 CR 111 RFI 0431-fire sprinkler piping size bldg 1600 renovations safb $366,487
Supplemental Agreement for work within scope A00025 · CR51 elect one-line REV CR78 RFI-0258 CKT BKR 3128-XMR-RP-1 CR81 RFI 110 telecom boxes sizing CR 94 RFI 0397 demo ductbank CR 102 add therm ignit barr RM CR 106… $245,087
Supplemental Agreement for work within scope P00014 · CR 0087 secure area head of wall detail bldg 1600 renovations safb $652,812
Change Order A00024 · CR145 1 roof elevations area a g $143,705
Supplemental Agreement for work within scope A00023 · CR101- framing system at CWS parapet $208,098
Supplemental Agreement for work within scope P00013 · CR 0059-2 drilled piers base - bldg 1600 renovations safb $7,507,850
Supplemental Agreement for work within scope A00022 · 00077 RFI-0253 depressed slab at bathrooms 00092 2ND and 3RD floor raceway heave $475,616
Supplemental Agreement for work within scope P00012 · CR 0129 RFI-0475 and 0483 revised roof details, base - bldg 1600 renovations safb $755,205
Exercise an Option P00011 · Exercise option 3, uninterrupted power supply for bldg 1600 renovations at scott AFB, IL. $52,298
Supplemental Agreement for work within scope A00021 · 00056 exterior glass grey tint 00104 RFI-0429 remove abandoned manhole - DSC 00105 inner PL1/2 fitment at A2/s-523 - DSC 00109 RFI-0434 demo perimeter steel… $241,683
Supplemental Agreement for work within scope A00020 · Building 1600 renovation, AMC headquarters base - bldg 1600 renovations safb $242,257
Supplemental Agreement for work within scope P00010 · 00030 window sill and canopy revisions $573,075
Supplemental Agreement for work within scope A00019 · CR61 RFI333 exstg beam cnctn A3 & A6 65 exstg STL/slab opng 66 column realignmnt 67 adtnl STL sprt for MEP 68 LVL 4 area f 73 RFI350 & 368 deck edge sprt 83… $249,529
Supplemental Agreement for work within scope P00009 · Change request 00059 2 supplemental part 1A drilled piers DSC $1,004,497
Supplemental Agreement for work within scope A00018 · 00060 RFI-235 column stiffener plates 00070 C15X50 fitment LVL 3 area f - DSC 00072 existing steel demo alterations - DSC 00075 RFI-0344 C15X50 bar joist… $244,598
Supplemental Agreement for work within scope A00017 · CR 0014 RFI 0061 frame/sidelight assembly CR 0063 level 2 and 3 HSS revisions bldg 1600 renovations safb $159,597
Exercise an Option P00008 · Exercise option 1 - one time in the amount of $4,022,992.00 for the bldg 1600 renovations at safb project. $4,022,992
Supplemental Agreement for work within scope A00016 · Change request 00006-2 part 2 - insulation/mastic ACM abatement $87,166
Supplemental Agreement for work within scope P00007 · Change request 00028 2ND/3RD floor slab repairs 00036 RFI-0190 slab edge repairs 00064 north column settlement remediation $1,855,934
Supplemental Agreement for work within scope A00015 · CR 19-2 waterproofing ACM abatement CR 47 1" ACU pipng branches CR 46 RFI0159 remove infill LVL 2 area b CR 50 glazing HSS chng to precast CR 53 RFI-0223… $179,922
Change Order P00006 · MOD P00006 for drilled piers - bldg 1600 renovations safb $8,272,467
Supplemental Agreement for work within scope A00014 · Change request 00018-2 part 2 - thickened slab removal $447,057
Supplemental Agreement for work within scope A00013 · CR 0037 clin 003B ACM VAT VEQ CR 0038 clin 0003 ACM fireproofing VEQ CR 0039 clin 003D ACM drywall VEQ base - bldg 1600 renovations safb $189,795
Supplemental Agreement for work within scope A00012 · CR 0029 elevator PIT and comm vault revisions bldg 1600 renovations safb $227,331
Supplemental Agreement for work within scope A00011 · Change request 00021 RFI-0112 steel at existing staircase $73,087
Supplemental Agreement for work within scope A00010 · Base - bldg 1600 renovations safb $132,359
Supplemental Agreement for work within scope A00009 · CR 0020 plenum wall ACM abatement bldg 1600 renovations safb $199,348
Supplemental Agreement for work within scope A00008 · Base - bldg 1600 renovations safb -$161,725
Supplemental Agreement for work within scope A00007 · Case 009 RFI 0020 heat tracing case 0013 acus and case 0017 RFI 0088 renovations scott AFB IL $312,781
Change Order P00005 · Base - bldg 1600 renovations safb, modification for vermiculite removal. $2,534,143
Supplemental Agreement for work within scope A00006 · CR 19-1 waterproofing ACM abatement bldg 1600 renovations safb $76,648
Change Order P00004 · Base - bldg 1600 renovations safb $1,491,561
Supplemental Agreement for work within scope A00005 · Case 008 drawing 05 12 00 7 steel and joist revision - bldg 1600 renovations safb $130,884
Supplemental Agreement for work within scope A00004 · CR 0018-1 part i thickened slab removal remove additional 2" of concrete slab base - bldg 1600 renovations safb $132,715
Supplemental Agreement for work within scope A00003 · CR 0006 insulation/mastic acma abatement, part i bldg 1600 renovations safb $160,386
Other Administrative Action A00002 · Base - bldg 1600 renovations safb $0
Change Order P00003 · MOD to remove FF & e from 1ST & 3RD floors - bldg 1600 renovations safb $633,779
Supplemental Agreement for work within scope A00001 · CR 0001 revise construction limits - bldg 1600 renovations safb $15,877
Other Administrative Action P00002 · Bldg 1600 renovations safb - notice to proceed $0
Change Order P00001 · Base - bldg 1600 renovations safb $0
Original award $113,142,519
Show all 50

About this award

The Department of the Army Corps of Engineers Engineering District Louisville awarded a $164.5 million definitive contract to Korte–River City JV for renovation of Building 1600, headquarters for the Air Force Mobility Command at Scott Air Force Base, Illinois, on November 10, 2021, under firm fixed price with no set-aside.

The originating pre-solicitation (posted November 27, 2018, due December 7, 2018) sought complete renovation of the 314,000 square foot, three-story facility to extend its service life 40 years. Evaluation criteria included small business status verification, bonding limits, relevant experience on similar-scale projects, and percentage of self-performed work. NAICS 236220 applies (general commercial and institutional building construction); the estimated cost range was $100 million to $250 million for a 42-month performance period.

Place of performance is South Drive, Scott Air Force Base, IL 62225. Ultimate completion date is December 10, 2026. The contract has been modified to include change requests addressing door hardware, elevator and masonry door frames, and OSS, SIPR, and JWICS hardware, with combined increases of $323,279.

Quick answers

Who was awarded contract W912QR22C0002?

W912QR22C0002 was awarded to Korte -River City JV by ENDIST Louisville (US Army Corps of Engineers) on November 10, 2021.

How much is contract W912QR22C0002 worth?

The government has obligated $149,771,384 on W912QR22C0002. Its current value, with exercised options, is $150,070,681. Its potential value, with all options, is $164,505,764.

Was contract W912QR22C0002 competed?

The extent of competition for W912QR22C0002 was full and open competition. The government received 2 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award